Evolvus

Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 53% of its units are booked.

Kharadi, Pune 411014 · Property rates in Kharadi · Promoter: Townshine Realties Private Limited

DeliveryExtended 4 moPromised Dec 2029 · now due Apr 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales53% booked591 of 1,119 units · as the promoter reported to MahaRERA
Evolvus project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2030

  • P52100054253Registered 10 Jan 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.
  • P52100056143Registered 16 May 2024, completion promised 31 Dec 2028, revised to 30 Apr 2029.
  • P52100080891Registered 1 Aug 2025, completion promised 31 Dec 2029, revised to 30 Apr 2030.

No extension certificate on record.

3 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

10 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations3
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005425310 Jan 202431 Dec 202830 Apr 2029Townshine Realties Private LimitedProject page
P5210005614316 May 202431 Dec 202830 Apr 2029Townshine Realties Private LimitedProject page
P521000808911 Aug 202531 Dec 202930 Apr 2030Townshine Realties Private LimitedProject page
Documents579

3 documents held by Deedo, 576 filings listed on MahaRERA's project page

Registration certificate (3)

  • Registration certificateP52100054253 · 10 Jan 2024ViewSource
  • Registration certificateP52100056143 · 11 Jun 2024ViewSource
  • Registration certificateP52100080891 · 1 Aug 2025ViewSource

Finance

  • PAN CardP52100054253 · 1 PAN Card.pdf · uploaded 26 Dec 2023Source
  • PAN CardP52100056143 · 1 PAN Card (1).pdf · uploaded 20 Apr 2024Source
  • Other – FinanceP52100056143 · LO NOC.pdf · uploaded 8 May 2024Source
  • Other – FinanceP52100056143 · POA_4609 SP-NP.pdf · uploaded 8 May 2024Source
  • Other – FinanceP52100056143 · 4 Bank Confirmation Letter.pdf · uploaded 22 May 2024Source
Show all 579 documentsShow fewer documents

Finance

  • PAN CardP52100080891 · PAN.pdf · uploaded 17 Mar 2025Source
  • PAN CardP52100080891 · PAN.pdf · uploaded 17 Mar 2025Source
  • PAN CardP52100080891 · PAN.pdf · uploaded 17 Mar 2025Source
  • PAN CardP52100080891 · PAN.pdf · uploaded 17 Mar 2025Source
  • Other – FinanceP52100080891 · NOC LO.pdf · uploaded 9 May 2025Source
  • Other – FinanceP52100080891 · POA Pashankar Nilkanth Sagar.pdf · uploaded 9 May 2025Source
  • Other – FinanceP52100080891 · NOC LO.pdf · uploaded 9 May 2025Source
  • Other – FinanceP52100080891 · POA Pashankar Nilkanth Sagar.pdf · uploaded 9 May 2025Source
  • Other – FinanceP52100080891 · NOC LO.pdf · uploaded 9 May 2025Source
  • Other – FinanceP52100080891 · POA Pashankar Nilkanth Sagar.pdf · uploaded 9 May 2025Source
  • Other – FinanceP52100080891 · NOC LO.pdf · uploaded 9 May 2025Source
  • Other – FinanceP52100080891 · POA Pashankar Nilkanth Sagar.pdf · uploaded 9 May 2025Source

Legal

  • Legal Title reportP52100054253 · doc11315820231228122303.pdf · uploaded 26 Dec 2023Source
  • Legal Title reportP52100054253 · doc11315720231228122103_compressed.pdf · uploaded 26 Dec 2023Source
  • Declaration Form BP52100054253 · 1 Declaration in FORM B.pdf · uploaded 26 Dec 2023Source
  • Legal Title reportP52100056143 · STR.pdf · uploaded 20 Apr 2024Source
  • Legal Title reportP52100056143 · STR Full_compressed.pdf · uploaded 20 Apr 2024Source
  • Declaration Form BP52100056143 · Form B Promoter.pdf · uploaded 20 Apr 2024Source
  • Declaration Form BP52100080891 · Form B Promoter.pdf · uploaded 18 Mar 2025Source
  • Declaration Form BP52100080891 · Form B Promoter.pdf · uploaded 18 Mar 2025Source
  • Declaration Form BP52100080891 · Form B Promoter.pdf · uploaded 18 Mar 2025Source
  • Declaration Form BP52100080891 · Form B Promoter.pdf · uploaded 18 Mar 2025Source
  • Legal Title reportP52100080891 · STR I.pdf · uploaded 23 Apr 2025Source
  • Legal Title reportP52100080891 · STR II_compressed.pdf · uploaded 23 Apr 2025Source
  • Legal Title reportP52100080891 · STR I.pdf · uploaded 23 Apr 2025Source
  • Legal Title reportP52100080891 · STR II_compressed.pdf · uploaded 23 Apr 2025Source
  • Legal Title reportP52100080891 · STR I.pdf · uploaded 23 Apr 2025Source
  • Legal Title reportP52100080891 · STR II_compressed.pdf · uploaded 23 Apr 2025Source
  • Legal Title reportP52100080891 · STR I.pdf · uploaded 23 Apr 2025Source
  • Legal Title reportP52100080891 · STR II_compressed.pdf · uploaded 23 Apr 2025Source
  • Other – LegalP52100080891 · NOC M2 Builtcon.pdf · uploaded 8 Jul 2025Source
  • Other – LegalP52100080891 · NOC M2 Builtcon.pdf · uploaded 8 Jul 2025Source
  • Other – LegalP52100080891 · NOC M2 Builtcon.pdf · uploaded 8 Jul 2025Source
  • Other – LegalP52100080891 · NOC M2 Builtcon.pdf · uploaded 8 Jul 2025Source
  • OthersP52100054253 · RERA.pdf · uploaded 24 Nov 2025Source

Migrated

  • 1 PAN CardP52100054253 · 1 PAN Card.pdf · uploaded 26 Dec 2023Source
  • 1 Copy of the legal title reportP52100054253 · doc11315820231228122303.pdf · uploaded 26 Dec 2023Source
  • 2 Copy of the legal title reportP52100054253 · doc11315720231228122103_compressed.pdf · uploaded 26 Dec 2023Source
  • 1 a Details of encumbrances concerned to FinanceP52100054253 · 1 a Details of encumbrances concerned to Finance.pdf · uploaded 26 Dec 2023Source
  • 1 b Details of encumbrances concerned to LegalP52100054253 · 1 a Details of encumbrances concerned to Finance.pdf · uploaded 26 Dec 2023Source
  • 1 Declaration in FORM BP52100054253 · 1 Declaration in FORM B.pdf · uploaded 26 Dec 2023Source
  • 1 CERSAI detailsP52100054253 · 1 CERSAI details.pdf · uploaded 26 Dec 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100054253 · 1 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 26 Dec 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsP52100054253 · 2 Disclosure of Interest in Other Real Estate Organizations.pdf · uploaded 26 Dec 2023Source
  • 1 Proforma of Agreement for saleP52100054253 · Agreement_New Draft_Residential_Kharadi 39.pdf · uploaded 26 Dec 2023Source
  • 1 Proforma of Allotment letterP52100054253 · 1 Proforma of Allotment letter.pdf · uploaded 26 Dec 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100054253 · Format A new.pdf · uploaded 26 Dec 2023Source
  • 1 Deviation Report with respect to Allotment letterP52100054253 · 1 Deviation Report with respect to Allotment letter.pdf · uploaded 26 Dec 2023Source
  • 1 Deviation Report with respect to model copy of AgreementP52100054253 · 1 Deviation Report with respect to model copy of Agreement.pdf · uploaded 26 Dec 2023Source
  • 1 Copy of Layout Approval (in case of layout)P52100054253 · 1-18.pdf · uploaded 28 Dec 2023Source
  • 2 Copy of Layout Approval (in case of layout)P52100054253 · LAYOUT.pdf · uploaded 28 Dec 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100054253 · 2-18.pdf · uploaded 28 Dec 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100054253 · 3-18.pdf · uploaded 28 Dec 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentP52100054253 · 4-18.pdf · uploaded 28 Dec 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentP52100054253 · 5-18.pdf · uploaded 28 Dec 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentP52100054253 · 6-18.pdf · uploaded 28 Dec 2023Source
  • 6 Building Plan Approval / NA Order for plotted developmentP52100054253 · 7-18.pdf · uploaded 28 Dec 2023Source
  • 7 Building Plan Approval / NA Order for plotted developmentP52100054253 · 8-18.pdf · uploaded 28 Dec 2023Source
  • 8 Building Plan Approval / NA Order for plotted developmentP52100054253 · 9-18.pdf · uploaded 28 Dec 2023Source
  • 9 Building Plan Approval / NA Order for plotted developmentP52100054253 · 10-18.pdf · uploaded 28 Dec 2023Source
  • 10 Building Plan Approval / NA Order for plotted developmentP52100054253 · 11-18.pdf · uploaded 28 Dec 2023Source
  • 11 Building Plan Approval / NA Order for plotted developmentP52100054253 · 12-18.pdf · uploaded 28 Dec 2023Source
  • 12 Building Plan Approval / NA Order for plotted developmentP52100054253 · 13-18.pdf · uploaded 28 Dec 2023Source
  • 13 Building Plan Approval / NA Order for plotted developmentP52100054253 · 17-18.pdf · uploaded 28 Dec 2023Source
  • 14 Building Plan Approval / NA Order for plotted developmentP52100054253 · 18-18.pdf · uploaded 28 Dec 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100054253 · C C LAYOUT.pdf · uploaded 28 Dec 2023Source
  • 1 Declaration about Commencement CertificateP52100054253 · 2 Declaration about Commencement Certificate (2).pdf · uploaded 28 Dec 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054253 · FORM 3.pdf · uploaded 28 Dec 2023Source
  • 2 a Details of encumbrances concerned to FinanceP52100054253 · Encumbrance Certificate.pdf · uploaded 16 Mar 2024Source
  • 2 b Details of encumbrances concerned to LegalP52100054253 · Encumbrance Certificate.pdf · uploaded 16 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054253 · Evolvus - Form 1 Arch certificate - Phase 1 - 311223 (2).pdf · uploaded 23 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054253 · Evolvus - Form 1 Arch certificate - Phase 1 - 29022024.pdf · uploaded 23 Mar 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054253 · PH-1 ENGG CERTIFICATE-EVOLVUS-220124.pdf · uploaded 23 Mar 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054253 · Evolvus-Engg certificate-29-02-2024.pdf · uploaded 23 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054253 · Form 3 - Evolvus_290224.pdf · uploaded 23 Mar 2024Source
  • 3 Copy of Layout Approval (in case of layout)P52100054253 · 1-19.pdf · uploaded 27 Mar 2024Source
  • 15 Building Plan Approval / NA Order for plotted developmentP52100054253 · 02-19.pdf · uploaded 27 Mar 2024Source
  • 16 Building Plan Approval / NA Order for plotted developmentP52100054253 · 03-19.pdf · uploaded 27 Mar 2024Source
  • 17 Building Plan Approval / NA Order for plotted developmentP52100054253 · 04-19.pdf · uploaded 27 Mar 2024Source
  • 18 Building Plan Approval / NA Order for plotted developmentP52100054253 · 05-19.pdf · uploaded 27 Mar 2024Source
  • 19 Building Plan Approval / NA Order for plotted developmentP52100054253 · 06-19.pdf · uploaded 27 Mar 2024Source
  • 20 Building Plan Approval / NA Order for plotted developmentP52100054253 · 07-19.pdf · uploaded 27 Mar 2024Source
  • 21 Building Plan Approval / NA Order for plotted developmentP52100054253 · 09-19.pdf · uploaded 27 Mar 2024Source
  • 22 Building Plan Approval / NA Order for plotted developmentP52100054253 · 09-19.pdf · uploaded 27 Mar 2024Source
  • 23 Building Plan Approval / NA Order for plotted developmentP52100054253 · 10-19.pdf · uploaded 27 Mar 2024Source
  • 24 Building Plan Approval / NA Order for plotted developmentP52100054253 · 11-19.pdf · uploaded 27 Mar 2024Source
  • 25 Building Plan Approval / NA Order for plotted developmentP52100054253 · 12-19.pdf · uploaded 27 Mar 2024Source
  • 26 Building Plan Approval / NA Order for plotted developmentP52100054253 · 13-19.pdf · uploaded 27 Mar 2024Source
  • 27 Building Plan Approval / NA Order for plotted developmentP52100054253 · 14-19.pdf · uploaded 27 Mar 2024Source
  • 28 Building Plan Approval / NA Order for plotted developmentP52100054253 · 15-19.pdf · uploaded 27 Mar 2024Source
  • 29 Building Plan Approval / NA Order for plotted developmentP52100054253 · 15-19.pdf · uploaded 27 Mar 2024Source
  • 30 Building Plan Approval / NA Order for plotted developmentP52100054253 · 16-19.pdf · uploaded 27 Mar 2024Source
  • 31 Building Plan Approval / NA Order for plotted developmentP52100054253 · 17-19.pdf · uploaded 27 Mar 2024Source
  • 32 Building Plan Approval / NA Order for plotted developmentP52100054253 · 18-19.pdf · uploaded 27 Mar 2024Source
  • 33 Building Plan Approval / NA Order for plotted developmentP52100054253 · 19-19.pdf · uploaded 27 Mar 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100054253 · CC.pdf · uploaded 27 Mar 2024Source
  • 1 Copy of Layout Approval (in case of layout)P52100056143 · LAYOUT.pdf · uploaded 19 Apr 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100056143 · PLAN-03-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100056143 · PLAN-03-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentP52100056143 · PLAN-04-25_compressed (1).pdf · uploaded 19 Apr 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentP52100056143 · PLAN-14-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentP52100056143 · PLAN-15-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentP52100056143 · PLAN-16-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentP52100056143 · PLAN-17-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 8 Building Plan Approval / NA Order for plotted developmentP52100056143 · PLAN-18-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 9 Building Plan Approval / NA Order for plotted developmentP52100056143 · PLAN-19-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100056143 · 12320240417_15571737.pdf · uploaded 19 Apr 2024Source
  • 4 Copy of Layout Approval (in case of layout)P52100054253 · PLAN-01-25.pdf · uploaded 19 Apr 2024Source
  • 34 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-02-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 35 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-03-25 (2)_compressed.pdf · uploaded 19 Apr 2024Source
  • 36 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-04-25_compressed (1).pdf · uploaded 19 Apr 2024Source
  • 37 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-05-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 38 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-06-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 39 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-07-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 40 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-08-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 41 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-09-25_compressed (1).pdf · uploaded 19 Apr 2024Source
  • 42 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-10-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 43 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-11-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 44 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-12-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 45 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-13-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 46 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-23-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 47 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-24-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 48 Building Plan Approval / NA Order for plotted developmentP52100054253 · PLAN-25-25_compressed.pdf · uploaded 19 Apr 2024Source
  • 3 Commencement Certificates / NA Order for plotted developmentP52100054253 · 12320240417_15571737.pdf · uploaded 19 Apr 2024Source
  • 2 Declaration about Commencement CertificateP52100054253 · Declaration about Commencement.pdf · uploaded 19 Apr 2024Source
  • 3 Declaration about Commencement CertificateP52100054253 · Declaration about Commencement.pdf · uploaded 19 Apr 2024Source
  • 1 PAN CardP52100056143 · 1 PAN Card (1).pdf · uploaded 20 Apr 2024Source
  • 1 Copy of the legal title reportP52100056143 · STR.pdf · uploaded 20 Apr 2024Source
  • 2 Copy of the legal title reportP52100056143 · STR Full_compressed.pdf · uploaded 20 Apr 2024Source
  • 1 a Details of encumbrances concerned to FinanceP52100056143 · Encum Fin Legal.pdf · uploaded 20 Apr 2024Source
  • 1 b Details of encumbrances concerned to LegalP52100056143 · Encum Fin Legal.pdf · uploaded 20 Apr 2024Source
  • 1 Declaration in FORM BP52100056143 · Form B Promoter.pdf · uploaded 20 Apr 2024Source
  • 1 CERSAI detailsP52100056143 · cersai_LOAN declaration_Kharadi 39 Ph II.pdf · uploaded 20 Apr 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100056143 · Discloser SM.pdf · uploaded 20 Apr 2024Source
  • 1 Proforma of Agreement for saleP52100056143 · Agreement Ph II.pdf · uploaded 20 Apr 2024Source
  • 1 Proforma of Allotment letterP52100056143 · Allotment.pdf · uploaded 20 Apr 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100056143 · Foarmat A.pdf · uploaded 20 Apr 2024Source
  • 1 Deviation Report with respect to Allotment letterP52100056143 · No Deviation Allotment.pdf · uploaded 20 Apr 2024Source
  • 1 Other – TechnicalP52100056143 · Order 50 Decl.pdf · uploaded 20 Apr 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054253 · Ph-1-Arch engg - 20042024.pdf · uploaded 20 Apr 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054253 · Ph-1 Evolvus - Engg Certificate - 18042024.pdf · uploaded 20 Apr 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsP52100056143 · Discloser Vishal Tejwani.pdf · uploaded 22 Apr 2024Source
  • 2 Copy of Layout Approval (in case of layout)P52100056143 · Tower 5,6,7 - Plot areas dwg.pdf · uploaded 23 Apr 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100056143 · Ph-2 Evolvus - Engg Certificate - 22042024.pdf · uploaded 23 Apr 2024Source
  • 1 Declaration about Commencement CertificateP52100056143 · Format D New.pdf · uploaded 25 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100056143 · Form-01.pdf · uploaded 25 Apr 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100056143 · Form 3 No LO_compressed.pdf · uploaded 25 Apr 2024Source
  • 1 Deviation Report with respect to model copy of AgreementP52100056143 · Deviation Agreement_compressed.pdf · uploaded 25 Apr 2024Source
  • 2 CERSAI detailsP52100056143 · CERSAI_Search_Report_BAnk.pdf · uploaded 3 May 2024Source
  • 2 Other – TechnicalP52100056143 · Area Declaration_Kharadi 39 Ph II.pdf · uploaded 7 May 2024Source
  • 1 Other – FinanceP52100056143 · LO NOC.pdf · uploaded 8 May 2024Source
  • 2 Other – FinanceP52100056143 · POA_4609 SP-NP.pdf · uploaded 8 May 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100056143 · 5 Form 3.pdf · uploaded 22 May 2024Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP52100056143 · 3 FORMAT_A_Bank__Kharadi 39 Ph II.pdf · uploaded 22 May 2024Source
  • 3 Other – FinanceP52100056143 · 4 Bank Confirmation Letter.pdf · uploaded 22 May 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054253 · 4 Architect Cerificate Evo-Phase-1.pdf · uploaded 7 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054253 · 5 Architect Cerificate Evo-Phase-1.pdf · uploaded 7 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054253 · 4 Engineers Certificate Form 2 Phase-1.pdf · uploaded 7 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054253 · 5 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 7 Oct 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054253 · 6 Architect Certificate Evo-Phase-1.pdf · uploaded 26 Oct 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054253 · 6 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 26 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100056143 · 2 Architect Certificate Evo-Phase 2.pdf · uploaded 9 Dec 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100056143 · 3 Architect Certificate Evo-Phase 2.pdf · uploaded 9 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100056143 · 3 CA Certificate_compressed.pdf · uploaded 9 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100056143 · 2 Engineer’s Certificate (Form 2) Evo-Phase-2.pdf · uploaded 9 Dec 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100056143 · 3 Engineer’s Certificate (Form 2) Evo-Phase-2.pdf · uploaded 9 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100054253 · RERA FORM 5 Townshine Realties Pvt Ltd Phase 1 .pdf · uploaded 17 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100056143 · Townshine Form 3 - Phase 2.pdf · uploaded 24 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054253 · Townshine Realties Pvt Ltd RERA Certificate Phase 1.pdf · uploaded 24 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054253 · Townshine Realties Pvt Ltd RERA Certificate Phase 1 .pdf · uploaded 24 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100056143 · 4 Evo-Form-1 Phase-2.pdf · uploaded 22 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100056143 · 4 Engineer’s Certificate (Form 2) Evo-Phase-2.pdf · uploaded 22 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054253 · 7 Evo- Form-1 Phase-1.pdf · uploaded 22 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054253 · 7 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 22 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100056143 · Townshine Realites Phase 2 Q3_compressed.pdf · uploaded 31 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054253 · Townshine Realites Phase 1 Q3_compressed.pdf · uploaded 31 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100056143 · Evolvuls T5-T6_compressed.pdf · uploaded 17 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100054253 · Evolvus Ph-I_compressed (2).pdf · uploaded 17 Feb 2025Source
  • 1 PAN CardP52100080891 · PAN.pdf · uploaded 17 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceP52100080891 · No Encum Finance new.pdf · uploaded 17 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceP52100080891 · No Encum Legal.pdf · uploaded 17 Mar 2025Source
  • 1 CERSAI detailsP52100080891 · Cersai Dec.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterP52100080891 · No Devi Allotment.pdf · uploaded 17 Mar 2025Source
  • 1 b Details of encumbrances concerned to LegalP52100080891 · No Encum Finance new.pdf · uploaded 17 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalP52100080891 · No Encum Legal.pdf · uploaded 17 Mar 2025Source
  • 2 Other – TechnicalP52100080891 · Decl Promoter and Architect.pdf · uploaded 17 Mar 2025Source
  • 1 Other – TechnicalP52100080891 · Annex 50.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementP52100080891 · No Devi Agreement_compressed.pdf · uploaded 17 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100080891 · Discloser SM.pdf · uploaded 17 Mar 2025Source
  • 1 PAN CardP52100080891 · PAN.pdf · uploaded 17 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceP52100080891 · No Encum Finance new.pdf · uploaded 17 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceP52100080891 · No Encum Legal.pdf · uploaded 17 Mar 2025Source
  • 1 CERSAI detailsP52100080891 · Cersai Dec.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterP52100080891 · No Devi Allotment.pdf · uploaded 17 Mar 2025Source
  • 1 b Details of encumbrances concerned to LegalP52100080891 · No Encum Finance new.pdf · uploaded 17 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalP52100080891 · No Encum Legal.pdf · uploaded 17 Mar 2025Source
  • 2 Other – TechnicalP52100080891 · Decl Promoter and Architect.pdf · uploaded 17 Mar 2025Source
  • 1 Other – TechnicalP52100080891 · Annex 50.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementP52100080891 · No Devi Agreement_compressed.pdf · uploaded 17 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100080891 · Discloser SM.pdf · uploaded 17 Mar 2025Source
  • 1 PAN CardP52100080891 · PAN.pdf · uploaded 17 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceP52100080891 · No Encum Finance new.pdf · uploaded 17 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceP52100080891 · No Encum Legal.pdf · uploaded 17 Mar 2025Source
  • 1 CERSAI detailsP52100080891 · Cersai Dec.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterP52100080891 · No Devi Allotment.pdf · uploaded 17 Mar 2025Source
  • 1 b Details of encumbrances concerned to LegalP52100080891 · No Encum Finance new.pdf · uploaded 17 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalP52100080891 · No Encum Legal.pdf · uploaded 17 Mar 2025Source
  • 2 Other – TechnicalP52100080891 · Decl Promoter and Architect.pdf · uploaded 17 Mar 2025Source
  • 1 Other – TechnicalP52100080891 · Annex 50.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementP52100080891 · No Devi Agreement_compressed.pdf · uploaded 17 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100080891 · Discloser SM.pdf · uploaded 17 Mar 2025Source
  • 1 PAN CardP52100080891 · PAN.pdf · uploaded 17 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceP52100080891 · No Encum Finance new.pdf · uploaded 17 Mar 2025Source
  • 2 a Details of encumbrances concerned to FinanceP52100080891 · No Encum Legal.pdf · uploaded 17 Mar 2025Source
  • 1 CERSAI detailsP52100080891 · Cersai Dec.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterP52100080891 · No Devi Allotment.pdf · uploaded 17 Mar 2025Source
  • 1 b Details of encumbrances concerned to LegalP52100080891 · No Encum Finance new.pdf · uploaded 17 Mar 2025Source
  • 2 b Details of encumbrances concerned to LegalP52100080891 · No Encum Legal.pdf · uploaded 17 Mar 2025Source
  • 2 Other – TechnicalP52100080891 · Decl Promoter and Architect.pdf · uploaded 17 Mar 2025Source
  • 1 Other – TechnicalP52100080891 · Annex 50.pdf · uploaded 17 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementP52100080891 · No Devi Agreement_compressed.pdf · uploaded 17 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100080891 · Discloser SM.pdf · uploaded 17 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054253 · 8 Architect Certificate Evo-Phase-1.pdf · uploaded 18 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054253 · Townshine Realites Phase 1 Q3 _compressed_compressed.pdf · uploaded 18 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054253 · 8 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 18 Mar 2025Source
  • 1 Declaration in FORM BP52100080891 · Form B Promoter.pdf · uploaded 18 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsP52100080891 · Discloser Vishal Tejwani.pdf · uploaded 18 Mar 2025Source
  • 1 Declaration in FORM BP52100080891 · Form B Promoter.pdf · uploaded 18 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsP52100080891 · Discloser Vishal Tejwani.pdf · uploaded 18 Mar 2025Source
  • 1 Declaration in FORM BP52100080891 · Form B Promoter.pdf · uploaded 18 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsP52100080891 · Discloser Vishal Tejwani.pdf · uploaded 18 Mar 2025Source
  • 1 Declaration in FORM BP52100080891 · Form B Promoter.pdf · uploaded 18 Mar 2025Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsP52100080891 · Discloser Vishal Tejwani.pdf · uploaded 18 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100056143 · CC_Kharadi 39_2025.pdf · uploaded 24 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100056143 · Evolvus Phase II.pdf · uploaded 25 Mar 2025Source
  • 1 Declaration about Commencement CertificateP52100056143 · Format D updated 2025.pdf · uploaded 25 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100054253 · Evolvus.pdf · uploaded 25 Mar 2025Source
  • 1 Proforma of Allotment letterP52100080891 · Allotment.pdf · uploaded 9 Apr 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)P52100080891 · FORMAT A UPDATED.pdf · uploaded 9 Apr 2025Source
  • 1 Proforma of Allotment letterP52100080891 · Allotment.pdf · uploaded 9 Apr 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)P52100080891 · FORMAT A UPDATED.pdf · uploaded 9 Apr 2025Source
  • 1 Proforma of Allotment letterP52100080891 · Allotment.pdf · uploaded 9 Apr 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)P52100080891 · FORMAT A UPDATED.pdf · uploaded 9 Apr 2025Source
  • 1 Proforma of Allotment letterP52100080891 · Allotment.pdf · uploaded 9 Apr 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)P52100080891 · FORMAT A UPDATED.pdf · uploaded 9 Apr 2025Source
  • 1 Proforma of Agreement for saleP52100080891 · Agreement.pdf · uploaded 10 Apr 2025Source
  • 1 Proforma of Agreement for saleP52100080891 · Agreement.pdf · uploaded 10 Apr 2025Source
  • 1 Proforma of Agreement for saleP52100080891 · Agreement.pdf · uploaded 10 Apr 2025Source
  • 1 Proforma of Agreement for saleP52100080891 · Agreement.pdf · uploaded 10 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100056143 · Evolvus II 31 march 2025_compressed.pdf · uploaded 11 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100054253 · Evolvus I 31 march 2025_compressed_compressed.pdf · uploaded 11 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P52100080891 · Format b bank.pdf · uploaded 12 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P52100080891 · Format b bank.pdf · uploaded 12 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P52100080891 · Format b bank.pdf · uploaded 12 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P52100080891 · Format b bank.pdf · uploaded 12 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100056143 · Phase-2 Form-2A-24-25.pdf · uploaded 15 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100054253 · Phase-1 Form-2A-24-25.pdf · uploaded 15 Apr 2025Source
  • 1 Copy of the legal title reportP52100080891 · STR I.pdf · uploaded 23 Apr 2025Source
  • 2 Copy of the legal title reportP52100080891 · STR II_compressed.pdf · uploaded 23 Apr 2025Source
  • 1 Copy of the legal title reportP52100080891 · STR I.pdf · uploaded 23 Apr 2025Source
  • 2 Copy of the legal title reportP52100080891 · STR II_compressed.pdf · uploaded 23 Apr 2025Source
  • 1 Copy of the legal title reportP52100080891 · STR I.pdf · uploaded 23 Apr 2025Source
  • 2 Copy of the legal title reportP52100080891 · STR II_compressed.pdf · uploaded 23 Apr 2025Source
  • 1 Copy of the legal title reportP52100080891 · STR I.pdf · uploaded 23 Apr 2025Source
  • 2 Copy of the legal title reportP52100080891 · STR II_compressed.pdf · uploaded 23 Apr 2025Source
  • 1 Copy of Layout Approval (in case of layout)P52100080891 · PLAN-01-27Bldg Layout.pdf · uploaded 2 May 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100080891 · CC-4036-24 DT 18-03-2025_compressed.pdf · uploaded 2 May 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-02-27Parking Layout1.pdf · uploaded 2 May 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-03-27Parking Layout2.pdf · uploaded 2 May 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-04-27_compressed.pdf · uploaded 2 May 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-20-27compressed.pdf · uploaded 2 May 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-21-27compressed.pdf · uploaded 2 May 2025Source
  • 1 Copy of Layout Approval (in case of layout)P52100080891 · PLAN-01-27Bldg Layout.pdf · uploaded 2 May 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100080891 · CC-4036-24 DT 18-03-2025_compressed.pdf · uploaded 2 May 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-02-27Parking Layout1.pdf · uploaded 2 May 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-03-27Parking Layout2.pdf · uploaded 2 May 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-04-27_compressed.pdf · uploaded 2 May 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-20-27compressed.pdf · uploaded 2 May 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-21-27compressed.pdf · uploaded 2 May 2025Source
  • 1 Copy of Layout Approval (in case of layout)P52100080891 · PLAN-01-27Bldg Layout.pdf · uploaded 2 May 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100080891 · CC-4036-24 DT 18-03-2025_compressed.pdf · uploaded 2 May 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-02-27Parking Layout1.pdf · uploaded 2 May 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-03-27Parking Layout2.pdf · uploaded 2 May 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-04-27_compressed.pdf · uploaded 2 May 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-20-27compressed.pdf · uploaded 2 May 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-21-27compressed.pdf · uploaded 2 May 2025Source
  • 1 Copy of Layout Approval (in case of layout)P52100080891 · PLAN-01-27Bldg Layout.pdf · uploaded 2 May 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100080891 · CC-4036-24 DT 18-03-2025_compressed.pdf · uploaded 2 May 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-02-27Parking Layout1.pdf · uploaded 2 May 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-03-27Parking Layout2.pdf · uploaded 2 May 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-04-27_compressed.pdf · uploaded 2 May 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-20-27compressed.pdf · uploaded 2 May 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentP52100080891 · PLAN-21-27compressed.pdf · uploaded 2 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100056143 · Townshine Realites Phase 2 Q4_compressed.pdf · uploaded 6 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100054253 · Townshine Realites Phase 1 Q4_compressed.pdf · uploaded 6 May 2025Source
  • 1 Declaration about Commencement CertificateP52100080891 · Form D for CC-4036-24 DECLARTION.pdf · uploaded 7 May 2025Source
  • 1 Declaration about Commencement CertificateP52100080891 · Form D for CC-4036-24 DECLARTION.pdf · uploaded 7 May 2025Source
  • 1 Declaration about Commencement CertificateP52100080891 · Form D for CC-4036-24 DECLARTION.pdf · uploaded 7 May 2025Source
  • 1 Declaration about Commencement CertificateP52100080891 · Form D for CC-4036-24 DECLARTION.pdf · uploaded 7 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100080891 · Form 3 updated_compressed.pdf · uploaded 8 May 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectP52100080891 · REVISED DISCLOSURE CA.pdf · uploaded 8 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100080891 · Form 3 updated_compressed.pdf · uploaded 8 May 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectP52100080891 · REVISED DISCLOSURE CA.pdf · uploaded 8 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100080891 · Form 3 updated_compressed.pdf · uploaded 8 May 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectP52100080891 · REVISED DISCLOSURE CA.pdf · uploaded 8 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100080891 · Form 3 updated_compressed.pdf · uploaded 8 May 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectP52100080891 · REVISED DISCLOSURE CA.pdf · uploaded 8 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100080891 · Form I.pdf · uploaded 9 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100080891 · Form II.pdf · uploaded 9 May 2025Source
  • 1 Other – FinanceP52100080891 · NOC LO.pdf · uploaded 9 May 2025Source
  • 2 Other – FinanceP52100080891 · POA Pashankar Nilkanth Sagar.pdf · uploaded 9 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100080891 · Form I.pdf · uploaded 9 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100080891 · Form II.pdf · uploaded 9 May 2025Source
  • 1 Other – FinanceP52100080891 · NOC LO.pdf · uploaded 9 May 2025Source
  • 2 Other – FinanceP52100080891 · POA Pashankar Nilkanth Sagar.pdf · uploaded 9 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100080891 · Form I.pdf · uploaded 9 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100080891 · Form II.pdf · uploaded 9 May 2025Source
  • 1 Other – FinanceP52100080891 · NOC LO.pdf · uploaded 9 May 2025Source
  • 2 Other – FinanceP52100080891 · POA Pashankar Nilkanth Sagar.pdf · uploaded 9 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100080891 · Form I.pdf · uploaded 9 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100080891 · Form II.pdf · uploaded 9 May 2025Source
  • 1 Other – FinanceP52100080891 · NOC LO.pdf · uploaded 9 May 2025Source
  • 2 Other – FinanceP52100080891 · POA Pashankar Nilkanth Sagar.pdf · uploaded 9 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100056143 · 5 Evo-Form-1 Phase-2.pdf · uploaded 10 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100056143 · 5 Engineer’s Certificate (Form 2) Evo-Phase-2.pdf · uploaded 10 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100054253 · 9 Architect Certificate Evo-Phase-1.pdf · uploaded 10 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100054253 · 9 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 10 May 2025Source
  • 2 Disclosure for secured/unsecured finance availed for the projectP52100080891 · Discloser Promoter Fin.pdf · uploaded 10 May 2025Source
  • 2 Disclosure for secured/unsecured finance availed for the projectP52100080891 · Discloser Promoter Fin.pdf · uploaded 10 May 2025Source
  • 2 Disclosure for secured/unsecured finance availed for the projectP52100080891 · Discloser Promoter Fin.pdf · uploaded 10 May 2025Source
  • 2 Disclosure for secured/unsecured finance availed for the projectP52100080891 · Discloser Promoter Fin.pdf · uploaded 10 May 2025Source
  • 2 Copy of Layout Approval (in case of layout)P52100080891 · Layout Hatching.pdf · uploaded 8 Jul 2025Source
  • 3 Copy of Layout Approval (in case of layout)P52100080891 · Commercial Hatching_compressed.pdf · uploaded 8 Jul 2025Source
  • 1 Other – LegalP52100080891 · NOC M2 Builtcon.pdf · uploaded 8 Jul 2025Source
  • 2 Copy of Layout Approval (in case of layout)P52100080891 · Layout Hatching.pdf · uploaded 8 Jul 2025Source
  • 3 Copy of Layout Approval (in case of layout)P52100080891 · Commercial Hatching_compressed.pdf · uploaded 8 Jul 2025Source
  • 1 Other – LegalP52100080891 · NOC M2 Builtcon.pdf · uploaded 8 Jul 2025Source
  • 2 Copy of Layout Approval (in case of layout)P52100080891 · Layout Hatching.pdf · uploaded 8 Jul 2025Source
  • 3 Copy of Layout Approval (in case of layout)P52100080891 · Commercial Hatching_compressed.pdf · uploaded 8 Jul 2025Source
  • 1 Other – LegalP52100080891 · NOC M2 Builtcon.pdf · uploaded 8 Jul 2025Source
  • 2 Copy of Layout Approval (in case of layout)P52100080891 · Layout Hatching.pdf · uploaded 8 Jul 2025Source
  • 3 Copy of Layout Approval (in case of layout)P52100080891 · Commercial Hatching_compressed.pdf · uploaded 8 Jul 2025Source
  • 1 Other – LegalP52100080891 · NOC M2 Builtcon.pdf · uploaded 8 Jul 2025Source
  • 4 Other – TechnicalP52100080891 · Additional Fees Demand Draft.pdf · uploaded 21 Jul 2025Source
  • 3 Other – TechnicalP52100080891 · Additional Fees Letter.pdf · uploaded 21 Jul 2025Source
  • 4 Other – TechnicalP52100080891 · Additional Fees Demand Draft.pdf · uploaded 21 Jul 2025Source
  • 3 Other – TechnicalP52100080891 · Additional Fees Letter.pdf · uploaded 21 Jul 2025Source
  • 4 Other – TechnicalP52100080891 · Additional Fees Demand Draft.pdf · uploaded 21 Jul 2025Source
  • 3 Other – TechnicalP52100080891 · Additional Fees Letter.pdf · uploaded 21 Jul 2025Source
  • 4 Other – TechnicalP52100080891 · Additional Fees Demand Draft.pdf · uploaded 21 Jul 2025Source
  • 3 Other – TechnicalP52100080891 · Additional Fees Letter.pdf · uploaded 21 Jul 2025Source
  • 5 Other – TechnicalP52100080891 · Receipt Additional Area.pdf · uploaded 23 Jul 2025Source
  • 5 Other – TechnicalP52100080891 · Receipt Additional Area.pdf · uploaded 23 Jul 2025Source
  • 5 Other – TechnicalP52100080891 · Receipt Additional Area.pdf · uploaded 23 Jul 2025Source
  • 5 Other – TechnicalP52100080891 · Receipt Additional Area.pdf · uploaded 23 Jul 2025Source
  • 6 Other – TechnicalP52100080891 · cc email verification.pdf · uploaded 28 Jul 2025Source
  • 6 Other – TechnicalP52100080891 · cc email verification.pdf · uploaded 28 Jul 2025Source
  • 6 Other – TechnicalP52100080891 · cc email verification.pdf · uploaded 28 Jul 2025Source
  • 6 Other – TechnicalP52100080891 · cc email verification.pdf · uploaded 28 Jul 2025Source
  • Form 1P52100056143 · Form 1 Evo Phase-2.pdf · uploaded 6 Nov 2025Source
  • Form 2P52100056143 · Form 2 Evo Phase-2.pdf · uploaded 6 Nov 2025Source
  • Form 3P52100056143 · Form 3 Evo Phase 2_compressed.pdf · uploaded 6 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP52100056143 · Evolvus II 30-09-25_compressed.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 1P52100054253 · 12 Architect Certificate Evo-Phase-1.pdf · uploaded 29 Nov 2025Source
  • Withdrawal Update Form 2P52100054253 · 12 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 29 Nov 2025Source
  • Withdrawal Update Form 3P52100054253 · Evo Phase 1_compressed.pdf · uploaded 29 Nov 2025Source
  • Form 1P52100080891 · Form 1 Architect Certificate.pdf · uploaded 29 Nov 2025Source
  • Form 2P52100080891 · Form 2 Engg Certtificate.pdf · uploaded 29 Nov 2025Source
  • Form 3P52100080891 · Townshine FORM 3 Phase 3 Q2 Evol.pdf · uploaded 29 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP52100080891 · Evolvus III 30-09-25.pdf · uploaded 29 Nov 2025Source
  • Form 5 (FY 2024-2025)P52100056143 · Townshine Phase 2 FORM 5.pdf · uploaded 10 Dec 2025Source
  • Form 5 (FY 2024-2025)P52100054253 · Townshine Phase 1 FORM 5.pdf · uploaded 10 Dec 2025Source
  • Withdrawal Update Form 1P52100054253 · 12 Architect Certificate Evo-Phase-1.pdf · uploaded 1 Jan 2026Source
  • Withdrawal Update Form 2P52100054253 · 12 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 1 Jan 2026Source
  • Withdrawal Update Form 3P52100054253 · Evo Phase 1_compressed.pdf · uploaded 1 Jan 2026Source
  • Form 1P52100056143 · 8 Evo-Form-1 Phase-2.pdf · uploaded 23 Jan 2026Source
  • Form 2P52100056143 · 8 Engineers Certificate Form 2 Evo Phase 2.pdf · uploaded 23 Jan 2026Source
  • Form 3P52100056143 · Townshine Phase 2 Q3_compressed.pdf · uploaded 23 Jan 2026Source
  • Disclosure of Sold and Booked InventoryP52100056143 · II 31 12 2025 compressed.pdf · uploaded 23 Jan 2026Source
  • Form 1P52100080891 · Architect Certificate-03.pdf · uploaded 23 Jan 2026Source
  • Form 2P52100080891 · Engg Certtificate 03 Phase-3.pdf · uploaded 23 Jan 2026Source
  • Form 3P52100080891 · Townshine Phase 3 Q3 compressed.pdf · uploaded 23 Jan 2026Source
  • Disclosure of Sold and Booked InventoryP52100080891 · III 31122025.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 1P52100054253 · 12 Architect Certificate Evo-Phase-1.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 1P52100054253 · 12 Architect Certificate Evo-Phase-1.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 2P52100054253 · 12 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 2P52100054253 · 12 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 3P52100054253 · Townshine Phase 1 Q3_compressed.pdf · uploaded 17 Feb 2026Source
  • Withdrawal Update Form 3P52100054253 · Townshine Phase 1 Q3_compressed.pdf · uploaded 17 Feb 2026Source
  • Form 1P52100056143 · 9 Evo-Form-1 Phase-2.pdf · uploaded 25 Apr 2026Source
  • Form 2P52100056143 · Engineer Certificate Form 2 Evo-Phase-2.pdf · uploaded 25 Apr 2026Source
  • Form 3P52100056143 · Townshine Phase 2 Q4_compressed.pdf · uploaded 25 Apr 2026Source
  • Disclosure of Sold and Booked InventoryP52100056143 · Ephelia Ph-II - 31-03-26.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 1P52100054253 · 14 Architect Certificate Evo-Phase-1.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 2P52100054253 · 14 Engineers Certificate Form 2 Phase-1.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 3P52100054253 · Townshine Phase 1 Q4_compressed.pdf · uploaded 25 Apr 2026Source
  • Form 1P52100080891 · Architect Certificate-04.pdf · uploaded 25 Apr 2026Source
  • Form 2P52100080891 · 4 Engineer Certificate Form 2 Evo-Phase-3.pdf · uploaded 25 Apr 2026Source
  • Form 3P52100080891 · Townshine Phase 3 Q4_compressed.pdf · uploaded 25 Apr 2026Source
  • Disclosure of Sold and Booked InventoryP52100080891 · Evolvus III 31-03-26.pdf · uploaded 25 Apr 2026Source
  • Form 2A (FY 2024-2025)P52100056143 · Phase-2 Form-2A-24-25.pdf · uploaded 22 Jul 2026Source
  • Form 2A (FY 2025-2026)P52100056143 · Phase-2 Form-2A-25-26.pdf · uploaded 22 Jul 2026Source
  • Form 2A (FY 2023-2024)P52100054253 · Phase-1 Form-2A-23-24.pdf · uploaded 22 Jul 2026Source
  • Form 2A (FY 2024-2025)P52100054253 · Phase-1 Form-2A-24-25.pdf · uploaded 22 Jul 2026Source
  • Form 2A (FY 2025-2026)P52100054253 · Phase-1 Form-2A-25-26.pdf · uploaded 22 Jul 2026Source
  • Form 2A (FY 2025-2026)P52100080891 · Phase-3 Form-2A-25-26.pdf · uploaded 22 Jul 2026Source
  • Form 1P52100056143 · 10 Evo-Form-1 Phase-2.pdf · uploaded 23 Jul 2026Source
  • Form 2P52100056143 · 10 Engineers Certificate Form 2 Evo-Phase-2.pdf · uploaded 23 Jul 2026Source
  • Form 3P52100056143 · TOWNSHINE PH2 - FY 202627 - Q1 - FORM 3_compressed.pdf · uploaded 23 Jul 2026Source
  • Disclosure of Sold and Booked InventoryP52100056143 · Evolvus II sold unsold.pdf · uploaded 23 Jul 2026Source
  • Withdrawal Update Form 1P52100054253 · 16 Architect Certificate Evo-Phase-1.pdf · uploaded 23 Jul 2026Source
  • Withdrawal Update Form 2P52100054253 · 16 Engineers Certificate Form 2 Phase-1.pdf · uploaded 23 Jul 2026Source
  • Withdrawal Update Form 3P52100054253 · Townshine Phase 1 Q4_compressed.pdf · uploaded 23 Jul 2026Source
  • Form 1P52100080891 · 5 Evo-Form-1 Phase-3.pdf · uploaded 23 Jul 2026Source
  • Form 2P52100080891 · 5 Engineer Certificate Form 2 Evo-Phase-3.pdf · uploaded 23 Jul 2026Source
  • Form 3P52100080891 · TOWNSHINE PH3 - FY 2026-27 -Q1 - FORM 3_compressed.pdf · uploaded 23 Jul 2026Source
  • Disclosure of Sold and Booked InventoryP52100080891 · Evolvus III sold unsold.pdf · uploaded 23 Jul 2026Source

Technical

  • DocumentP52100054253 · 1-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 2-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 3-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 4-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 5-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 6-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 7-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 8-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 9-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 10-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 11-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 12-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 13-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 17-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 18-18.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · LAYOUT.pdf · uploaded 28 Dec 2023Source
  • DocumentP52100054253 · 03-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 04-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 05-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 06-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 07-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 09-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 09-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 10-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 11-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 12-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 13-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 14-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 15-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 15-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 16-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 17-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 18-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 19-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 1-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100054253 · 02-19.pdf · uploaded 27 Mar 2024Source
  • DocumentP52100056143 · PLAN-03-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100056143 · PLAN-03-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100056143 · PLAN-04-25_compressed (1).pdf · uploaded 19 Apr 2024Source
  • DocumentP52100056143 · PLAN-14-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100056143 · PLAN-15-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100056143 · PLAN-16-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100056143 · PLAN-17-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100056143 · PLAN-18-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100056143 · PLAN-19-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100056143 · LAYOUT.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-01-25.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-02-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-03-25 (2)_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-04-25_compressed (1).pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-05-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-06-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-07-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-08-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-09-25_compressed (1).pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-10-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-11-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-12-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-13-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-23-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-24-25_compressed.pdf · uploaded 19 Apr 2024Source
  • DocumentP52100054253 · PLAN-25-25_compressed.pdf · uploaded 19 Apr 2024Source
  • Other – TechnicalP52100056143 · Order 50 Decl.pdf · uploaded 20 Apr 2024Source
  • DocumentP52100056143 · Tower 5,6,7 - Plot areas dwg.pdf · uploaded 23 Apr 2024Source
  • Other – TechnicalP52100056143 · Area Declaration_Kharadi 39 Ph II.pdf · uploaded 7 May 2024Source
  • Other – TechnicalP52100080891 · Annex 50.pdf · uploaded 17 Mar 2025Source
  • Other – TechnicalP52100080891 · Decl Promoter and Architect.pdf · uploaded 17 Mar 2025Source
  • Other – TechnicalP52100080891 · Annex 50.pdf · uploaded 17 Mar 2025Source
  • Other – TechnicalP52100080891 · Decl Promoter and Architect.pdf · uploaded 17 Mar 2025Source
  • Other – TechnicalP52100080891 · Annex 50.pdf · uploaded 17 Mar 2025Source
  • Other – TechnicalP52100080891 · Decl Promoter and Architect.pdf · uploaded 17 Mar 2025Source
  • Other – TechnicalP52100080891 · Annex 50.pdf · uploaded 17 Mar 2025Source
  • Other – TechnicalP52100080891 · Decl Promoter and Architect.pdf · uploaded 17 Mar 2025Source
  • DocumentP52100080891 · PLAN-01-27Bldg Layout.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-01-27Bldg Layout.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-01-27Bldg Layout.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-01-27Bldg Layout.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-02-27Parking Layout1.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-03-27Parking Layout2.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-04-27_compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-20-27compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-21-27compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-02-27Parking Layout1.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-03-27Parking Layout2.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-04-27_compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-20-27compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-21-27compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-02-27Parking Layout1.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-03-27Parking Layout2.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-04-27_compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-20-27compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-21-27compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-02-27Parking Layout1.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-03-27Parking Layout2.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-04-27_compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-20-27compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · PLAN-21-27compressed.pdf · uploaded 2 May 2025Source
  • DocumentP52100080891 · Layout Hatching.pdf · uploaded 8 Jul 2025Source
  • DocumentP52100080891 · Commercial Hatching_compressed.pdf · uploaded 8 Jul 2025Source
  • DocumentP52100080891 · Layout Hatching.pdf · uploaded 8 Jul 2025Source
  • DocumentP52100080891 · Commercial Hatching_compressed.pdf · uploaded 8 Jul 2025Source
  • DocumentP52100080891 · Layout Hatching.pdf · uploaded 8 Jul 2025Source
  • DocumentP52100080891 · Commercial Hatching_compressed.pdf · uploaded 8 Jul 2025Source
  • DocumentP52100080891 · Layout Hatching.pdf · uploaded 8 Jul 2025Source
  • DocumentP52100080891 · Commercial Hatching_compressed.pdf · uploaded 8 Jul 2025Source
  • Other – TechnicalP52100080891 · Additional Fees Letter.pdf · uploaded 21 Jul 2025Source
  • Other – TechnicalP52100080891 · Additional Fees Demand Draft.pdf · uploaded 21 Jul 2025Source
  • Other – TechnicalP52100080891 · Additional Fees Letter.pdf · uploaded 21 Jul 2025Source
  • Other – TechnicalP52100080891 · Additional Fees Demand Draft.pdf · uploaded 21 Jul 2025Source
  • Other – TechnicalP52100080891 · Additional Fees Letter.pdf · uploaded 21 Jul 2025Source
  • Other – TechnicalP52100080891 · Additional Fees Demand Draft.pdf · uploaded 21 Jul 2025Source
  • Other – TechnicalP52100080891 · Additional Fees Letter.pdf · uploaded 21 Jul 2025Source
  • Other – TechnicalP52100080891 · Additional Fees Demand Draft.pdf · uploaded 21 Jul 2025Source
  • Other – TechnicalP52100080891 · Receipt Additional Area.pdf · uploaded 23 Jul 2025Source
  • Other – TechnicalP52100080891 · Receipt Additional Area.pdf · uploaded 23 Jul 2025Source
  • Other – TechnicalP52100080891 · Receipt Additional Area.pdf · uploaded 23 Jul 2025Source
  • Other – TechnicalP52100080891 · Receipt Additional Area.pdf · uploaded 23 Jul 2025Source
  • Other – TechnicalP52100080891 · cc email verification.pdf · uploaded 28 Jul 2025Source
  • Other – TechnicalP52100080891 · cc email verification.pdf · uploaded 28 Jul 2025Source
  • Other – TechnicalP52100080891 · cc email verification.pdf · uploaded 28 Jul 2025Source
  • Other – TechnicalP52100080891 · cc email verification.pdf · uploaded 28 Jul 2025Source
  • OthersP52100054253 · RERA.pdf · uploaded 24 Nov 2025Source

Technical (Architect)

  • DocumentP52100056143 · Form-01.pdf · uploaded 25 Apr 2024Source
  • DocumentP52100054253 · 4 Architect Cerificate Evo-Phase-1.pdf · uploaded 7 Oct 2024Source
  • DocumentP52100054253 · 5 Architect Cerificate Evo-Phase-1.pdf · uploaded 7 Oct 2024Source
  • DocumentP52100054253 · 6 Architect Certificate Evo-Phase-1.pdf · uploaded 26 Oct 2024Source
  • DocumentP52100056143 · 2 Architect Certificate Evo-Phase 2.pdf · uploaded 9 Dec 2024Source
  • DocumentP52100056143 · 3 Architect Certificate Evo-Phase 2.pdf · uploaded 9 Dec 2024Source
  • DocumentP52100056143 · 4 Evo-Form-1 Phase-2.pdf · uploaded 22 Jan 2025Source
  • DocumentP52100054253 · 7 Evo- Form-1 Phase-1.pdf · uploaded 22 Jan 2025Source
  • DocumentP52100054253 · 8 Architect Certificate Evo-Phase-1.pdf · uploaded 18 Mar 2025Source
  • DocumentP52100080891 · Form I.pdf · uploaded 9 May 2025Source
  • DocumentP52100080891 · Form I.pdf · uploaded 9 May 2025Source
  • DocumentP52100080891 · Form I.pdf · uploaded 9 May 2025Source
  • DocumentP52100080891 · Form I.pdf · uploaded 9 May 2025Source
  • DocumentP52100056143 · 5 Evo-Form-1 Phase-2.pdf · uploaded 10 May 2025Source
  • DocumentP52100054253 · 9 Architect Certificate Evo-Phase-1.pdf · uploaded 10 May 2025Source
  • DocumentP52100054253 · 16 Architect Certificate Evo-Phase-1.pdf · uploaded 23 Jul 2026Source

Technical (Engineer)

  • DocumentP52100056143 · Ph-2 Evolvus - Engg Certificate - 22042024.pdf · uploaded 23 Apr 2024Source
  • DocumentP52100054253 · 4 Engineers Certificate Form 2 Phase-1.pdf · uploaded 7 Oct 2024Source
  • DocumentP52100054253 · 5 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 7 Oct 2024Source
  • DocumentP52100054253 · 6 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 26 Oct 2024Source
  • DocumentP52100056143 · 2 Engineer’s Certificate (Form 2) Evo-Phase-2.pdf · uploaded 9 Dec 2024Source
  • DocumentP52100056143 · 3 Engineer’s Certificate (Form 2) Evo-Phase-2.pdf · uploaded 9 Dec 2024Source
  • DocumentP52100056143 · 4 Engineer’s Certificate (Form 2) Evo-Phase-2.pdf · uploaded 22 Jan 2025Source
  • DocumentP52100054253 · 7 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 22 Jan 2025Source
  • DocumentP52100054253 · 8 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 18 Mar 2025Source
  • DocumentP52100080891 · Form II.pdf · uploaded 9 May 2025Source
  • DocumentP52100080891 · Form II.pdf · uploaded 9 May 2025Source
  • DocumentP52100080891 · Form II.pdf · uploaded 9 May 2025Source
  • DocumentP52100080891 · Form II.pdf · uploaded 9 May 2025Source
  • DocumentP52100056143 · 5 Engineer’s Certificate (Form 2) Evo-Phase-2.pdf · uploaded 10 May 2025Source
  • DocumentP52100054253 · 9 Engineers Certificate (Form 2) Phase-1.pdf · uploaded 10 May 2025Source
  • DocumentP52100054253 · 16 Engineers Certificate Form 2 Phase-1.pdf · uploaded 23 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals39/1

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Phases
3
Unit types
2BHK, 3BHK, Office space, Shop, 4BHK, 1RK1,119 units in all
Address
39/1, Kharadi, KharadiPIN 411014
Village
Kharadi
Designated bank account
85
Developed in phases
Yes
Also registered as
Evolvus Phase-I, Evolvus Phase-II, Evolvus Phase-III

Survey, CTS, gat or plot numbers

39/1

Boundaries

North
Adj Plot S No 39-1 P
South
Adj Plot S No 39-P
East
18 M Wide Dp Road
West
45 M Wide Dp Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking1,119 units

591 of 1,119 units booked (53%), as the promoter reported to MahaRERA

2BHK · 398 units3BHK · 519 unitsOffice space · 72 unitsShop · 25 units4BHK · 104 units1RK · 1 unit
RERABuildingTypeCarpet areaUnitsBooked
P52100054253Tower-012BHK63.86 sq m · 687 sq ft2323
P52100054253Tower-012BHK77.93 sq m · 839 sq ft11
P52100054253Tower-013BHK92.07 sq m · 991 sq ft2724
P52100054253Tower-013BHK94.23 sq m · 1,014 sq ft208
P52100054253Tower-013BHK98.09 sq m · 1,056 sq ft2120
P52100054253Tower-013BHK98.32 sq m · 1,058 sq ft219
P52100054253Tower-013BHK99.87 sq m · 1,075 sq ft278
P52100054253Tower-01Office space104.97 sq m · 1,130 sq ft30
Show all 99 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P52100054253Tower-01Office space143.44 sq m · 1,544 sq ft30
P52100054253Tower-01Office space146.66 sq m · 1,579 sq ft30
P52100054253Tower-01Office space355.25 sq m · 3,824 sq ft30
P52100054253Tower-01Shop189.87 sq m · 2,044 sq ft10
P52100054253Tower-01Shop198.6 sq m · 2,138 sq ft10
P52100054253Tower-01Shop200.02 sq m · 2,153 sq ft10
P52100054253Tower-01Shop202.68 sq m · 2,182 sq ft10
P52100054253Tower-01Shop257.1 sq m · 2,767 sq ft10
P52100054253Tower-022BHK71.51 sq m · 770 sq ft2121
P52100054253Tower-022BHK76.47 sq m · 823 sq ft2725
P52100054253Tower-022BHK77.93 sq m · 839 sq ft56
P52100054253Tower-023BHK94.23 sq m · 1,014 sq ft1611
P52100054253Tower-023BHK99.87 sq m · 1,075 sq ft2718
P52100054253Tower-02Office space109.97 sq m · 1,184 sq ft30
P52100054253Tower-02Office space112.5 sq m · 1,211 sq ft30
P52100054253Tower-02Office space169.7 sq m · 1,827 sq ft30
P52100054253Tower-02Shop192.06 sq m · 2,067 sq ft10
P52100054253Tower-02Shop192.06 sq m · 2,067 sq ft10
P52100054253Tower-02Shop227.98 sq m · 2,454 sq ft10
P52100054253Tower-032BHK71.51 sq m · 770 sq ft2120
P52100054253Tower-032BHK76.47 sq m · 823 sq ft2726
P52100054253Tower-032BHK77.93 sq m · 839 sq ft54
P52100054253Tower-033BHK94.23 sq m · 1,014 sq ft1614
P52100054253Tower-033BHK99.87 sq m · 1,075 sq ft2721
P52100054253Tower-03Office space109.97 sq m · 1,184 sq ft30
P52100054253Tower-03Office space112.5 sq m · 1,211 sq ft30
P52100054253Tower-03Office space167.18 sq m · 1,800 sq ft30
P52100054253Tower-03Shop189.88 sq m · 2,044 sq ft10
P52100054253Tower-03Shop194.24 sq m · 2,091 sq ft10
P52100054253Tower-03Shop275.18 sq m · 2,962 sq ft10
P52100054253Tower-042BHK71.51 sq m · 770 sq ft2120
P52100054253Tower-042BHK76.47 sq m · 823 sq ft2726
P52100054253Tower-042BHK77.93 sq m · 839 sq ft55
P52100054253Tower-043BHK94.23 sq m · 1,014 sq ft1610
P52100054253Tower-043BHK99.87 sq m · 1,075 sq ft2723
P52100054253Tower-04Office space109.97 sq m · 1,184 sq ft30
P52100054253Tower-04Office space113.76 sq m · 1,225 sq ft30
P52100054253Tower-04Office space168.44 sq m · 1,813 sq ft30
P52100054253Tower-04Shop191.33 sq m · 2,059 sq ft10
P52100054253Tower-04Shop192.79 sq m · 2,075 sq ft10
P52100054253Tower-04Shop229.54 sq m · 2,471 sq ft10
P52100056143Tower-052BHK71.51 sq m · 770 sq ft2120
P52100056143Tower-052BHK76.47 sq m · 823 sq ft2724
P52100056143Tower-052BHK77.93 sq m · 839 sq ft512
P52100056143Tower-053BHK94.23 sq m · 1,014 sq ft162
P52100056143Tower-053BHK99.87 sq m · 1,075 sq ft2721
P52100056143Tower-05Office space112.5 sq m · 1,211 sq ft30
P52100056143Tower-05Office space168.44 sq m · 1,813 sq ft60
P52100056143Tower-05Shop194.23 sq m · 2,091 sq ft10
P52100056143Tower-05Shop279.54 sq m · 3,009 sq ft10
P52100056143Tower-05Shop288.8 sq m · 3,109 sq ft10
P52100056143Tower-062BHK71.51 sq m · 770 sq ft2113
P52100056143Tower-062BHK76.47 sq m · 823 sq ft2717
P52100056143Tower-062BHK77.93 sq m · 839 sq ft53
P52100056143Tower-063BHK94.23 sq m · 1,014 sq ft164
P52100056143Tower-063BHK99.87 sq m · 1,075 sq ft2713
P52100056143Tower-06Office space165.92 sq m · 1,786 sq ft30
P52100056143Tower-06Office space169.7 sq m · 1,827 sq ft30
P52100056143Tower-06Shop276.18 sq m · 2,973 sq ft10
P52100056143Tower-06Shop288.8 sq m · 3,109 sq ft10
P52100056143Tower-072BHK71.51 sq m · 770 sq ft210
P52100056143Tower-072BHK76.46 sq m · 823 sq ft260
P52100056143Tower-072BHK77.93 sq m · 839 sq ft50
P52100056143Tower-072BHK83.93 sq m · 903 sq ft10
P52100056143Tower-073BHK94.23 sq m · 1,014 sq ft160
P52100056143Tower-073BHK99.87 sq m · 1,075 sq ft250
P52100056143Tower-07Office space109.97 sq m · 1,184 sq ft30
P52100056143Tower-07Office space113.76 sq m · 1,225 sq ft30
P52100056143Tower-07Office space167.18 sq m · 1,800 sq ft30
P52100056143Tower-07Shop192.06 sq m · 2,067 sq ft10
P52100056143Tower-07Shop194.24 sq m · 2,091 sq ft10
P52100056143Tower-07Shop232.72 sq m · 2,505 sq ft10
P52100054253Tower-132BHK90.14 sq m · 970 sq ft40
P52100054253Tower-133BHK108.27 sq m · 1,165 sq ft5028
P52100054253Tower-133BHK108.67 sq m · 1,170 sq ft5342
P52100054253Tower-143BHK120.66 sq m · 1,299 sq ft44
P52100054253Tower-144BHK142.15 sq m · 1,530 sq ft5015
P52100054253Tower-144BHK149.63 sq m · 1,611 sq ft5430
P52100080891Tower 81RK43.76 sq m · 471 sq ft10
P52100080891Tower 82BHK71.51 sq m · 770 sq ft210
P52100080891Tower 82BHK76.46 sq m · 823 sq ft250
P52100080891Tower 82BHK77.93 sq m · 839 sq ft50
P52100080891Tower 82BHK83.93 sq m · 903 sq ft10
P52100080891Tower 83BHK94.24 sq m · 1,014 sq ft160
P52100080891Tower 83BHK99.87 sq m · 1,075 sq ft240
P52100080891Tower 8Office space109.97 sq m · 1,184 sq ft30
P52100080891Tower 8Office space112.5 sq m · 1,211 sq ft30
P52100080891Tower 8Office space169.7 sq m · 1,827 sq ft30
P52100080891Tower 8Shop189.87 sq m · 2,044 sq ft10
P52100080891Tower 8Shop194.23 sq m · 2,091 sq ft10
P52100080891Tower 8Shop263.9 sq m · 2,841 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals16

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectArJay Aeram—P52100056143
ArchitectArJay Aeram—P52100080891
ArchitectJay Aeram—P52100054253
ArchitectJay Aeram—P52100080891
ArchitectJay Aeram—P52100056143
Chartered accountantMallika Bhalgat & Co—P52100080891
Chartered accountantMallika Bhalgat & Co—P52100056143
Chartered accountantVinod Kumar Jindal—P52100054253
Show all 16 professionalsShow fewer professionals
RoleNameRegistration no.RERA
Chartered accountantVinod Kumar Jindal—P52100056143
EngineerHemant Nimalkar—P52100054253
EngineerHemant Nimalkar—P52100056143
EngineerHemant Nimalkar—P52100080891
EngineerHemant Nimbalkar—P52100056143
EngineerHemant Nimbalkar—P52100080891
EngineerVinayak Bhosale—P52100054253
EngineerVinayak Bhosale—P52100056143

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology