Skip to content
Residential / Group Housing · 1 building · 27 unitsRERA PR1260002400068

Laxminarayan

Deedo IDDP-PUN-PJ3C

Completion was pushed back 4 months, to Nov 2027; no MahaRERA orders on record; 11% of its units are booked.

Pune City, Maharashtra 411009 · by Issued to MADKAR CONSTRUCTIONS PRIVATE LIMITED, Madkar Constructions Private Limited

DeliveryExtended 4 moPromised Jul 2027 · now due Nov 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales11% booked3 of 27 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Nov 2027

  • This projectRegistered 8 Oct 2024, completion promised 31 Jul 2027, revised to 30 Nov 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1260002400068
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR12600024000688 Oct 202431 Jul 202730 Nov 2027Madkar Constructions Private LimitedProject page
Documents37

1 document held by Deedo, 36 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card1pancardMCPL.pdf · uploaded 5 Sep 2024Source

Legal

  • OthersLease deed.PDF · uploaded 3 Sep 2024Source
  • Declaration Form BTITLE REPORT.pdf · uploaded 3 Sep 2024Source
  • Declaration Form BFORM B BUILDER.pdf · uploaded 3 Sep 2024Source
  • OthersShivprasad Soc NOC.PDF · uploaded 5 Sep 2024Source
  • OthersTITLE REPORT.pdf · uploaded 5 Sep 2024Source
  • OthersDeclaration Financial and Legal Encumbrances.pdf · uploaded 5 Sep 2024Source
Show all 37 documentsShow fewer documents

Legal

  • OthersPOA Laxminarayan project_.pdf · uploaded 13 Sep 2024Source

Migrated

  • Form 1Form -1 Laxminaryan June2025.PDF · uploaded 19 Jul 2025Source
  • Form 2Form -2 Laxminaryan June2025.PDF · uploaded 19 Jul 2025Source
  • Form 3Laxminarayan Signed form 3.pdf · uploaded 19 Jul 2025Source
  • Disclosure of Sold and Booked InventoryUnsold inventory Laxminarayan.PDF · uploaded 19 Jul 2025Source
  • Self-declaration of Quarterly ProgressQPR Laxminarayan.PDF · uploaded 19 Jul 2025Source
  • Form 5 (FY 2024-2025)Form 5 Laxminarayan.PDF · uploaded 29 Sep 2025Source
  • Form 3Laxminarayan Form 3.pdf · uploaded 19 Oct 2025Source
  • Form 1Form 1.PDF · uploaded 19 Oct 2025Source
  • Form 2Form 2.PDF · uploaded 19 Oct 2025Source
  • Disclosure of Sold and Booked InventoryUnsold Inventory.PDF · uploaded 19 Oct 2025Source
  • Form 1Form 1.PDF · uploaded 20 Jan 2026Source
  • Form 2Form 2.PDF · uploaded 20 Jan 2026Source
  • Form 3laxminarayan form 3 (2).pdf · uploaded 20 Jan 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold inventory.PDF · uploaded 20 Jan 2026Source
  • Form 1Laxminarayan FORM 1.PDF · uploaded 20 Apr 2026Source
  • Form 2Laxminarayan FORM 2.PDF · uploaded 20 Apr 2026Source
  • Form 3Laxminarayan Signed Form 3 31MAr 2026.pdf · uploaded 20 Apr 2026Source
  • Disclosure of Sold and Booked InventoryUNSOLD INVENTORY.PDF · uploaded 20 Apr 2026Source
  • Form 3Signed Form 3 Laxminarayan 30 June 2026.pdf · uploaded 20 Jul 2026Source
  • Form 1FORM 1.PDF · uploaded 20 Jul 2026Source
  • Form 2FORM 2.PDF · uploaded 20 Jul 2026Source
  • Disclosure of Sold and Booked InventoryUnsold Inventory.PDF · uploaded 20 Jul 2026Source
  • Form 5 (FY 2025-2026)Form5 Laxminarayan signed.pdf · uploaded 23 Aug 2026Source
  • Form 2A (FY 2025-2026)00 Form 2A Madkar.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentSanction Plan.pdf · uploaded 4 Sep 2024Source
  • Annexure-A as per order 50/2024Annexure A.pdf · uploaded 4 Sep 2024Source

Technical (Architect)

  • Documentform 1 signed 7-9-24.pdf · uploaded 13 Sep 2024Source

Technical (Engineer)

  • DocumentForm 2 signed.pdf · uploaded 13 Sep 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S.No. 130A CTS Number 259B/8 Hissa No. 1A FP No 581 P. No. 8 at S NO. 130A CTS NO. 259B/8 HISSA NO. 1A FP NO. 581 PLOT NO. 8

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—27 units in all
Address
S No. 130a Cts No. 259b/8 Hissa No. 1a Fp No. 581 Plot No. 8, Parvati, PanmalaPIN 411009
Village
Pune (M Corp.), Pune City taluka
Land area for this project
513 sq m (5,526 sq ft)
Permissible built-up area
1,849 sq m (19,903 sq ft)
Sanctioned built-up area
1,840 sq m (19,806 sq ft)
Designated bank account
119
Developed in phases
No

Survey, CTS, gat or plot numbers

S.No. 130A CTS Number 259B/8 Hissa No. 1A FP No 581 P. No. 8 at S NO. 130A CTS NO. 259B/8 HISSA NO. 1A FP NO. 581 PLOT NO. 8

Land as published on MahaRERA's project page

S.No. 130A CTS Number 259B/8 Hissa No. 1A FP No 581 P. No. 8

Boundaries

North
Plot No 7 Of Rajendra Sathe
South
Plot No 9 Of Smt Kusum Shinde
East
Part Of Plot No 14 And 15
West
By Road And Thereafter Bank Of India Colony

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking27 units

27 units registered

— · 27 units
TypeCarpet areaUnits
——27

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantAshish Awati—
EngineerMoreshwar Dhage—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology