Its promised completion date, Apr 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record.

Lonavala (M Cl), Pune 410401 · Promoter: Jitu Properties & Developments Pvt Ltd

Delivery3 yrs 6 mo past duePromised Apr 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read
Royal Park project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Apr 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 6 Dec 2020, completion promised 30 Apr 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100027378
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000273786 Dec 202030 Apr 202330 Apr 2023Jitu Properties & Developments Pvt LtdProject page
Documents23

1 document held by Deedo, 22 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardboth pan0001.pdf · uploaded 7 Nov 2020Source

Legal

  • Otherproperty card_compressed.pdf · uploaded 7 Nov 2020Source
  • Declaration Form BNOTRY OF RERA DOCUMENT_compressed.pdf · uploaded 7 Nov 2020Source
  • Legal Title reportsearch report_compressed.pdf · uploaded 7 Nov 2020Source

Migrated

  • 1 PAN Cardboth pan0001.pdf · uploaded 7 Nov 2020Source
  • 1 Copy of the legal title reportsearch report_compressed.pdf · uploaded 7 Nov 2020Source
  • 1 Details of encumbrancesdetails of non encubrences.pdf · uploaded 7 Nov 2020Source
Show all 23 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentblue plan scan document.pdf · uploaded 7 Nov 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate_compressed.pdf · uploaded 7 Nov 2020Source
  • 1 Declaration in FORM BNOTRY OF RERA DOCUMENT_compressed.pdf · uploaded 7 Nov 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form no 3 certificate from CA_compressed.pdf · uploaded 7 Nov 2020Source
  • 1 Otherproperty card_compressed.pdf · uploaded 7 Nov 2020Source
  • 1 Copy of Layout Approval (in case of layout)blue plan scan document.pdf · uploaded 19 Nov 2020Source
  • 1 Proforma of Allotment letterrera draft_compressed-11-20.pdf · uploaded 19 Nov 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 jitu properties.pdf · uploaded 20 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Royal_Park_Form_5 2021.pdf · uploaded 26 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)royal park form 5 21-22.pdf · uploaded 26 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)quality assurance royal park20-21.pdf · uploaded 8 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)quality assurance royal park21-22.pdf · uploaded 8 May 2023Source

Technical

  • Documentblue plan scan document.pdf · uploaded 7 Nov 2020Source
  • Documentblue plan scan document.pdf · uploaded 19 Nov 2020Source

Technical (Architect)

  • DocumentForm 1 jitu properties.pdf · uploaded 20 Feb 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals105, 105A

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Address
105, 105a, 106, Minar Masjid Road, Lonavala GaothanPIN 410401
Village
Lonavala (M Cl), Mawal taluka
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

105105A106

Boundaries

North
Municipal Road
South
Cts No 104
East
Vacant Land And Road
West
Municipal Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Architectyogesh shiva—
Chartered accountantRajendra joshi—
Engineerpavan joshi—
Othermahindar singh bakshi—

Source: MahaRERA project page. Contact details are not shown.