Its promised completion date, May 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.
Parvati, Pune 411009 · Promoter: Skyline Enterprises
Its promised completion date, May 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 9 Mar 2020, completion promised 10 May 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100024819
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100024819 | 9 Mar 2020 | 10 May 2023 | 10 May 2023 | Skyline Enterprises | Project page |
Documents39
1 document held by Deedo, 38 filings listed on MahaRERA's project page
Finance
- PAN CardSkyline Enterprise Partnership Pan card.pdf · uploaded 29 Jan 2020Source
- PAN CardAmeya JOshi Pan Card.pdf · uploaded 29 Jan 2020Source
- PAN CardArun JOshi Pan Card.pdf · uploaded 29 Jan 2020Source
- DocumentConveyance_Deed .pdf · uploaded 4 Aug 2026Source
- DocumentSociety Formation Final.pdf · uploaded 4 Aug 2026Source
Show all 39 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardSkyline Enterprise Partnership Pan card.pdf · uploaded 29 Jan 2020Source
- 2 PAN CardAmeya JOshi Pan Card.pdf · uploaded 29 Jan 2020Source
- 3 PAN CardArun JOshi Pan Card.pdf · uploaded 29 Jan 2020Source
- 1 Copy of the legal title reportTitle Search Report New.pdf · uploaded 30 Jan 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentPMC Sanction plan NEW.pdf · uploaded 30 Jan 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentPMC Sanction plan REVISED.pdf · uploaded 30 Jan 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate NEW.pdf · uploaded 30 Jan 2020Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate REVISED.pdf · uploaded 30 Jan 2020Source
- 1 Details of encumbrancesENCUMBRANCES.pdf · uploaded 31 Jan 2020Source
- 1 Declaration in FORM BGanesh Gadgil.pdf · uploaded 8 Feb 2020Source
- 2 Declaration in FORM BShrikant Gadgil.pdf · uploaded 8 Feb 2020Source
- 3 Declaration in FORM BVijay Gadgil.pdf · uploaded 8 Feb 2020Source
- 4 Declaration in FORM BRajani Gadgil.pdf · uploaded 8 Feb 2020Source
- 5 Declaration in FORM BShobharani Pathak.pdf · uploaded 8 Feb 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 11 Feb 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate.pdf · uploaded 11 Feb 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 C A Certificate.pdf · uploaded 11 Feb 2020Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 13 Feb 2020Source
- 1 Proforma of Allotment letterAgreement For Sale.pdf · uploaded 13 Feb 2020Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompliction Certificate.PDF · uploaded 1 Mar 2022Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Architect Certificate.pdf · uploaded 9 Mar 2022Source
- 1 Status of ConveyanceConveyance Deed .pdf · uploaded 26 Apr 2023Source
Technical
Technical (Architect)
- DocumentForm 1 Architect Certificate.pdf · uploaded 11 Feb 2020Source
Technical (Engineer)
- DocumentForm 2 Engineers Certificate.pdf · uploaded 11 Feb 2020Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsCTS NO. 168, FINAL PLOT NO.514
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK15 units in all
- Address
- Plot No. 5, Cts No. 168, Survey No. 94, Final Plot No.514, Parvati Payatha Road, Near Vrushali Slimming CentrePIN 411009
- Village
- Parvati, Haveli taluka
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Road
- South
- Open Plot
- East
- Plot No 6
- West
- Plot No 4
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking15 units
15 of 15 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 66.51 sq m · 716 sq ft | 5 | 5 |
| 3BHK | 83.51 sq m · 899 sq ft | 5 | 5 |
| 3BHK | 92.62 sq m · 997 sq ft | 5 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals10
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shinde Joshi And Associates | — |
| Chartered accountant | Ambar Naik And Associates | — |
| Engineer | Raghvendra Guttal | — |
| Other | Ashok Enterprises | — |
| Other | Bhagwat Andil | — |
| Other | Dilip Chorghe | — |
| Other | Narendra Marathe | — |
| Other | Prompt Fire | — |
| Other | Udaykumar Kulkarni | — |
| Other | Vaijinath Koli | — |
Source: MahaRERA project page. Contact details are not shown.