Residential / Group Housing · 3 buildings · 64 unitsRERA P52100017973

Rangavali

Deedo IDDP-PUN-VK60

Completion was pushed back 1 year to Oct 2024, and that date has passed too; no MahaRERA orders on record; 97% of its units are booked.

Kasar Amboli, Pune 412115 · by Ronishka Developers

Delivery3 yrs 1 mo latePromised Oct 2023 · revised Oct 2024 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales97% booked62 of 64 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 1 year to Oct 2024, and that date has passed too

  • This projectRegistered 1 Oct 2018, completion promised 30 Oct 2023, revised to 29 Oct 2024, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100017973
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000179731 Oct 201830 Oct 202329 Oct 2024Ronishka DevelopersProject page
Documents86

3 documents held by Deedo, 83 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPan Card.pdf · uploaded 8 Aug 2018Source

Legal

  • Legal Title reportSearch report 16082018 Reduced.pdf · uploaded 16 Aug 2018Source
  • Declaration Form BFORM B SCAN upload.pdf · uploaded 12 Sep 2018Source

Migrated

  • 1 PAN CardPan Card.pdf · uploaded 8 Aug 2018Source
  • 1 Copy of Layout Approval (in case of layout)1.pdf · uploaded 8 Aug 2018Source
Show all 86 documentsShow fewer documents

Migrated

  • 2 Copy of Layout Approval (in case of layout)2.pdf · uploaded 8 Aug 2018Source
  • 1 Building Plan Approval (IOD)3.pdf · uploaded 8 Aug 2018Source
  • 2 Building Plan Approval (IOD)4.pdf · uploaded 8 Aug 2018Source
  • 3 Building Plan Approval (IOD)5.pdf · uploaded 8 Aug 2018Source
  • 4 Building Plan Approval (IOD)6.pdf · uploaded 8 Aug 2018Source
  • 5 Building Plan Approval (IOD)7.pdf · uploaded 8 Aug 2018Source
  • 1 Copy of the legal title reportSearch report 16082018 Reduced.pdf · uploaded 16 Aug 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate Upload.pdf · uploaded 16 Aug 2018Source
  • 1 Proforma of Allotment letterAllotment Letter PDF.pdf · uploaded 30 Aug 2018Source
  • 2 Proforma of Allotment letterRangavali Agreement to Sale PDF.pdf · uploaded 30 Aug 2018Source
  • 1 Details of encumbrancesNo encumbrance Cert PDF.pdf · uploaded 12 Sep 2018Source
  • 1 Declaration in FORM BFORM B SCAN upload.pdf · uploaded 12 Sep 2018Source
  • 1 Certificates of CA (Form 3)CA Certificate Upload.pdf · uploaded 13 Sep 2018Source
  • 1 Annual Audit Report of Statutory CA (Form 5)FORM 5.pdf · uploaded 30 Sep 2019Source
  • 3 Copy of Layout Approval (in case of layout)01-07 (1).pdf · uploaded 23 Nov 2020Source
  • 4 Copy of Layout Approval (in case of layout)02-07_ NEW.pdf · uploaded 23 Nov 2020Source
  • 6 Building Plan Approval (IOD)03-07 (1).pdf · uploaded 23 Nov 2020Source
  • 7 Building Plan Approval (IOD)04-07 (1).pdf · uploaded 23 Nov 2020Source
  • 8 Building Plan Approval (IOD)05-07 (1).pdf · uploaded 23 Nov 2020Source
  • 9 Building Plan Approval (IOD)06-07 (1).pdf · uploaded 23 Nov 2020Source
  • 10 Building Plan Approval (IOD)07-07 (1).pdf · uploaded 23 Nov 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC Rev 1.pdf · uploaded 23 Nov 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5.pdf · uploaded 27 Mar 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 SIGNED.pdf · uploaded 27 Mar 2021Source
  • 5 Copy of Layout Approval (in case of layout)01-08.pdf · uploaded 22 Sep 2022Source
  • 6 Copy of Layout Approval (in case of layout)02-08.pdf · uploaded 22 Sep 2022Source
  • 7 Copy of Layout Approval (in case of layout)03-08.pdf · uploaded 22 Sep 2022Source
  • 8 Copy of Layout Approval (in case of layout)04-08.pdf · uploaded 22 Sep 2022Source
  • 9 Copy of Layout Approval (in case of layout)05-08.pdf · uploaded 22 Sep 2022Source
  • 10 Copy of Layout Approval (in case of layout)06-08.pdf · uploaded 22 Sep 2022Source
  • 11 Copy of Layout Approval (in case of layout)07-08.pdf · uploaded 22 Sep 2022Source
  • 12 Copy of Layout Approval (in case of layout)08-08.pdf · uploaded 22 Sep 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC REV II COMP.pdf · uploaded 22 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5_1.pdf · uploaded 18 Oct 2022Source
  • 1 Declaration about Commencement CertificateDecl about Commencement Cert.pdf · uploaded 3 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 20-21.pdf · uploaded 3 Feb 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 20-21.pdf · uploaded 3 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 COMP.pdf · uploaded 16 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 COMP.pdf · uploaded 16 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A March 20 COMP.pdf · uploaded 16 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A June 20 COMP.pdf · uploaded 16 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 31 Dec 22 cOMP.pdf · uploaded 16 Feb 2023Source
  • 1 Proforma of Agreement for saleRangavali Agreement to Sale PDF.pdf · uploaded 16 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER S CERT COMP COST 21-22.pdf · uploaded 17 Feb 2023Source
  • 1 Disclosure of sold/ booked inventoryIMG_0001.pdf · uploaded 17 Feb 2023View
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Form 1 RERA 03062024 COMP.pdf · uploaded 6 Jun 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA-Form-5_2022-23.pdf · uploaded 27 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)rera Form 5_202324 KA 435 450_.pdf · uploaded 27 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Form 1 RERA 03062024 COMP.pdf · uploaded 28 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryDISCL 20092024.pdf · uploaded 13 Dec 2024View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2 A 2021-22 merged comp.pdf · uploaded 7 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 2022-23 merged comp.pdf · uploaded 7 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2023 24 merged Comp.pdf · uploaded 7 Jan 2025Source

Technical

  • Document1.pdf · uploaded 8 Aug 2018Source
  • Document2.pdf · uploaded 8 Aug 2018Source
  • Document3.pdf · uploaded 8 Aug 2018Source
  • Document4.pdf · uploaded 8 Aug 2018Source
  • Document5.pdf · uploaded 8 Aug 2018Source
  • Document6.pdf · uploaded 8 Aug 2018Source
  • Document7.pdf · uploaded 8 Aug 2018Source
  • Document01-07 (1).pdf · uploaded 23 Nov 2020Source
  • Document02-07_ NEW.pdf · uploaded 23 Nov 2020Source
  • Document03-07 (1).pdf · uploaded 23 Nov 2020Source
  • Document04-07 (1).pdf · uploaded 23 Nov 2020Source
  • Document05-07 (1).pdf · uploaded 23 Nov 2020Source
  • Document06-07 (1).pdf · uploaded 23 Nov 2020Source
  • Document07-07 (1).pdf · uploaded 23 Nov 2020Source
  • Document01-08.pdf · uploaded 22 Sep 2022Source
  • Document02-08.pdf · uploaded 22 Sep 2022Source
  • Document03-08.pdf · uploaded 22 Sep 2022Source
  • Document04-08.pdf · uploaded 22 Sep 2022Source
  • Document05-08.pdf · uploaded 22 Sep 2022Source
  • Document06-08.pdf · uploaded 22 Sep 2022Source
  • Document07-08.pdf · uploaded 22 Sep 2022Source
  • Document08-08.pdf · uploaded 22 Sep 2022Source

Technical (Architect)

  • DocumentArch Form 1 RERA 03062024 COMP.pdf · uploaded 6 Jun 2024Source
  • DocumentArch Form 1 RERA 03062024 COMP.pdf · uploaded 28 Oct 2024Source

Technical (Engineer)

  • DocumentENGINEER S CERT COMP COST 21-22.pdf · uploaded 17 Feb 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 435, 450/5

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK64 units in all
Address
435, 450/5, Kasar Amboli, Off Paud Road, Mankarwadi Road, Ganpati Mandir, Kasaramboli PirangutPIN 412115
Village
Kasar Amboli, Mulshi taluka
Land area for this project
0 sq m (0 sq ft)
Permissible built-up area
3,527 sq m (37,963 sq ft)
Sanctioned built-up area
2,776 sq m (29,881 sq ft)
Recreational open space
279 sq m (3,006 sq ft)
Designated bank account
82
Developed in phases
Yes

Survey, CTS, gat or plot numbers

435450/5

Land as published on MahaRERA's project page

435, 450/5, KASAR AMBOLI

Boundaries

North
430- 431 Kasar Amboli
South
445- 446- 450 P Kasar Amboli
East
Government Road
West
445- 434 Kasar Amboli

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking64 units

62 of 64 units booked (97%), as the promoter reported to MahaRERA

1BHK · 48 units2BHK · 16 units
BuildingTypeCarpet areaUnitsBooked
A Part1BHK30.33 sq m · 326 sq ft66
A Part1BHK30.66 sq m · 330 sq ft1212
A Part1BHK31.73 sq m · 342 sq ft66
A Part1BHK31.75 sq m · 342 sq ft66
A Part1BHK33.78 sq m · 364 sq ft1010
A Part1BHK34.11 sq m · 367 sq ft44
A Part1BHK35.2 sq m · 379 sq ft44
B Part2BHK45.42 sq m · 489 sq ft44
Show all 11 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
B Part2BHK46.95 sq m · 505 sq ft43
B Part2BHK52.65 sq m · 567 sq ft43
B Part2BHK55.76 sq m · 600 sq ft44

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrakash Kanhekar—