Extended 4 mo6 floors · 12 flatsRERA PR1260002501285
Main building, Uma
Deedo IDDP-PUN-T1ZY-UMA0 flats have a sale on record, 0 are booked without a sale deed yet and 9 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
Median saleNot on recordneeds 3 or more sales
Booked0%0 of 12 · Oct 2026
Completion30 Oct 202830 Jun 2028 · revised
Every flat, floor by floor
Tap a flat to see its record.
- Unsold
- Reserved, rehab or other
0102
Fl 7
Fl 6
Fl 5
Fl 4
Fl 3
Fl 2
Fl 1
3 BHK
Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
SelectedUnsold
Flat 702
2 BHK · 967 sq ft · floor 7
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Not on record | Not on record | 12 | Not on record |
As registered with MahaRERA
- RERA registration
- PR1260002501285 · registered 20 Oct 2025
- Promised completion
- 30 Jun 2028
- Revised completion
- 30 Oct 2028
- Sanctioned habitable floors
- 6
- Units
- 12
- Floors with commencement certificate
- 8
- Also named
- Uma
- Deedo ID
- Deedo IDDP-PUN-T1ZY-UMA
Questions about Main building
How many flats in Main building are sold?
0 flats have a sale on record, 0 are booked without a sale deed yet and 9 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
When is Main building due for completion?
The MahaRERA registration promises 30 Jun 2028, revised to 30 Oct 2028.
How many floors does Main building have?
6 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology
