Selena B
Deedo IDDP-PUN-7F9VIts promised completion date, Mar 2019, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 50% of its units are booked.
Pashan, Pune 411021 · Property rates in Pashan · Promoter: Kumar Construction and Properties Pvt Ltd
Its promised completion date, Mar 2019, has passed and MahaRERA does not show it completed
- This projectRegistered 10 Jul 2017, completion promised 30 Mar 2019, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100000252
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100000252 | 10 Jul 2017 | 30 Mar 2019 | 30 Mar 2019 | Kumar Construction and Properties Pvt Ltd | Project page |
Documents29
1 document held by Deedo, 28 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Card.PDF · uploaded 17 May 2017Source
Legal
Show all 29 documentsShow fewer documents
Migrated
- 1 Building Plan Approval (IOD)SELENA BLDG B.pdf · uploaded 19 May 2017Source
- 1 Details of encumbrancesMortgage Deed.pdf · uploaded 3 Jun 2017Source
- 1 Copy of the legal title reportSELENA TITLE-compressed (1).pdf · uploaded 21 Jun 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)SELENA B Engineer certificate.pdf · uploaded 26 Jun 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Selena B Architect Certificate.pdf · uploaded 27 Jun 2017Source
- 1 Certificates of CA (Form 3)SELENA B - CA CERTIFICATE.pdf · uploaded 28 Jun 2017Source
- 1 Proforma of Allotment letterPROFORMA.pdf · uploaded 29 Jun 2017Source
- 1 Declaration in FORM BSELENA FORM B-compressed.pdf · uploaded 4 Jul 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)1ST QUARTER ARCH CERT.pdf · uploaded 18 Oct 2017Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)IST QUARTER ENGG CERT.pdf · uploaded 18 Oct 2017Source
- 2 Certificates of CA (Form 3)1SR QUARTER CA CERT.pdf · uploaded 18 Oct 2017Source
- 1 Certificates of CA (Form 5)Selena FORM 5.pdf · uploaded 15 Oct 2018Source
- 1 OtherKUMAR SELEN B BUILDING OCCUPANCY CERTIFICATE.PDF · uploaded 9 Jul 2019Source
- 2 Certificates of CA (Form 5)Form 5 Selena B.pdf · uploaded 30 Sep 2019Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)KUMAR SELENA.pdf · uploaded 1 Aug 2020Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentKUMAR SELEN B BUILDING OCCUPANCY CERTIFICATE.PDF · uploaded 2 Sep 2020Source
- 2 Architect’s Certificate on Completion of Project (Form 4)SELENA B FORM 4.pdf · uploaded 2 Sep 2020Source
Technical
Technical (Architect)
- Document1ST QUARTER ARCH CERT.pdf · uploaded 18 Oct 2017Source
Technical (Engineer)
- DocumentIST QUARTER ENGG CERT.pdf · uploaded 18 Oct 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals135 PLOT A
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 4.5 BHK, 4.5BHK22 units in all
- Address
- 135 Plot APIN 411021
- Village
- Pashan, Haveli taluka
- Location
- 18.54928, 73.79309
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 135 1 Part
- South
- S No 136
- East
- Building A
- West
- Open Space
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking22 units
11 of 22 units booked (50%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 4.5 BHK | 147.24 sq m · 1,585 sq ft | 10 | 5 |
| 4.5BHK | 147.09 sq m · 1,583 sq ft | 10 | 5 |
| 4.5BHK | 152.33 sq m · 1,640 sq ft | 2 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vikas Achalkar | — |
| Engineer | Sunil Mutalik | — |
| Registered real estate agent | Prafulla Vivek Vaidya | — |
| Registered real estate agent | Ronisun Knowledge Application Center | — |
Source: MahaRERA project page. Contact details are not shown.