Residential / Group Housing · 2 buildings · 110 unitsRERA P52100045498

Amaara

Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 98% of its units are booked.

Ravet, Pune 411044 · Property rates in Ravet · Promoter: M2b Infra LLP

Delivery1 yr 4 mo past duePromised Jun 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales98% booked108 of 110 units · as the promoter reported to MahaRERA

Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed

  • This projectRegistered 24 May 2022, completion promised 30 Jun 2025, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100045498
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004549824 May 202230 Jun 202530 Jun 2025M2b Infra LLPProject page
Documents123

1 document held by Deedo, 122 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardCompany Pan Card.pdf · uploaded 9 Apr 2022Source

Legal

  • Legal Title reportFormat A_compressed (2).pdf · uploaded 9 Apr 2022Source
  • Legal Title reportSearch Report (2)_compressed.pdf · uploaded 9 Apr 2022Source
  • Declaration Form BForm B AMAARA.pdf · uploaded 9 Apr 2022Source

Migrated

  • 1 PAN CardCompany Pan Card.pdf · uploaded 9 Apr 2022Source
  • 1 Copy of the legal title reportFormat A_compressed (2).pdf · uploaded 9 Apr 2022Source
  • 2 Copy of the legal title reportSearch Report (2)_compressed.pdf · uploaded 9 Apr 2022Source
Show all 123 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesEncumbrance (3).pdf · uploaded 9 Apr 2022Source
  • 1 Copy of Layout Approval (in case of layout)scan0896_compressed.pdf · uploaded 9 Apr 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentscan0895_compressed.pdf · uploaded 9 Apr 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentscan0894_compressed.pdf · uploaded 9 Apr 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentscan0893_compressed.pdf · uploaded 9 Apr 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement_compressed.pdf · uploaded 9 Apr 2022Source
  • 1 Declaration about Commencement CertificateFormat D (3).pdf · uploaded 9 Apr 2022Source
  • 1 Declaration in FORM BForm B AMAARA.pdf · uploaded 9 Apr 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 9 Apr 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - AAMARA.pdf · uploaded 9 Apr 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200234916487_For_Asset_Based_Search_09_04_2022_14_11_34_115.pdf · uploaded 9 Apr 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)fORM 3_compressed (1).pdf · uploaded 9 Apr 2022Source
  • 1 Proforma of Allotment letterRERA Draft.pdf · uploaded 9 Apr 2022Source
  • 2 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 9 Apr 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)A B Building_Plinth Completed_Form 1.pdf · uploaded 13 Oct 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Amaara_compressed.pdf · uploaded 13 Oct 2022Source
  • 1 Disclosure of sold/ booked inventorySold Undold - Amaara.pdf · uploaded 13 Oct 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Amaara_compressed.pdf · uploaded 13 Oct 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Rohit Infra Form 5 28092022.pdf · uploaded 13 Oct 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Aamara_compressed.pdf · uploaded 3 Jan 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Amaara Engineer Certificate.pdf · uploaded 3 Jan 2023Source
  • 2 Disclosure of sold/ booked inventorySOLD-UNSOLD INVENTORY AAMARA_compressed.pdf · uploaded 3 Jan 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certifiate Amara_compressed.pdf · uploaded 3 Jan 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Amara F-3.pdf · uploaded 8 May 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Amara F2.pdf · uploaded 13 Jun 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera _ 3 Scan (1).pdf · uploaded 7 Jul 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Asmara having June 2023 NEW.pdf · uploaded 7 Jul 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Asmara having June 2023 NEW.pdf · uploaded 7 Jul 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 24 Jul 2023Source
  • 2 Copy of Layout Approval (in case of layout)HPSC1356_compressed.pdf · uploaded 14 Aug 2023Source
  • 3 Copy of Layout Approval (in case of layout)HPSC1357_compressed.pdf · uploaded 14 Aug 2023Source
  • 4 Copy of Layout Approval (in case of layout)HPSC1358_compressed.pdf · uploaded 14 Aug 2023Source
  • 5 Copy of Layout Approval (in case of layout)HPSC1354_compressed.pdf · uploaded 14 Aug 2023Source
  • 6 Copy of Layout Approval (in case of layout)HPSC1355_compressed.pdf · uploaded 14 Aug 2023Source
  • 7 Copy of Layout Approval (in case of layout)HPSC1353_compressed.pdf · uploaded 14 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentSKM_C250i23041314540_compressed.pdf · uploaded 14 Aug 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Qu sep amaara (1).pdf · uploaded 4 Oct 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 RERA 06102023.pdf · uploaded 25 Nov 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 9 Dec 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)amaara engineer certificate.pdf · uploaded 9 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form 2A.pdf · uploaded 9 Dec 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 .pdf · uploaded 9 Mar 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2 Amaara.pdf · uploaded 20 Apr 2024Source
  • 3 Disclosure of sold/ booked inventoryAdobe Scan Apr 20, 2024.pdf · uploaded 20 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 4 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 4 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 4 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 amara.pdf · uploaded 11 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 amara.pdf · uploaded 11 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 amara.pdf · uploaded 11 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 amara.pdf · uploaded 11 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryScan11042025170722 (1).pdf · uploaded 11 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)A B Building_Plinth Completed_Form 1.pdf · uploaded 23 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Amaara_compressed (1).pdf · uploaded 23 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certifiate Amara_compressed.pdf · uploaded 23 Apr 2025Source
  • Form 2A (FY 2022-2023)Form 2A 2022-23.pdf · uploaded 25 Aug 2025Source
  • Form 2A (FY 2023-2024)Form 2A 2023-24.pdf · uploaded 25 Aug 2025Source
  • Form 2A (FY 2024-2025)Form 2A 2024-25.pdf · uploaded 25 Aug 2025Source
  • Form 1Form 1 (9) (1).pdf · uploaded 9 May 2026Source
  • Form 2Form 2 (6) (1).pdf · uploaded 9 May 2026Source
  • Form 3Form 3 (8) (1).pdf · uploaded 9 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold (7) (1).pdf · uploaded 9 May 2026Source
  • Form 1Form 1 (10) (1).pdf · uploaded 9 May 2026Source
  • Form 2Form 2 (7) (1).pdf · uploaded 9 May 2026Source
  • Form 3Form 3 (9) (1).pdf · uploaded 9 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold (8).pdf · uploaded 9 May 2026Source
  • Form 1Form 1 Jun 2022.pdf · uploaded 5 Jun 2026Source
  • Form 2AMAARA june 22 Form 2.pdf · uploaded 5 Jun 2026Source
  • Form 3Form 3 Jun 2022.pdf · uploaded 5 Jun 2026Source
  • Disclosure of Sold and Booked InventoryJun-2022 Amaara Sold-Unsold Inventories.pdf · uploaded 5 Jun 2026Source
  • Form 1Form 1 March 2023.pdf · uploaded 5 Jun 2026Source
  • Form 2March 2023 Form 2 Signed.pdf · uploaded 5 Jun 2026Source
  • Form 3March 2023 Form 3.pdf · uploaded 5 Jun 2026Source
  • Disclosure of Sold and Booked InventoryMarch-2023 Amaara Sold-Unsold Inventories (1).pdf · uploaded 5 Jun 2026Source
  • Form 1Form 1 Jun 2022.pdf · uploaded 5 Jun 2026Source
  • Form 2AMAARA june 22 Form 2.pdf · uploaded 5 Jun 2026Source
  • Form 3Form 3 Jun 2022.pdf · uploaded 5 Jun 2026Source
  • Disclosure of Sold and Booked InventoryJun-2022 Amaara Sold-Unsold Inventories.pdf · uploaded 5 Jun 2026Source
  • Form 1Sep 2023 Form 1.pdf · uploaded 5 Jun 2026Source
  • Form 2Sep 2023 Form 2 Signed.pdf · uploaded 5 Jun 2026Source
  • Form 3Sep 2023 Form 3.pdf · uploaded 5 Jun 2026Source
  • Disclosure of Sold and Booked InventorySept-2023 Amaara Sold-Unsold Inventories.pdf · uploaded 5 Jun 2026Source
  • Form 1March 2024 Form 1.pdf · uploaded 5 Jun 2026Source
  • Form 2March 2024 Form 2 Signed.pdf · uploaded 5 Jun 2026Source
  • Form 3Form 3 March 2024.pdf · uploaded 5 Jun 2026Source
  • Disclosure of Sold and Booked InventoryMarch 2024 Sold Unsold.pdf · uploaded 5 Jun 2026Source
  • Form 1Jun 2024 Form 1 (1).pdf · uploaded 5 Jun 2026Source
  • Form 2Jun 2024 Form 2 Amaara.pdf · uploaded 5 Jun 2026Source
  • Form 3Form 3 Jun 2024.pdf · uploaded 5 Jun 2026Source
  • Disclosure of Sold and Booked InventoryJune-2024 Amaara Sold-Unsold Inventories (1).pdf · uploaded 5 Jun 2026Source
  • Form 1Dec 2024 Form 1.pdf · uploaded 5 Jun 2026Source
  • Form 2Dec 2024 Form 2.pdf · uploaded 5 Jun 2026Source
  • Form 3Dec 2024 Form 3.pdf · uploaded 5 Jun 2026Source
  • Disclosure of Sold and Booked InventoryDec-2024 Amaara Sold-Unsold Inventories (1).pdf · uploaded 5 Jun 2026Source
  • Form 1Form 1 MAin Sep 22.pdf · uploaded 10 Jun 2026Source
  • Form 2Sep 2022 Form 2 Signed.pdf · uploaded 10 Jun 2026Source
  • Form 3Sep 2022 Form 3 (1).pdf · uploaded 10 Jun 2026Source
  • Disclosure of Sold and Booked InventorySep 2022 Sold Unsold.pdf · uploaded 10 Jun 2026Source

Technical

  • Documentscan0896_compressed.pdf · uploaded 9 Apr 2022Source
  • Documentscan0895_compressed.pdf · uploaded 9 Apr 2022Source
  • Documentscan0894_compressed.pdf · uploaded 9 Apr 2022Source
  • Documentscan0893_compressed.pdf · uploaded 9 Apr 2022Source
  • DocumentHPSC1356_compressed.pdf · uploaded 14 Aug 2023Source
  • DocumentHPSC1357_compressed.pdf · uploaded 14 Aug 2023Source
  • DocumentHPSC1358_compressed.pdf · uploaded 14 Aug 2023Source
  • DocumentHPSC1354_compressed.pdf · uploaded 14 Aug 2023Source
  • DocumentHPSC1355_compressed.pdf · uploaded 14 Aug 2023Source
  • DocumentHPSC1353_compressed.pdf · uploaded 14 Aug 2023Source

Technical (Architect)

  • DocumentForm1 .pdf · uploaded 9 Mar 2024Source
  • DocumentForm 1.pdf · uploaded 4 Jan 2025Source
  • Documentform 1 amara.pdf · uploaded 11 Apr 2025Source
  • DocumentA B Building_Plinth Completed_Form 1.pdf · uploaded 23 Apr 2025Source

Technical (Engineer)

  • DocumentForm2 Amaara.pdf · uploaded 20 Apr 2024Source
  • DocumentForm 2.pdf · uploaded 4 Jan 2025Source
  • Documentform 2 amara.pdf · uploaded 11 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSURVEY NO 86/3/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK110 units in all
Address
Survey No 86/3/2, Ravet, RavetPIN 411044
Village
Ravet, Haveli taluka
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

SURVEY NO 86/3/2

Boundaries

North
By Land Bearing S No 86 2
South
By Land Bearing S No 86 3 1 A
East
By Land Bearing S No 88
West
By Land Out S No 86 3 1

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking110 units

108 of 110 units booked (98%), as the promoter reported to MahaRERA

2BHK · 78 units3BHK · 32 units
BuildingTypeCarpet areaUnitsBooked
A Building2BHK56.74 sq m · 611 sq ft11
A Building2BHK56.74 sq m · 611 sq ft77
A Building2BHK61.95 sq m · 667 sq ft88
A Building2BHK62.11 sq m · 669 sq ft77
A Building2BHK63.89 sq m · 688 sq ft1616
A Building3BHK74.63 sq m · 803 sq ft77
A Building3BHK74.63 sq m · 803 sq ft10
A Building3BHK78.22 sq m · 842 sq ft88
Show all 15 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
B Building2BHK56.74 sq m · 611 sq ft87
B Building2BHK61.95 sq m · 667 sq ft88
B Building2BHK62.11 sq m · 669 sq ft77
B Building2BHK63.89 sq m · 688 sq ft1616
B Building3BHK74.63 sq m · 803 sq ft77
B Building3BHK74.63 sq m · 803 sq ft11
B Building3BHK78.22 sq m · 842 sq ft88

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMg Architects—
Chartered accountantCa Pahlani And Associates—
EngineerDagdu Surnar—
EngineerMr Rajeshwar Karanjikar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology