2 projects under 2 MahaRERA registrations, registered 2017–2017. None has an extended completion date on record.

2RERA projects
2Registrations
2Completion still due0 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172

Projects in Pasure

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Bougain Villa - Cluster 1Synergy PropertiesP5210001190231 Aug 201731 Dec 2031—Not yet due0
Bougain Villa - Cluster 3Synergy PropertiesP5210000905819 Aug 201731 Dec 2031—Not yet due0

Other localities in Bhor

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Synergy Properties2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology