Residential / Group Housing · 1 building · 15 unitsRERA P52100024819

Trimurti

Its promised completion date, May 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.

Parvati, Pune 411009 · Promoter: Skyline Enterprises

Delivery3 yrs 5 mo past duePromised May 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked15 of 15 units · as the promoter reported to MahaRERA
Trimurti project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, May 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 9 Mar 2020, completion promised 10 May 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100024819
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000248199 Mar 202010 May 202310 May 2023Skyline EnterprisesProject page
Documents39

1 document held by Deedo, 38 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardSkyline Enterprise Partnership Pan card.pdf · uploaded 29 Jan 2020Source
  • PAN CardAmeya JOshi Pan Card.pdf · uploaded 29 Jan 2020Source
  • PAN CardArun JOshi Pan Card.pdf · uploaded 29 Jan 2020Source
  • DocumentConveyance_Deed .pdf · uploaded 4 Aug 2026Source
  • DocumentSociety Formation Final.pdf · uploaded 4 Aug 2026Source

Legal

  • Legal Title reportTitle Search Report New.pdf · uploaded 30 Jan 2020Source
  • Declaration Form BGanesh Gadgil.pdf · uploaded 8 Feb 2020Source
Show all 39 documentsShow fewer documents

Legal

  • Declaration Form BShrikant Gadgil.pdf · uploaded 8 Feb 2020Source
  • Declaration Form BVijay Gadgil.pdf · uploaded 8 Feb 2020Source
  • Declaration Form BRajani Gadgil.pdf · uploaded 8 Feb 2020Source
  • Declaration Form BShobharani Pathak.pdf · uploaded 8 Feb 2020Source

Migrated

  • 1 PAN CardSkyline Enterprise Partnership Pan card.pdf · uploaded 29 Jan 2020Source
  • 2 PAN CardAmeya JOshi Pan Card.pdf · uploaded 29 Jan 2020Source
  • 3 PAN CardArun JOshi Pan Card.pdf · uploaded 29 Jan 2020Source
  • 1 Copy of the legal title reportTitle Search Report New.pdf · uploaded 30 Jan 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentPMC Sanction plan NEW.pdf · uploaded 30 Jan 2020Source
  • 2 Building Plan Approval / NA Order for plotted developmentPMC Sanction plan REVISED.pdf · uploaded 30 Jan 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate NEW.pdf · uploaded 30 Jan 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate REVISED.pdf · uploaded 30 Jan 2020Source
  • 1 Details of encumbrancesENCUMBRANCES.pdf · uploaded 31 Jan 2020Source
  • 1 Declaration in FORM BGanesh Gadgil.pdf · uploaded 8 Feb 2020Source
  • 2 Declaration in FORM BShrikant Gadgil.pdf · uploaded 8 Feb 2020Source
  • 3 Declaration in FORM BVijay Gadgil.pdf · uploaded 8 Feb 2020Source
  • 4 Declaration in FORM BRajani Gadgil.pdf · uploaded 8 Feb 2020Source
  • 5 Declaration in FORM BShobharani Pathak.pdf · uploaded 8 Feb 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 11 Feb 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate.pdf · uploaded 11 Feb 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 C A Certificate.pdf · uploaded 11 Feb 2020Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 13 Feb 2020Source
  • 1 Proforma of Allotment letterAgreement For Sale.pdf · uploaded 13 Feb 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompliction Certificate.PDF · uploaded 1 Mar 2022Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Architect Certificate.pdf · uploaded 9 Mar 2022Source
  • 1 Status of ConveyanceConveyance Deed .pdf · uploaded 26 Apr 2023Source

Technical

  • DocumentPMC Sanction plan REVISED.pdf · uploaded 30 Jan 2020Source
  • DocumentPMC Sanction plan NEW.pdf · uploaded 30 Jan 2020Source
  • DocumentLayout.pdf · uploaded 13 Feb 2020Source

Technical (Architect)

  • DocumentForm 1 Architect Certificate.pdf · uploaded 11 Feb 2020Source

Technical (Engineer)

  • DocumentForm 2 Engineers Certificate.pdf · uploaded 11 Feb 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsCTS NO. 168, FINAL PLOT NO.514

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK15 units in all
Address
Plot No. 5, Cts No. 168, Survey No. 94, Final Plot No.514, Parvati Payatha Road, Near Vrushali Slimming CentrePIN 411009
Village
Parvati, Haveli taluka
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

CTS NO. 168FINAL PLOT NO.514PLOT NO. 5SURVEY NO. 94

Boundaries

North
Road
South
Open Plot
East
Plot No 6
West
Plot No 4

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking15 units

15 of 15 units booked (100%), as the promoter reported to MahaRERA

2BHK · 5 units3BHK · 10 units
TypeCarpet areaUnitsBooked
2BHK66.51 sq m · 716 sq ft55
3BHK83.51 sq m · 899 sq ft55
3BHK92.62 sq m · 997 sq ft55

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals10

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShinde Joshi And Associates—
Chartered accountantAmbar Naik And Associates—
EngineerRaghvendra Guttal—
OtherAshok Enterprises—
OtherBhagwat Andil—
OtherDilip Chorghe—
OtherNarendra Marathe—
OtherPrompt Fire—
OtherUdaykumar Kulkarni—
OtherVaijinath Koli—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology