Skip to content
Promised date passed34 floorsRERA P52100000385

A, Pancham

Deedo IDDP-PUN-C8ZY-A

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Booked88%219 of 248 · MahaRERA
Completion31 Oct 2019as registered
Units & parking in A
TypeCarpet areaUnitsBooked
2 BHK53.9 m² (580 sq.ft)3129
2 BHK56.3 m² (606 sq.ft)217190
As registered with MahaRERA
RERA registration
P52100000385 · registered 15 Jul 2017
Promised completion
31 Oct 2019
Revised completion
31 Oct 2019
Sanctioned habitable floors
34
Sanctioned floors (incl. basement, stilt, podium)
34
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
Deedo IDDP-PUN-C8ZY-A
Questions about A

When is A due for completion?

The MahaRERA registration promises 31 Oct 2019.

How many floors does A have?

34 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology