Skip to content
Residential / Group Housing · 1 building · 45 unitsRERA P52100012055

Savitri Complex

Its promised completion date, Dec 2019, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 36% of its units are booked.

Otur, Pune 412409 · Promoter: M/S Trimurti Developers

Delivery6 yrs 10 mo past duePromised Dec 2019 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales36% booked16 of 45 units · as the promoter reported to MahaRERA
Savitri Complex project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Dec 2019, has passed and MahaRERA does not show it completed

  • This projectRegistered 1 Sep 2017, completion promised 31 Dec 2019, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100012055
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000120551 Sep 201731 Dec 201931 Dec 2019M/S Trimurti DevelopersProject page
Documents21

1 document held by Deedo, 20 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFirm Pan.pdf · uploaded 15 Aug 2017Source

Legal

  • Declaration Form BFORM B.pdf · uploaded 15 Aug 2017Source
  • Legal Title reportSEARCH REPORT(1).pdf · uploaded 15 Aug 2017Source

Migrated

  • 1 PAN CardFirm Pan.pdf · uploaded 15 Aug 2017Source
  • 1 Copy of the legal title reportSEARCH REPORT(1).pdf · uploaded 15 Aug 2017Source
  • 1 Details of encumbrancesENCUMBRANCES CERTIFICATE.pdf · uploaded 15 Aug 2017Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN(1).pdf · uploaded 15 Aug 2017Source
Show all 21 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)BUILDING PLAN 1 (2 files merged).pdf · uploaded 15 Aug 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT.pdf · uploaded 15 Aug 2017Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 15 Aug 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECH CERTIFICATE.pdf · uploaded 16 Aug 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGG CERTIFICATE.pdf · uploaded 16 Aug 2017Source
  • 1 Certificates of CA (Form 3)CERTIFICATE - 2 (2).pdf · uploaded 16 Aug 2017Source
  • 1 Proforma of Allotment letter1 (5 files merged).pdf · uploaded 16 Aug 2017Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupancy Certificate-PDF.pdf · uploaded 21 Jul 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Savitri Complex-Rera 559-1B-1-FORM -04 .pdf · uploaded 21 Jul 2020Source

Technical

  • DocumentBUILDING PLAN 1 (2 files merged).pdf · uploaded 15 Aug 2017Source
  • DocumentLAYOUT PLAN(1).pdf · uploaded 15 Aug 2017Source

Technical (Architect)

  • DocumentARCHITECH CERTIFICATE.pdf · uploaded 16 Aug 2017Source

Technical (Engineer)

  • DocumentENGG CERTIFICATE.pdf · uploaded 16 Aug 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals559/1B/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
Flat, Shop45 units in all
Address
559/1b/1PIN 412409
Village
Otur, Junnar taluka
Designated bank account
99
Developed in phases
No

Survey, CTS, gat or plot numbers

559/1B/1

Boundaries

North
559 1 B Hissa No 1
South
559 1 B Hissa No 2
East
Old Otur Ozar Road
West
559 1 B Hissa No 3

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking45 units

16 of 45 units booked (36%), as the promoter reported to MahaRERA

Flat · 41 unitsShop · 4 units
TypeCarpet areaUnitsBooked
Flat1,319.4 sq m · 14,202 sq ft4116
Shop49.6 sq m · 534 sq ft40

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectLaxmikant Ambadas Naikwadi—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology