Residential / Group Housing · 10 buildings · 717 unitsRERA P52100004281 +1

Eela

Deedo IDDP-PUN-A81B

Completion was pushed back 1 year to Dec 2021, and that date has passed too; no MahaRERA orders on record; 94% of its units are booked.

Punawale, Pune 411033 · Promoter: M/s. Siddhashila Developers

Delivery5 yrs 10 mo latePromised Dec 2020 · revised Dec 2021 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales94% booked675 of 717 units · as the promoter reported to MahaRERA
Eela project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 1 year to Dec 2021, and that date has passed too

  • P52100004281Registered 9 Aug 2017, completion promised 30 Dec 2020, revised to 30 Dec 2021, and still not shown completed today.
  • P52100012382Registered 1 Sep 2017, completion promised 31 Dec 2018, revised to 31 Dec 2019, and still not shown completed today.

2 extension certificates on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

10 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000042819 Aug 201730 Dec 202030 Dec 2021M/s. Siddhashila DevelopersProject page
P521000123821 Sep 201731 Dec 201831 Dec 2019M/s. Siddhashila DevelopersProject page
Documents88

4 documents held by Deedo, 84 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP52100004281 · 9 Aug 2017ViewSource
  • Registration certificateP52100012382 · 1 Sep 2017ViewSource

Extension certificate (2)

  • Extension certificateP52100012382 · 15 Feb 2019ViewSource
  • Extension certificateP52100004281 · 9 Sep 2021ViewSource

Finance

  • PAN CardP52100004281 · PAN_ Siddhashila Developers.pdf · uploaded 28 Jul 2017Source
  • PAN CardP52100012382 · PAN_ Siddhashila Developers.pdf · uploaded 28 Jul 2017Source

Legal

  • Legal Title reportP52100004281 · Title Report.pdf · uploaded 28 Jul 2017Source
  • Declaration Form BP52100004281 · Declaration SD (Phase 02).pdf · uploaded 28 Jul 2017Source
Show all 88 documentsShow fewer documents

Legal

  • Legal Title reportP52100012382 · Title Report.pdf · uploaded 28 Jul 2017Source
  • Declaration Form BP52100012382 · Declaration SD (Phase 01).pdf · uploaded 28 Jul 2017Source
  • OtherP52100012382 · Madhuban J-Building Completion Certificate.pdf · uploaded 25 Jul 2019Source
  • OtherP52100012382 · Completion Phase -I.pdf · uploaded 25 Jul 2019Source

Migrated

  • 1 PAN CardP52100004281 · PAN_ Siddhashila Developers.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of the legal title reportP52100004281 · Title Report.pdf · uploaded 28 Jul 2017Source
  • 1 Details of encumbrancesP52100004281 · Mortgage Deed Index II.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P52100004281 · Layout plan Copy 31-3-2017.pdf · uploaded 28 Jul 2017Source
  • 1 Building Plan Approval (IOD)P52100004281 · Layout plan Copy 31-3-2017.pdf · uploaded 28 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100004281 · Commencement Certificate.pdf · uploaded 28 Jul 2017Source
  • 1 Declaration in FORM BP52100004281 · Declaration SD (Phase 02).pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100004281 · Architect Certificate Phase-II.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100004281 · Engg Certificate PH-II.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 3)P52100004281 · CA Certificate Phase II.pdf · uploaded 28 Jul 2017Source
  • 1 Proforma of Allotment letterP52100004281 · Agreement For Sale Phase-II Eela PDF.pdf · uploaded 28 Jul 2017Source
  • 2 Proforma of Allotment letterP52100004281 · Booking Form.pdf · uploaded 28 Jul 2017Source
  • 1 PAN CardP52100012382 · PAN_ Siddhashila Developers.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of the legal title reportP52100012382 · Title Report.pdf · uploaded 28 Jul 2017Source
  • 1 Details of encumbrancesP52100012382 · Mortgage Deed Index II.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P52100012382 · Layout plan Copy 31-3-2017-ilovepdf-compressed.pdf · uploaded 28 Jul 2017Source
  • 1 Building Plan Approval (IOD)P52100012382 · Layout plan Copy 31-3-2017.pdf · uploaded 28 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100012382 · Commencement Certificate.pdf · uploaded 28 Jul 2017Source
  • 1 Declaration in FORM BP52100012382 · Declaration SD (Phase 01).pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100012382 · Architect Certificate Phase-I.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100012382 · Engg Certificate PH-I.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 3)P52100012382 · CA Certificate Phase I.pdf · uploaded 28 Jul 2017Source
  • 1 Proforma of Allotment letterP52100012382 · Agreement For Sale Phase-I Eela PDF.pdf · uploaded 28 Jul 2017Source
  • 2 Proforma of Allotment letterP52100012382 · Booking Form.pdf · uploaded 28 Jul 2017Source
  • 2 Building Plan Approval (IOD)P52100004281 · Plan1-38.pdf · uploaded 18 Dec 2017Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100004281 · eela new CC.pdf · uploaded 18 Dec 2017Source
  • 2 Building Plan Approval (IOD)P52100012382 · Plan1-38.pdf · uploaded 18 Dec 2017Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100012382 · eela new CC.pdf · uploaded 18 Dec 2017Source
  • 3 Proforma of Allotment letterP52100004281 · RERA Agreement Phase II-.pdf · uploaded 20 Dec 2017Source
  • 3 Proforma of Allotment letterP52100012382 · RERA Agreement Phase I-.pdf · uploaded 20 Dec 2017Source
  • 1 Certificates of CA (Form 5)P52100004281 · Form 5 - Phase II.pdf · uploaded 7 Jan 2019Source
  • 1 Certificates of CA (Form 5)P52100012382 · Form 5 - Phase I.pdf · uploaded 7 Jan 2019Source
  • 1 OtherP52100012382 · Madhuban J-Building Completion Certificate.pdf · uploaded 25 Jul 2019Source
  • 2 OtherP52100012382 · Completion Phase -I.pdf · uploaded 25 Jul 2019Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100012382 · Society Certificate ATIRA.pdf · uploaded 15 Oct 2019Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)P52100012382 · Society Certificate GAYA.pdf · uploaded 15 Oct 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A)P52100012382 · SCAN_20190822_122545184_compressed.pdf · uploaded 21 Oct 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100004281 · Form 5 Phase II.pdf · uploaded 30 Nov 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100012382 · Form 5 Phase I.pdf · uploaded 30 Nov 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100012382 · Part Completion Phase 1.pdf · uploaded 30 Dec 2019Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100012382 · Completion Certificate of K - Parking Building.pdf · uploaded 30 Dec 2019Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)P52100012382 · COMPLETION-CERTIFICATE-080219.PDF · uploaded 1 Jan 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100004281 · SCAN_20200114_172304413_compressed.pdf · uploaded 14 Jan 2020Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A)P52100012382 · SCAN_20200114_173020626_compressed.pdf · uploaded 14 Jan 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100004281 · Quality Assurance Certificate 27-03-21 Phase-II_compressed.pdf · uploaded 6 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100004281 · Quality Assurance Certificate 29-06-21 Phase-II_compressed.pdf · uploaded 6 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100004281 · Form 5 - Phase II 2019-20.pdf · uploaded 6 Aug 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100004281 · Completion Certificate of E F.pdf · uploaded 6 Aug 2021Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100004281 · Completion Certificate of G H.pdf · uploaded 6 Aug 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100004281 · Terra Society Certificate_compressed.pdf · uploaded 6 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100012382 · Quality Assurance Certificate 27-03-21 Phase-I_compressed.pdf · uploaded 6 Aug 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100012382 · Quality Assurance Certificate 29-06-21 Phase-I_compressed.pdf · uploaded 6 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100012382 · Form 5 - Phase I 2019-20.pdf · uploaded 6 Aug 2021Source
  • 1 Declaration about Commencement CertificateP52100004281 · SCAN_20210813_124449710.pdf · uploaded 13 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryP52100004281 · Sales Diclaration - E Building.pdf · uploaded 13 Aug 2021Source
  • 2 Disclosure of sold/ booked inventoryP52100004281 · Sales Diclaration - F Building.pdf · uploaded 13 Aug 2021Source
  • 3 Disclosure of sold/ booked inventoryP52100004281 · Sales Diclaration - G Building.pdf · uploaded 13 Aug 2021Source
  • 4 Disclosure of sold/ booked inventoryP52100004281 · Sales Diclaration - H Building.pdf · uploaded 13 Aug 2021Source
  • 1 Declaration about Commencement CertificateP52100012382 · SCAN_20210813_124449710.pdf · uploaded 13 Aug 2021Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)P52100004281 · WhatsApp Image.pdf · uploaded 22 Nov 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100004281 · Form 5 - Phase II - 20-21.pdf · uploaded 21 Dec 2021Source
  • 9 Architect’s Certificate on Completion of Project (Form 4)P52100004281 · 20221215025328.pdf · uploaded 15 Dec 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentP52100004281 · EX NA Order Finel.pdf · uploaded 28 Apr 2023Source
  • 4 Commencement Certificates / NA Order for plotted developmentP52100004281 · N A Order from callecter office.pdf · uploaded 28 Apr 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentP52100012382 · EX NA Order Finel.pdf · uploaded 28 Apr 2023Source
  • 4 Commencement Certificates / NA Order for plotted developmentP52100012382 · N A Order from callecter office.pdf · uploaded 28 Apr 2023Source

Technical

  • DocumentP52100004281 · Layout plan Copy 31-3-2017.pdf · uploaded 28 Jul 2017Source
  • DocumentP52100004281 · Layout plan Copy 31-3-2017.pdf · uploaded 28 Jul 2017Source
  • DocumentP52100012382 · Layout plan Copy 31-3-2017-ilovepdf-compressed.pdf · uploaded 28 Jul 2017Source
  • DocumentP52100012382 · Layout plan Copy 31-3-2017.pdf · uploaded 28 Jul 2017Source
  • DocumentP52100004281 · Plan1-38.pdf · uploaded 18 Dec 2017Source
  • DocumentP52100012382 · Plan1-38.pdf · uploaded 18 Dec 2017Source

Technical (Architect)

  • DocumentP52100004281 · Architect Certificate Phase-II.pdf · uploaded 28 Jul 2017Source
  • DocumentP52100012382 · Architect Certificate Phase-I.pdf · uploaded 28 Jul 2017Source

Technical (Engineer)

  • DocumentP52100004281 · Engg Certificate PH-II.pdf · uploaded 28 Jul 2017Source
  • DocumentP52100012382 · Engg Certificate PH-I.pdf · uploaded 28 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals34/2/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
2
Unit types
1rhk, 2rhk, 3rhk, 1RK, 0717 units in all
Address
34/2/1, Marunji-Punwale Road, PunawalePIN 411033
Village
Punawale, Mulshi taluka
Designated bank account
76
Developed in phases
Yes
Also registered as
EELA Phase-I, EELA Phase-II

Survey, CTS, gat or plot numbers

34/2/1

Boundaries

North
Part of Survey No 34 Hissa 1
South
Survey No 28
East
Marunji Road
West
Part of Survey No 34 Hissa 2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking717 units

675 of 717 units booked (94%), as the promoter reported to MahaRERA

1rhk · 174 units2rhk · 419 units3rhk · 116 units1RK · 8 units0 · 0 units
RERABuildingTypeCarpet areaUnitsBooked
P52100012382A-Building / Atira-A1rhk45.26 sq m · 487 sq ft22
P52100012382A-Building / Atira-A2rhk59.86 sq m · 644 sq ft77
P52100012382A-Building / Atira-A2rhk60.01 sq m · 646 sq ft77
P52100012382A-Building / Atira-A2rhk60.37 sq m · 650 sq ft88
P52100012382A-Building / Atira-A2rhk60.52 sq m · 651 sq ft88
P52100012382A-Building / Atira-A2rhk62.68 sq m · 675 sq ft88
P52100012382A-Building / Atira-A2rhk63.19 sq m · 680 sq ft77
P52100012382A-Building / Atira-A2rhk63.53 sq m · 684 sq ft11
Show all 100 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P52100012382A-Building / Atira-A2rhk66.68 sq m · 718 sq ft11
P52100012382A-Building / Atira-A3rhk84.08 sq m · 905 sq ft76
P52100012382A-Building / Atira-A3rhk84.14 sq m · 906 sq ft88
P52100012382A-Building / Atira-A3rhk84.56 sq m · 910 sq ft66
P52100012382A-Building / Atira-A3rhk84.59 sq m · 911 sq ft77
P52100012382A-Building / Atira-A3rhk84.94 sq m · 914 sq ft11
P52100012382B-Building / Atira-B1rhk45.26 sq m · 487 sq ft21
P52100012382B-Building / Atira-B2rhk59.86 sq m · 644 sq ft77
P52100012382B-Building / Atira-B2rhk60.01 sq m · 646 sq ft77
P52100012382B-Building / Atira-B2rhk60.37 sq m · 650 sq ft88
P52100012382B-Building / Atira-B2rhk60.52 sq m · 651 sq ft88
P52100012382B-Building / Atira-B2rhk62.68 sq m · 675 sq ft88
P52100012382B-Building / Atira-B2rhk63.19 sq m · 680 sq ft77
P52100012382B-Building / Atira-B2rhk63.53 sq m · 684 sq ft11
P52100012382B-Building / Atira-B2rhk66.68 sq m · 718 sq ft11
P52100012382B-Building / Atira-B3rhk84.08 sq m · 905 sq ft77
P52100012382B-Building / Atira-B3rhk84.14 sq m · 906 sq ft88
P52100012382B-Building / Atira-B3rhk84.56 sq m · 910 sq ft66
P52100012382B-Building / Atira-B3rhk84.59 sq m · 911 sq ft77
P52100012382B-Building / Atira-B3rhk84.94 sq m · 914 sq ft11
P52100012382C-Building / Gaia-A1rhk41.2 sq m · 443 sq ft1413
P52100012382C-Building / Gaia-A1rhk41.6 sq m · 448 sq ft1616
P52100012382C-Building / Gaia-A1RK26.6 sq m · 286 sq ft22
P52100012382C-Building / Gaia-A2rhk51.69 sq m · 556 sq ft1616
P52100012382C-Building / Gaia-A2rhk51.89 sq m · 559 sq ft11
P52100012382C-Building / Gaia-A2rhk51.9 sq m · 559 sq ft77
P52100012382C-Building / Gaia-A2rhk51.96 sq m · 559 sq ft1414
P52100012382C-Building / Gaia-A2rhk52.33 sq m · 563 sq ft66
P52100012382C-Building / Gaia-A2rhk52.74 sq m · 568 sq ft22
P52100012382D-Building / Gaia-B1rhk41.2 sq m · 443 sq ft1414
P52100012382D-Building / Gaia-B1rhk41.6 sq m · 448 sq ft1616
P52100012382D-Building / Gaia-B1RK26.6 sq m · 286 sq ft21
P52100012382D-Building / Gaia-B2rhk51.69 sq m · 556 sq ft1616
P52100012382D-Building / Gaia-B2rhk51.89 sq m · 559 sq ft10
P52100012382D-Building / Gaia-B2rhk51.9 sq m · 559 sq ft77
P52100012382D-Building / Gaia-B2rhk51.96 sq m · 559 sq ft1413
P52100012382D-Building / Gaia-B2rhk52.33 sq m · 563 sq ft66
P52100012382D-Building / Gaia-B2rhk52.74 sq m · 568 sq ft22
P52100004281E-Building / Terra-A1rhk36.71 sq m · 395 sq ft88
P52100004281E-Building / Terra-A1rhk36.72 sq m · 395 sq ft77
P52100004281E-Building / Terra-A1rhk37.97 sq m · 409 sq ft77
P52100004281E-Building / Terra-A1rhk38.26 sq m · 412 sq ft88
P52100004281E-Building / Terra-A1RK26.6 sq m · 286 sq ft10
P52100004281E-Building / Terra-A1RK26.91 sq m · 290 sq ft11
P52100004281E-Building / Terra-A2rhk53.21 sq m · 573 sq ft88
P52100004281E-Building / Terra-A2rhk53.51 sq m · 576 sq ft1616
P52100004281E-Building / Terra-A2rhk53.54 sq m · 576 sq ft66
P52100004281E-Building / Terra-A2rhk53.85 sq m · 580 sq ft1414
P52100004281E-Building / Terra-A2rhk54.59 sq m · 588 sq ft20
P52100004281F-Building / Terra-B1rhk36.71 sq m · 395 sq ft88
P52100004281F-Building / Terra-B1rhk36.72 sq m · 395 sq ft77
P52100004281F-Building / Terra-B1rhk37.97 sq m · 409 sq ft77
P52100004281F-Building / Terra-B1rhk38.26 sq m · 412 sq ft88
P52100004281F-Building / Terra-B1RK26.6 sq m · 286 sq ft10
P52100004281F-Building / Terra-B1RK26.91 sq m · 290 sq ft11
P52100004281F-Building / Terra-B2rhk53.21 sq m · 573 sq ft88
P52100004281F-Building / Terra-B2rhk53.51 sq m · 576 sq ft1615
P52100004281F-Building / Terra-B2rhk53.54 sq m · 576 sq ft66
P52100004281F-Building / Terra-B2rhk53.85 sq m · 580 sq ft1414
P52100004281F-Building / Terra-B2rhk54.59 sq m · 588 sq ft21
P52100004281G-Building / Ashira-A1rhk45.26 sq m · 487 sq ft22
P52100004281G-Building / Ashira-A2rhk59.86 sq m · 644 sq ft76
P52100004281G-Building / Ashira-A2rhk60.01 sq m · 646 sq ft77
P52100004281G-Building / Ashira-A2rhk60.37 sq m · 650 sq ft87
P52100004281G-Building / Ashira-A2rhk60.52 sq m · 651 sq ft87
P52100004281G-Building / Ashira-A2rhk62.68 sq m · 675 sq ft88
P52100004281G-Building / Ashira-A2rhk63.19 sq m · 680 sq ft77
P52100004281G-Building / Ashira-A2rhk63.53 sq m · 684 sq ft11
P52100004281G-Building / Ashira-A2rhk66.68 sq m · 718 sq ft11
P52100004281G-Building / Ashira-A3rhk84.08 sq m · 905 sq ft76
P52100004281G-Building / Ashira-A3rhk84.14 sq m · 906 sq ft87
P52100004281G-Building / Ashira-A3rhk84.56 sq m · 910 sq ft65
P52100004281G-Building / Ashira-A3rhk84.59 sq m · 911 sq ft77
P52100004281G-Building / Ashira-A3rhk84.94 sq m · 914 sq ft10
P52100004281H-Building / Ashira-B1rhk45.26 sq m · 487 sq ft21
P52100004281H-Building / Ashira-B2rhk59.86 sq m · 644 sq ft75
P52100004281H-Building / Ashira-B2rhk60.01 sq m · 646 sq ft77
P52100004281H-Building / Ashira-B2rhk60.37 sq m · 650 sq ft87
P52100004281H-Building / Ashira-B2rhk60.52 sq m · 651 sq ft88
P52100004281H-Building / Ashira-B2rhk62.68 sq m · 675 sq ft85
P52100004281H-Building / Ashira-B2rhk63.19 sq m · 680 sq ft76
P52100004281H-Building / Ashira-B2rhk63.53 sq m · 684 sq ft11
P52100004281H-Building / Ashira-B2rhk66.68 sq m · 718 sq ft11
P52100004281H-Building / Ashira-B3rhk84.08 sq m · 905 sq ft77
P52100004281H-Building / Ashira-B3rhk84.14 sq m · 906 sq ft88
P52100004281H-Building / Ashira-B3rhk84.56 sq m · 910 sq ft65
P52100004281H-Building / Ashira-B3rhk84.59 sq m · 911 sq ft77
P52100004281H-Building / Ashira-B3rhk84.94 sq m · 914 sq ft10
P52100012382J-EWS Building / EWS1rhk42.31 sq m · 455 sq ft2421
P52100012382J-EWS Building / EWS1rhk42.37 sq m · 456 sq ft2218
P52100012382J-EWS Building / EWS2rhk47.31 sq m · 509 sq ft4741
P52100012382K-Building / Parking Podium0—00

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectAbhikalpan Architects and Planners—P52100004281
ArchitectAbhikalpan Architects & Planners—P52100012382

Source: MahaRERA project page. Contact details are not shown.