Extended 18 mo16 floorsRERA P52100018013
Building - A, Fusion
Deedo IDDP-PUN-3Y19-AMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked100%110 of 110 · MahaRERA
Completion30 Dec 202230 Jun 2021 · revised
Units & parking in Building - A
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 RHK | 47 m² (506 sq.ft) | 6 | 6 |
| 2 RHK | 47.3 m² (509 sq.ft) | 20 | 20 |
| 2 RHK | 47.7 m² (513 sq.ft) | 28 | 28 |
| 2 RHK | 47.8 m² (514 sq.ft) | 28 | 28 |
| 2 RHK | 48.1 m² (518 sq.ft) | 28 | 28 |
As registered with MahaRERA
- RERA registration
- P52100018013 · registered 3 Oct 2018
- Promised completion
- 30 Jun 2021
- Revised completion
- 30 Dec 2022
- Sanctioned habitable floors
- 16
- Sanctioned floors (incl. basement, stilt, podium)
- 16
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-3Y19-A
Questions about Building - A
When is Building - A due for completion?
The MahaRERA registration promises 30 Jun 2021, revised to 30 Dec 2022.
How many floors does Building - A have?
16 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology