Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 58% of its units are booked.
Punawale, Pune 411033 · Promoter: Mr Vijay Kishin Matani
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 27 Jun 2023, completion promised 31 Dec 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100051626
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100051626 | 27 Jun 2023 | 31 Dec 2025 | 31 Dec 2025 | Mr Vijay Kishin Matani | Project page |
Documents65
1 document held by Deedo, 64 filings listed on MahaRERA's project page
Show all 65 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportFormat A 22 8.pdf · uploaded 14 Jan 2023Source
- 2 Copy of the legal title reportSearch Report 22 8.pdf · uploaded 14 Jan 2023Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance - Sai Grace.pdf · uploaded 14 Jan 2023Source
- 1 b Details of encumbrances concerned to LegalEncumbrance - Sai Grace.pdf · uploaded 14 Jan 2023Source
- 1 Copy of Layout Approval (in case of layout)liladar00012.pdf · uploaded 14 Jan 2023Source
- 1 Declaration in FORM BForm B - Sai Grace.pdf · uploaded 14 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 (1).pdf · uploaded 14 Jan 2023Source
- 1 Proforma of Allotment letterSai grace - Model of AL.pdf · uploaded 14 Jan 2023Source
- 1 Proforma of Agreement for saleRra Draft (1).pdf · uploaded 14 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSai grace- Format A bank.pdf · uploaded 14 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterSai grace - devition of AL.pdf · uploaded 14 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementSai grace - Deviation of AFS.pdf · uploaded 14 Jan 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200257671754_For_Asset_Based_Search_16_01_2023_17_46_41_470.pdf · uploaded 16 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentIOD Letter Punawale 22 8.pdf · uploaded 18 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Adobe Scan 14 Jun 2023 (1)_compressed.pdf · uploaded 18 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDocScanner Jan 18, 2023 11-23 AM-1.pdf · uploaded 18 Jan 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentkop013_compressed.pdf · uploaded 23 Feb 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentkop014_compressed.pdf · uploaded 23 Feb 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentkop015_compressed.pdf · uploaded 23 Feb 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentkop017_compressed.pdf · uploaded 23 Feb 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentrevise cc.pdf · uploaded 23 Feb 2023Source
- 1 Declaration about Commencement CertificatePDF Declaration SSD Infra (1).pdf · uploaded 1 Mar 2023Source
- 1 Other – FinanceDeclaration for amenities.pdf · uploaded 9 Jun 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sai Grace_11zon.pdf · uploaded 19 Oct 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)sai grace Qu october 23.pdf · uploaded 19 Oct 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)arch cert.pdf · uploaded 12 Jan 2024Source
- 1 Disclosure of sold/ booked inventorySai Grace Sold Unsold Flat.pdf · uploaded 12 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Declaration Nill Wthdrawal Sai Grace.pdf · uploaded 12 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Sai Grace.pdf · uploaded 15 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 15 Apr 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM2.pdf · uploaded 15 Apr 2024Source
- 2 Disclosure of sold/ booked inventorystatement.pdf · uploaded 15 Apr 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sai Grace_0001.pdf · uploaded 15 Apr 2024Source
- 2 Declaration about Commencement CertificateComencement Certificate.pdf · uploaded 29 Apr 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)form3.pdf · uploaded 29 Apr 2024Source
- 1 Other – Legalform a.pdf · uploaded 29 Apr 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 18 Jul 2024Source
- 3 Disclosure of sold/ booked inventorySTATEMENT.pdf · uploaded 18 Jul 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 18 Jul 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 20 Jul 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3-compressed (2).pdf · uploaded 23 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SSD INFRA_0001.pdf · uploaded 23 Oct 2024Source
- 1 Disclosure of sold/ booked inventorySTATEMENT.pdf · uploaded 23 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 23 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 24 Oct 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentcompletion cert.pdf · uploaded 6 Jan 2025Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 7 Jan 2025Source
Technical
- Documentliladar00012.pdf · uploaded 14 Jan 2023Source
- DocumentIOD Letter Punawale 22 8.pdf · uploaded 18 Jan 2023Source
- Documentkop017_compressed.pdf · uploaded 23 Feb 2023Source
- Documentkop013_compressed.pdf · uploaded 23 Feb 2023Source
- Documentkop014_compressed.pdf · uploaded 23 Feb 2023Source
- Documentkop015_compressed.pdf · uploaded 23 Feb 2023Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSr No 22/8 P Poonwale
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK110 units in all
- Address
- Sr No 22/8 P Poonwale, Punawale, PunawalePIN 411033
- Village
- Punawale, Mulshi taluka
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- By Prop of Mr Manohar Kate
- South
- By Punavale Tathwade Shiv
- East
- By Prop of Mr Chandrakant Kate Mr Ankush Kate
- West
- By Prop of Nathu Waghire
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking110 units
64 of 110 units booked (58%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 53.89 sq m · 580 sq ft | 28 | 19 |
| 2BHK | 54.49 sq m · 587 sq ft | 27 | 15 |
| 2BHK | 58.03 sq m · 625 sq ft | 35 | 24 |
| 2BHK | 58.31 sq m · 628 sq ft | 20 | 6 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar N D Joshi | — |
| Chartered accountant | Azam Mulani | — |
| Chartered accountant | CA Pravin Pise and Assocites | — |
| Chartered accountant | Ca Rinkesh Gupta | — |
| Engineer | Mr Anil Pradhan | — |