Skip to content
Residential / Group Housing · 2 buildings · 100 unitsRERA P52100018865

Neeti Privilege

Deedo IDDP-PUN-449W

Its promised completion date, Nov 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 33% of its units are booked.

Marunji, Pune 411057 · by Neeti Shelters Llp, Neeti Shelters LLP

Delivery2 yrs past duePromised Nov 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales33% booked33 of 100 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Nov 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 6 Dec 2018, completion promised 29 Nov 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100018865
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000188656 Dec 201829 Nov 202429 Nov 2024Neeti Shelters LLPProject page
Documents63

1 document held by Deedo, 62 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportSearch-Report-1-4.pdf · uploaded 23 Nov 2018Source
  • Legal Title reportSearch-Report-5-8.pdf · uploaded 23 Nov 2018Source
  • Declaration Form BPromoter Declaraation_FORM B.pdf · uploaded 23 Nov 2018Source

Migrated

  • 1 Copy of the legal title reportSearch-Report-1-4.pdf · uploaded 23 Nov 2018Source
  • 2 Copy of the legal title reportSearch-Report-5-8.pdf · uploaded 23 Nov 2018Source
  • 1 Details of encumbrancesNo Encumbrances letter.pdf · uploaded 23 Nov 2018Source
  • 1 Copy of Layout Approval (in case of layout)layout 1.pdf · uploaded 23 Nov 2018Source
Show all 63 documentsShow fewer documents

Migrated

  • 2 Copy of Layout Approval (in case of layout)layout 6.pdf · uploaded 23 Nov 2018Source
  • 1 Building Plan Approval (IOD)layout 2.pdf · uploaded 23 Nov 2018Source
  • 2 Building Plan Approval (IOD)layout 3.pdf · uploaded 23 Nov 2018Source
  • 3 Building Plan Approval (IOD)layout 4.pdf · uploaded 23 Nov 2018Source
  • 4 Building Plan Approval (IOD)layout 5.pdf · uploaded 23 Nov 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencemnet Certificate_PMRDA Marunji.pdf · uploaded 23 Nov 2018Source
  • 1 Declaration in FORM BPromoter Declaraation_FORM B.pdf · uploaded 23 Nov 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ROHAN SURVE ARCHITECTS.pdf · uploaded 23 Nov 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS_CERTIFICATE_Neeti Shelters.pdf · uploaded 23 Nov 2018Source
  • 1 Proforma of Allotment letterAgreement to sale.pdf · uploaded 23 Nov 2018Source
  • 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 23 Nov 2018Source
  • 1 Certificates of CA (Form 3)CA Certificate_NEETTI SHELTERS LLP.pdf · uploaded 26 Nov 2018Source
  • 1 Form 2AForm 2A_compressed.pdf · uploaded 3 Jun 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)Form 5 - 2019 Neeti shelters.pdf · uploaded 30 Sep 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 - 2019 Neeti shelters.pdf · uploaded 26 Nov 2019Source
  • 3 Proforma of Allotment letterNew Agreement to sale 5-2-20.pdf · uploaded 8 Feb 2020Source
  • 2 Details of encumbrancesEncumbrances letter 10-2-2020.pdf · uploaded 11 Feb 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A 2021.pdf · uploaded 3 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Report .pdf · uploaded 15 Sep 2023Source
  • 1 Declaration about Commencement CertificateCompletion Certificate B BLD 1.pdf · uploaded 5 Feb 2024Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Rera _form 1 _211123.pdf · uploaded 5 Feb 2024Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Dec.pdf · uploaded 5 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)RERA FROM 2A 22.pdf · uploaded 5 Feb 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)RERA FORM-2A 23.pdf · uploaded 5 Feb 2024Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Rera _form 1 .pdf · uploaded 23 Feb 2024Source
  • 12 Certificates of CA (Form 3)Neeti Privilage Sep 2021.pdf · uploaded 17 Jan 2025Source
  • 22 Certificates of CA (Form 3)Neeti Privilage Mar 2024.pdf · uploaded 17 Jan 2025Source
  • 21 Certificates of CA (Form 3)Neeti Privilage Dec 2023.pdf · uploaded 17 Jan 2025Source
  • 20 Certificates of CA (Form 3)Neeti Privilage Sep 2023.pdf · uploaded 17 Jan 2025Source
  • 19 Certificates of CA (Form 3)Neeti Privilage Jun 2023.pdf · uploaded 17 Jan 2025Source
  • 18 Certificates of CA (Form 3)Neeti Privilage Mar 2023.pdf · uploaded 17 Jan 2025Source
  • 17 Certificates of CA (Form 3)Neeti Privilage Dec 2022_11zon.pdf · uploaded 17 Jan 2025Source
  • 16 Certificates of CA (Form 3)Neeti Privilage Sep 2022.pdf · uploaded 17 Jan 2025Source
  • 15 Certificates of CA (Form 3)Neeti Privilage Jun 2022.pdf · uploaded 17 Jan 2025Source
  • 14 Certificates of CA (Form 3)Neeti Privilage Mar 2022.pdf · uploaded 17 Jan 2025Source
  • 13 Certificates of CA (Form 3)Neeti Privilage Dec 2021.pdf · uploaded 17 Jan 2025Source
  • 1 Certificates of CA (Form 3)Neeti Privilage Dec 2018.pdf · uploaded 17 Jan 2025Source
  • 11 Certificates of CA (Form 3)Neeti Privilage Jun 2021.pdf · uploaded 17 Jan 2025Source
  • 10 Certificates of CA (Form 3)Neeti Privilage Mar 2021.pdf · uploaded 17 Jan 2025Source
  • 9 Certificates of CA (Form 3)Neeti Privilage Dec 2020.pdf · uploaded 17 Jan 2025Source
  • 8 Certificates of CA (Form 3)Neeti Privilage Sep 2020.pdf · uploaded 17 Jan 2025Source
  • 7 Certificates of CA (Form 3)Neeti Privilage Jun 2020.pdf · uploaded 17 Jan 2025Source
  • 6 Certificates of CA (Form 3)Neeti Privilage Mar 2020.pdf · uploaded 17 Jan 2025Source
  • 5 Certificates of CA (Form 3)Neeti Privilage Dec 2019.pdf · uploaded 17 Jan 2025Source
  • 4 Certificates of CA (Form 3)Neeti Privilage Sep 2019.pdf · uploaded 17 Jan 2025Source
  • 3 Certificates of CA (Form 3)Neeti Privilage Jun 2019.pdf · uploaded 17 Jan 2025Source
  • 2 Certificates of CA (Form 3)Neeti Privilage Mar 2019.pdf · uploaded 17 Jan 2025Source

Technical

  • Documentlayout 1.pdf · uploaded 23 Nov 2018Source
  • Documentlayout 6.pdf · uploaded 23 Nov 2018Source
  • Documentlayout 2.pdf · uploaded 23 Nov 2018Source
  • Documentlayout 3.pdf · uploaded 23 Nov 2018Source
  • Documentlayout 4.pdf · uploaded 23 Nov 2018Source
  • Documentlayout 5.pdf · uploaded 23 Nov 2018Source

Technical (Architect)

  • DocumentRera _form 1 .pdf · uploaded 23 Feb 2024Source

Technical (Engineer)

  • DocumentForm 2 Dec.pdf · uploaded 5 Feb 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 78/3/1P

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK100 units in all
Address
78/3/1p, Marunji, MarunjiPIN 411057
Village
Marunji, Mulshi taluka
Land area for this project
4,000 sq m (43,056 sq ft)
Permissible built-up area
4,226 sq m (45,484 sq ft)
Sanctioned built-up area
3,629 sq m (39,066 sq ft)
Recreational open space
400 sq m (4,306 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

78/3/1P

Land as published on MahaRERA's project page

78/3/1P

Boundaries

North
Sr No 78-6
South
Sr No 78-7
East
Dp Road
West
Sr No 78-3-1

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking100 units

33 of 100 units booked (33%), as the promoter reported to MahaRERA

1BHK · 76 units2BHK · 24 units
BuildingTypeCarpet areaUnitsBooked
Building - A1BHK35.29 sq m · 380 sq ft101
Building - A1BHK35.49 sq m · 382 sq ft81
Building - A1BHK35.52 sq m · 382 sq ft20
Building - A1BHK36.68 sq m · 395 sq ft61
Building - A1BHK36.89 sq m · 397 sq ft40
Building - A1BHK36.91 sq m · 397 sq ft20
Building - A2BHK51.48 sq m · 554 sq ft20
Building - A2BHK51.58 sq m · 555 sq ft20
Show all 28 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Building - A2BHK51.65 sq m · 556 sq ft20
Building - A2BHK51.97 sq m · 559 sq ft20
Building - A2BHK52.28 sq m · 563 sq ft20
Building - A2BHK60.48 sq m · 651 sq ft20
Building - B1BHK35.29 sq m · 380 sq ft146
Building - B1BHK35.31 sq m · 380 sq ft20
Building - B1BHK35.44 sq m · 381 sq ft21
Building - B1BHK35.46 sq m · 382 sq ft63
Building - B1BHK35.47 sq m · 382 sq ft61
Building - B1BHK35.62 sq m · 383 sq ft20
Building - B1BHK36.68 sq m · 395 sq ft43
Building - B1BHK36.84 sq m · 397 sq ft22
Building - B1BHK36.88 sq m · 397 sq ft43
Building - B1BHK37.04 sq m · 399 sq ft22
Building - B2BHK45.24 sq m · 487 sq ft21
Building - B2BHK45.55 sq m · 490 sq ft22
Building - B2BHK48 sq m · 517 sq ft21
Building - B2BHK48.5 sq m · 522 sq ft22
Building - B2BHK50.26 sq m · 541 sq ft21
Building - B2BHK51.01 sq m · 549 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Rohan Surve—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology