Pushpak Wing B
Deedo IDDP-PUN-6TSAIts promised completion date, Jun 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.
Pimpri Chinchawad (M Corp.), Pune 412105 · by Khushi Enterprises
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jun 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 15 Oct 2021, completion promised 30 Jun 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100031282
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100031282 | 15 Oct 2021 | 30 Jun 2024 | 30 Jun 2024 | Khushi Enterprises | Project page |
Documents31
1 document held by Deedo, 30 filings listed on MahaRERA's project page
Finance
- PAN CardPan card.pdf · uploaded 26 Aug 2021Source
Legal
Show all 31 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCommencment Certificate.pdf · uploaded 26 Aug 2021Source
- 1 Copy of the legal title reportSearch Report_compressed.pdf · uploaded 21 Sep 2021Source
- 2 Copy of the legal title reportDeclaration.pdf · uploaded 21 Sep 2021Source
- 1 Details of encumbrancesNo encumbrances khushi.pdf · uploaded 21 Sep 2021Source
- 1 Declaration about Commencement CertificateKhushi Enterprises.pdf · uploaded 21 Sep 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 21 Sep 2021Source
- 1 Disclosure of sold/ booked inventoryKhushi Sold Unsold.pdf · uploaded 21 Sep 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Khushi Enterprises (Pushpak Wing B) FORM-3.pdf · uploaded 21 Sep 2021Source
- 1 Proforma of Allotment letterPushpak_B Wing_Provisional Allotment Letter.pdf · uploaded 21 Sep 2021Source
- 2 Proforma of Allotment letterPUSHPAK_B Wing_Flat Agreement_RERA_20-09-21_PART I.pdf · uploaded 21 Sep 2021Source
- 3 Proforma of Allotment letterPUSHPAK_B Wing_Flat Agreement_RERA_20-09-21_PART II.pdf · uploaded 21 Sep 2021Source
- 1 Declaration in FORM BForm B Promoter.pdf · uploaded 9 Oct 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 10 Dec 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 10 Dec 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION CERTIFICATE B WING.pdf · uploaded 10 Dec 2022Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 10 Dec 2022Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY CERTIFICATE.pdf · uploaded 10 Dec 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 21-22.pdf · uploaded 28 Jan 2023Source
- 1 Status of Conveyanceconveyance deed.pdf · uploaded 5 Jul 2024Source
Technical
Technical (Architect)
- DocumentFORM 1.pdf · uploaded 10 Dec 2022Source
Technical (Engineer)
- DocumentFORM 2.pdf · uploaded 10 Dec 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel GAT NUMBER 105
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK14 units in all
- Address
- Gat Number 105, Dudulgaon, Gat Number - 105, Moshi Alandi Road., DudulgaonPIN 412105
- Village
- Pimpri Chinchawad (M Corp.), Haveli taluka
- Designated bank account
- 220
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Survey Number 108
- South
- 30 Meter Wide D P Road
- East
- By A Property Of Mr Talekar
- West
- Survey Number 105 And 106
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking14 units
14 of 14 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 60.31 sq m · 649 sq ft | 14 | 14 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Kimaya Associates | — |
| Chartered accountant | Vinit D Achha And Associates | — |
| Engineer | Hemant Nimkar | — |
Source: MahaRERA project page. Contact details are not shown.