Completion was pushed back 4 months, to Dec 2027; no MahaRERA orders on record; 0% of its units are booked.

Parvati, Pune 411009 · by Shree Ram Builders & Promoters

DeliveryExtended 4 moPromised Aug 2027 · now due Dec 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 9 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Dec 2027

  • This projectRegistered 19 Nov 2024, completion promised 31 Aug 2027, revised to 31 Dec 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100077998
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210007799819 Nov 202431 Aug 202731 Dec 2027Shree Ram Builders & PromotersProject page
Documents69

1 document held by Deedo, 68 filings listed on MahaRERA's project page

Registration certificate

Finance

  • Other – FinanceBANK DECLARATION LANDOWNER.pdf · uploaded 17 Oct 2024Source
  • PAN CardPAN CARD.pdf · uploaded 17 Oct 2024Source

Legal

  • Other – LegalPARTNERSHIP DEED.pdf · uploaded 17 Oct 2024Source
  • Legal Title reportTITLE REPORT SUMEDHA.pdf · uploaded 17 Oct 2024Source
  • Declaration Form BFORM B BUILDER.pdf · uploaded 17 Oct 2024Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 17 Oct 2024Source
  • 1 Copy of the legal title reportTITLE REPORT SUMEDHA.pdf · uploaded 17 Oct 2024Source
Show all 69 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceENCUMBRANCES DETAILS.pdf · uploaded 17 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 17 Oct 2024Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 17 Oct 2024Source
  • 1 Declaration in FORM BFORM B BUILDER.pdf · uploaded 17 Oct 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 17 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN COPY 1.pdf · uploaded 17 Oct 2024Source
  • 1 Other – LegalPARTNERSHIP DEED.pdf · uploaded 17 Oct 2024Source
  • 1 Declaration about Commencement CertificateCOMMENCEMENT DECLARATION.pdf · uploaded 17 Oct 2024Source
  • 1 CERSAI detailsCERSAI DETAILS.pdf · uploaded 17 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A NEW.pdf · uploaded 17 Oct 2024Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT.pdf · uploaded 17 Oct 2024Source
  • 1 b Details of encumbrances concerned to LegalENCUMBRANCES DETAILS.pdf · uploaded 17 Oct 2024Source
  • 1 Other – FinanceBANK DECLARATION LANDOWNER.pdf · uploaded 17 Oct 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT.pdf · uploaded 17 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST.pdf · uploaded 17 Oct 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST 1.pdf · uploaded 17 Oct 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST 2.pdf · uploaded 17 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDISCLOSURE OF SECURED AND UNSECURED FINANCE.pdf · uploaded 17 Oct 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT B NEW.pdf · uploaded 23 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 24 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 24 Oct 2024Source
  • 1 Other – TechnicalANNEXURE A.pdf · uploaded 24 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 9 Nov 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT FOR SELL NEW.pdf · uploaded 9 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentNEW CC.pdf · uploaded 10 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan.pdf · uploaded 12 Mar 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 12 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1ARCHITECT CERTIFICATE.pdf · uploaded 8 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 CA CERTIFICATE.pdf · uploaded 8 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE.pdf · uploaded 8 May 2025Source
  • Form 1FORM 1ARCHITECT CERTIFICATE.pdf · uploaded 16 May 2025Source
  • Form 2ENGINEERS CERTIFICATE.pdf · uploaded 16 May 2025Source
  • Form 33 CA CERTIFICATE.pdf · uploaded 16 May 2025Source
  • Form 1FORM 1.pdf · uploaded 19 Jul 2025Source
  • Form 2FORM 2.pdf · uploaded 19 Jul 2025Source
  • Disclosure of Sold and Booked InventoryPhotoScan.pdf · uploaded 19 Jul 2025Source
  • Form 3FORM 3 - converted.pdf · uploaded 19 Jul 2025Source
  • Form 1FORM 1.pdf · uploaded 29 Oct 2025Source
  • Form 2FORM 2.pdf · uploaded 29 Oct 2025Source
  • Form 3FORM 3 CA.pdf · uploaded 29 Oct 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 29 Oct 2025Source
  • Form 1Form No 1 Architect Certificate.pdf · uploaded 28 Jan 2026Source
  • Form 2FORM 2 Engineer Certificate.pdf · uploaded 28 Jan 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 28 Jan 2026Source
  • Form 3Form 3 CA Sumedha.pdf · uploaded 28 Jan 2026Source
  • Form 1FORM 1 - ARCHITECT CERTIFICATE.pdf · uploaded 21 Apr 2026Source
  • Form 2FORM 2 engineer certificate.pdf · uploaded 21 Apr 2026Source
  • Form 3FORM 3 - CA CERTIFICATE.pdf · uploaded 21 Apr 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 CA.pdf · uploaded 12 Aug 2026Source

Technical

  • DocumentPLAN COPY 1.pdf · uploaded 17 Oct 2024Source
  • DocumentLAYOUT.pdf · uploaded 17 Oct 2024Source
  • Other – TechnicalANNEXURE A.pdf · uploaded 24 Oct 2024Source
  • DocumentPlan.pdf · uploaded 12 Mar 2025Source
  • DocumentPlan 2.pdf · uploaded 12 Mar 2025Source

Technical (Architect)

  • DocumentFORM 1ARCHITECT CERTIFICATE.pdf · uploaded 8 May 2025Source
  • DocumentFORM 1.pdf · uploaded 12 Aug 2026Source

Technical (Engineer)

  • DocumentENGINEERS CERTIFICATE.pdf · uploaded 8 May 2025Source
  • DocumentFORM 2.pdf · uploaded 12 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CTS NO. 4612, FINAL PLOT NO. 477B/4A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 2 BHK LANDOWNER, 3 BHK LANDOWNER9 units in all
Address
Cts No. 4612, Final Plot No. 477b/4a, Shahu College Road, Near Shalimar ChslPIN 411009
Village
Parvati, Haveli taluka
Land area for this project
1,021 sq m (10,986 sq ft)
Permissible built-up area
4,379 sq m (47,139 sq ft)
Sanctioned built-up area
1,018 sq m (10,961 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
35
Developed in phases
No

Survey, CTS, gat or plot numbers

CTS NO. 4612FINAL PLOT NO. 477B/4A

Land as published on MahaRERA's project page

CTS NO. 4612, FINAL PLOT NO. 477B/4A

Boundaries

North
Shahu College Road
South
Open Space
East
Shalimar Chsl
West
477 4 B

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking9 units

0 of 9 units booked (0%), as the promoter reported to MahaRERA

2BHK · 1 unit2 BHK LANDOWNER · 2 units3 BHK LANDOWNER · 6 units
TypeCarpet areaUnitsBooked
2BHK79.43 sq m · 855 sq ft10
2 BHK LANDOWNER71.07 sq m · 765 sq ft20
3 BHK LANDOWNER107.02 sq m · 1,152 sq ft60

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShinde Joshi And Associates—
Chartered accountantG R Shendye And Co LLP—
EngineerShubham Rajesh Shinde—
OtherShree Sairaj Buildcon—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology