Deedo IDDP-PUN-XRAECompletion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 7% of its units are booked.
Kiwale, Pune 412101 · Promoter: Crestline Realty LLP
Completion was pushed back 4 months, to Apr 2030
- This projectRegistered 6 Nov 2025, completion promised 31 Dec 2029, revised to 30 Apr 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPM1260002501391
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1260002501391 | 6 Nov 2025 | 31 Dec 2029 | 30 Apr 2030 | Crestline Realty LLP | Project page |
Documents45
1 document held by Deedo, 44 filings listed on MahaRERA's project page
Finance
Show all 45 documentsShow fewer documents
Legal
- OthersAkshay (1).pdf · uploaded 20 Oct 2025Source
- OthersBapuji (1).pdf · uploaded 20 Oct 2025Source
- OthersVaibhav vidhate (1).pdf · uploaded 20 Oct 2025Source
- Othersकिवळे_82_12.pdf · uploaded 20 Oct 2025Source
- Othersकिवळे_82-1.pdf · uploaded 20 Oct 2025Source
- OthersCRYSTLINE LLP AGREEMENT (1)_11zon.pdf · uploaded 20 Oct 2025Source
- OthersPromoter Declaration (1) (2).pdf · uploaded 20 Oct 2025Source
- OthersPromoter Declaration on 712 extract.pdf · uploaded 29 Oct 2025Source
- Declaration Form BBlank page.pdf · uploaded 29 Oct 2025Source
- Declaration Form BSearch title report (4).pdf · uploaded 29 Oct 2025Source
Migrated
- Withdrawal Update Form 1Form 1 s.pdf · uploaded 16 Feb 2026Source
- Withdrawal Update Form 2Form 2 s.pdf · uploaded 16 Feb 2026Source
- Withdrawal Update Form 3FORM 3 s_compressed (9).pdf · uploaded 16 Feb 2026Source
- Withdrawal Update Form 1F1-Q4.pdf · uploaded 7 May 2026Source
- Withdrawal Update Form 2F2-Q4.pdf · uploaded 7 May 2026Source
- Withdrawal Update Form 3F3-Q4.pdf · uploaded 7 May 2026Source
- Withdrawal Update Form 1F1-Q1.pdf · uploaded 14 Jul 2026Source
- Withdrawal Update Form 2F2-Q1.pdf · uploaded 14 Jul 2026Source
- Withdrawal Update Form 3F3-Q1.pdf · uploaded 14 Jul 2026Source
Technical
- DocumentMain Layout Crestline project.pdf · uploaded 5 Sep 2025Source
- Documentscan 862.pdf · uploaded 5 Sep 2025Source
- Documentscan 863.pdf · uploaded 5 Sep 2025Source
- Documentscan 864.pdf · uploaded 5 Sep 2025Source
- Documentscan 865.pdf · uploaded 5 Sep 2025Source
- Documentscan 866.pdf · uploaded 5 Sep 2025Source
- Documentscan 867.pdf · uploaded 5 Sep 2025Source
- Documentscan 868.pdf · uploaded 5 Sep 2025Source
- Documentscan 869.pdf · uploaded 5 Sep 2025Source
- Documentscan 870.pdf · uploaded 5 Sep 2025Source
- Documentscan 871.pdf · uploaded 5 Sep 2025Source
- Otherscrestline shreshth (1) (2) (1).pdf · uploaded 29 Sep 2025Source
- OthersDecalaration commencement CRESTLINE SHRESHTH (1) (1).pdf · uploaded 30 Sep 2025Source
- DocumentAnnexture A -Order No 50 (1).pdf · uploaded 4 Oct 2025Source
- OthersArchitect Certificate Crestline (1).pdf · uploaded 4 Oct 2025Source
- OthersCrestline project CC mail (1).pdf · uploaded 20 Oct 2025Source
Technical (Architect)
- DocumentF1-Q1.pdf · uploaded 14 Jul 2026Source
Technical (Engineer)
- DocumentF2-Q1.pdf · uploaded 14 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals82/12 Kiwale, Survey No. 82/1
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- —74 units in all
- Address
- KiwalePIN 412101
- Village
- Kiwale, Haveli taluka
- Location
- 18.66116, 73.72866
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- By 24 Mtrs. vide Road
- South
- By Survey No. 82 Mr. Nimbalkar property
- East
- By Survey No. 82 Mr. Balaji Builders property
- West
- By survey No. 82 Mr. Balasaheb Taras property
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking74 units
74 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 74 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Pravin Pise | — |
| Engineer | Mangesh Deochake | — |
| Engineer | Rohinee Kailas Badgujar | — |
Source: MahaRERA project page. Contact details are not shown.