Deedo IDDP-PUN-VSXTIts promised completion date, Mar 2022, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Parvati, Pune 411009 · Promoter: Citadel Landmarks
Its promised completion date, Mar 2022, has passed and MahaRERA does not show it completed
- This projectRegistered 5 Sep 2019, completion promised 30 Mar 2022, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100022237
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100022237 | 5 Sep 2019 | 30 Mar 2022 | 30 Mar 2022 | Citadel Landmarks | Project page |
Documents28
1 document held by Deedo, 27 filings listed on MahaRERA's project page
Finance
- PAN CardCitadel PAN.pdf · uploaded 28 Aug 2019Source
Legal
Show all 28 documentsShow fewer documents
Migrated
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECTS CERTIFICATE FORM 1_compressed.pdf · uploaded 28 Aug 2019Source
- 1 Status of ConveyanceDevelopment Agreement (Compressed).pdf · uploaded 28 Aug 2019Source
- 1 OtherPower of Attorney (Compressed).pdf · uploaded 28 Aug 2019Source
- 1 Declaration in FORM BForm B (Compressed).pdf · uploaded 29 Aug 2019Source
- 1 Copy of Layout Approval (in case of layout)Not Applicable.pdf · uploaded 30 Aug 2019Source
- 1 Building Plan Approval / NA Order for plotted developmentSanctioned Plan (Page 1) (Compressed).pdf · uploaded 30 Aug 2019Source
- 2 Building Plan Approval / NA Order for plotted developmentSanctioned Plan (Page 2) (Compressed).pdf · uploaded 30 Aug 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate (Compressed).pdf · uploaded 30 Aug 2019Source
- 1 Engineers Certificate on Quality Assurance (Form 2A)FORM 2A - Site Engineer.pdf · uploaded 30 Aug 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - CA Certificate (Compressed).pdf · uploaded 30 Aug 2019Source
- 1 Proforma of Allotment letterNew Flat Purchaser Agreement.pdf · uploaded 30 Aug 2019Source
- 3 Building Plan Approval / NA Order for plotted developmentPage 1.pdf · uploaded 15 Jul 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentPage 2.pdf · uploaded 15 Jul 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate (Compressed).pdf · uploaded 15 Jul 2022Source
Technical
- DocumentNot Applicable.pdf · uploaded 30 Aug 2019Source
- DocumentSanctioned Plan (Page 1) (Compressed).pdf · uploaded 30 Aug 2019Source
- DocumentSanctioned Plan (Page 2) (Compressed).pdf · uploaded 30 Aug 2019Source
- DocumentPage 1.pdf · uploaded 15 Jul 2022Source
- DocumentPage 2.pdf · uploaded 15 Jul 2022Source
Technical (Architect)
- DocumentARCHITECTS CERTIFICATE FORM 1_compressed.pdf · uploaded 28 Aug 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals52, 53A
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, Office space, Shop9 units in all
- Address
- Plot No. 94/2, CTS 3669, Sr. No.50, 52, 53A, Plot No. 94/2, CTS 3669, Walvekar Nagar, ParvatiPIN 411009
- Village
- Parvati, Haveli taluka
- Location
- 18.48233, 73.85691
- Designated bank account
- 171
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Colony Road
- South
- Plot no 94-1 of CTS 3669
- East
- Pune - Satara Road
- West
- Shubhashri on Plot 94-2
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking9 units
0 of 9 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 76.74 sq m · 826 sq ft | 3 | 0 |
| 1BHK | 78.91 sq m · 849 sq ft | 3 | 0 |
| Office space | 76.74 sq m · 826 sq ft | 1 | 0 |
| Office space | 78.91 sq m · 849 sq ft | 1 | 0 |
| Shop | 158.3 sq m · 1,704 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Masterstroke Architects And Interior Designers | — |
| Chartered accountant | Shyam I Davawala | — |
| Engineer | Santosh Anandrao Patil | — |
| Other | Sunil Mutalik & Associates | — |