Silver Park
Deedo IDDP-PUN-67SDCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 26% of its units are booked.
Jalochi, Pune 413102 · Promoter: Gole & Hole Builders
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 19 Oct 2022, completion promised 1 Dec 2027, revised to 1 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
- Silver Park Building A8 floors · 74 units3% booked
- Silver Park Building B7 floors · 56 units58% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100047322
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100047322 | 19 Oct 2022 | 1 Dec 2027 | 1 Apr 2028 | Gole & Hole Builders | Project page |
Documents157
1 document held by Deedo, 156 filings listed on MahaRERA's project page
Finance
- PAN Card1 Pan card firm.pdf · uploaded 12 Sep 2022Source
Legal
- Other – Legal15 other doc 7 12 of plot.pdf · uploaded 12 Sep 2022Source
- Legal Title report2 Detail Search Report Gat 186_C.pdf · uploaded 12 Sep 2022Source
- Declaration Form BAffidavit in form B Builder N.pdf · uploaded 22 Sep 2022Source
- Declaration Form B9 Declation in form B Affidavit Owner.pdf · uploaded 22 Sep 2022Source
- Declaration Form BSearch report.pdf · uploaded 6 May 2026Source
- Declaration Form B7-12 Letest.pdf · uploaded 6 May 2026Source
Show all 157 documentsShow fewer documents
Migrated
- 1 PAN Card1 Pan card firm.pdf · uploaded 12 Sep 2022Source
- 1 Copy of the legal title report2 Detail Search Report Gat 186_C.pdf · uploaded 12 Sep 2022Source
- 1 b Details of encumbrances concerned to Legal4 Detail of encumrances concern to legal.pdf · uploaded 12 Sep 2022Source
- 1 Copy of Layout Approval (in case of layout)5 Lay Out Approval vinishtikaran N A order.pdf · uploaded 12 Sep 2022Source
- 1 Building Plan Approval / NA Order for plotted development6 Approved building plan.pdf · uploaded 12 Sep 2022Source
- 1 Commencement Certificates / NA Order for plotted development7 BMC commencement cert.pdf · uploaded 12 Sep 2022Source
- 1 Declaration about Commencement Certificate8 Declaration about commencement cert.pdf · uploaded 12 Sep 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)10 Architect certificate.pdf · uploaded 12 Sep 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 Engineer certificate.pdf · uploaded 12 Sep 2022Source
- 1 CERSAI details12 Cersai Certificate report.pdf · uploaded 12 Sep 2022Source
- 1 Proforma of Allotment letter17 model form of allottment letter.pdf · uploaded 12 Sep 2022Source
- 2 Proforma of Allotment letter1 16 model form of agreement to be entered into between promoter and allottee_C-1-7.pdf · uploaded 12 Sep 2022Source
- 3 Proforma of Allotment letter2 16 model form of agreement to be entered into between promoter and allottee_C-8-14.pdf · uploaded 12 Sep 2022Source
- 1 Deviation Report with respect to Allotment letter18 Declaration regarding no deviation in allotment letter.pdf · uploaded 12 Sep 2022Source
- 1 Deviation Report with respect to model copy of Agreement19 Declaration regarding no deviation in model agreement for sale.pdf · uploaded 12 Sep 2022Source
- 1 Other – Legal15 other doc 7 12 of plot.pdf · uploaded 12 Sep 2022Source
- 1 a Details of encumbrances concerned to FinanceFinancial encumbrance N.pdf · uploaded 22 Sep 2022Source
- 1 Declaration in FORM BAffidavit in form B Builder N.pdf · uploaded 22 Sep 2022Source
- 2 Declaration in FORM B9 Declation in form B Affidavit Owner.pdf · uploaded 22 Sep 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about separate bank Account N.pdf · uploaded 22 Sep 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate N.pdf · uploaded 27 Sep 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)C1 Architect Certificate form1.pdf · uploaded 28 Feb 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)C1 Architect Certificate form1.pdf · uploaded 28 Feb 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)C1 Engineer Certificate form2.pdf · uploaded 28 Feb 2023Source
- 1 Disclosure of sold/ booked inventoryC1 Disclosure of Inventory.pdf · uploaded 28 Feb 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)C1 CA certificate Form--3.pdf · uploaded 28 Feb 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 5 4 23.pdf · uploaded 5 Nov 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 4 7 23.pdf · uploaded 5 Nov 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate 6 10 23.pdf · uploaded 5 Nov 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's certificate 5 4 23 C.pdf · uploaded 5 Nov 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's certificate 4 7 23 C.pdf · uploaded 5 Nov 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate 6 10 23 C.pdf · uploaded 5 Nov 2023Source
- 2 Disclosure of sold/ booked inventoryBOOKED INVENTORY 3 10 23.pdf · uploaded 5 Nov 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate 31 3 23 C.pdf · uploaded 5 Nov 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 30 6 23 C.pdf · uploaded 5 Nov 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 30 9 23 C.pdf · uploaded 5 Nov 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 23 Architect Certificate.pdf · uploaded 16 Mar 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Dec 23 Engineering Certificate.pdf · uploaded 16 Mar 2024Source
- 3 Disclosure of sold/ booked inventoryDec 23- Discloser of sold Inventory.pdf · uploaded 16 Mar 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA QUARTERLY REPORT-FORM 3 - Dec 23.pdf · uploaded 16 Mar 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)CA-ANNUAL REPORT- Form No 5 -(FY2022 -23).pdf · uploaded 16 Mar 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 31 March24.pdf · uploaded 20 Jun 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineering Certificate 31 March24.pdf · uploaded 20 Jun 2024Source
- 4 Disclosure of sold/ booked inventoryDiscloser of Inventory 31 March24.pdf · uploaded 20 Jun 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FORM NO 3- 31March24 -C.pdf · uploaded 20 Jun 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate 30 6 24.pdf · uploaded 24 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A certificate 30 6 24.pdf · uploaded 24 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineering Certificate 30 06 24.pdf · uploaded 24 Nov 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold flat 30 6 24.pdf · uploaded 24 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality assurance 23 24.pdf · uploaded 24 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)CA FORM NO 5 FY 2023 24.pdf · uploaded 24 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect cert 30 09 24.pdf · uploaded 4 May 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect cert 31 12 24.pdf · uploaded 4 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERT 30 09 24_comp.pdf · uploaded 4 May 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA cert 31 12 24_comp.pdf · uploaded 4 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg cert 30 09 24.pdf · uploaded 4 May 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg cert 31 12 24.pdf · uploaded 4 May 2025Source
- 1 Disclosure of sold/ booked inventorydisclosure of sold booked inventory 30 9 24.pdf · uploaded 4 May 2025Source
- 2 Disclosure of sold/ booked inventorydisclosure of sold booked inventory 31 12 24.pdf · uploaded 4 May 2025Source
- 3 Disclosure of sold/ booked inventorydisclosure of sold booked inventory 31 3 25.pdf · uploaded 4 May 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Engg Quality Assurance 2024 25.pdf · uploaded 4 May 2025Source
- Form 1Architect Certificate -dec 22.pdf · uploaded 6 Aug 2025Source
- Form 2Engineer Certificate-dec 22.pdf · uploaded 6 Aug 2025Source
- Form 3CA certificate-dec 22.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked Inventorydisclosure of invetory-dec 22.pdf · uploaded 6 Aug 2025Source
- Form 1FORM 1-ARCH CERT-March 23.pdf · uploaded 6 Aug 2025Source
- Form 2FORM 2-ENGG CERT-March 23.pdf · uploaded 6 Aug 2025Source
- Form 3FORM 3-CA CERT-March 23.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked InventorySold inventory-March 23.pdf · uploaded 6 Aug 2025Source
- Form 1FORM 1-ARCH CERT-JUNE 23.pdf · uploaded 6 Aug 2025Source
- Form 2FORM 2-ENGG CERT -JUNE 23.pdf · uploaded 6 Aug 2025Source
- Form 3FORM 3-CA CERT -JUNE 23.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked InventoryDICLOSURE OF INVENTORY -JUNE 23.pdf · uploaded 6 Aug 2025Source
- Form 1FORM 1-ARCH CERT-SEPT 23.pdf · uploaded 6 Aug 2025Source
- Form 2FORM 2-ENGG CERT-SEPT 23.pdf · uploaded 6 Aug 2025Source
- Form 3FORM 3-CA CERT-SEPT 23.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked InventoryDIS INVENTORY -SEPT 23.pdf · uploaded 6 Aug 2025Source
- Form 1FORM 1-ARCH CERT-DEC 23.pdf · uploaded 6 Aug 2025Source
- Form 2FORM 2-ENGG CERT-DEC 23.pdf · uploaded 6 Aug 2025Source
- Form 3FORM 3-CA CERT- DEC 23.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE INVENTORY-DEC23.pdf · uploaded 6 Aug 2025Source
- Form 1FORM 1-ARCH CERT-MARCH 24.pdf · uploaded 6 Aug 2025Source
- Form 2FORM 2-ENGG CERT-MARCH 24.pdf · uploaded 6 Aug 2025Source
- Form 3FORM 3-CA CERT-MARCH 24.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE INVENTORY-MARCH 24.pdf · uploaded 6 Aug 2025Source
- Form 1FORM 1- ARCH CERT-JUNE 24.pdf · uploaded 6 Aug 2025Source
- Form 2FROM 2-ENGG CERT-JUNE 24.pdf · uploaded 6 Aug 2025Source
- Form 3FORM 3-CA CERT-JUNE 24.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF INVENTORY-JUNE 24.pdf · uploaded 6 Aug 2025Source
- Form 1FORM 1-ARCH CERT-SEPT 24.pdf · uploaded 6 Aug 2025Source
- Form 2FORM 2- ENGG CERT-SEPT 24.pdf · uploaded 6 Aug 2025Source
- Form 3FORM 3-CA CERT - SEPT 24.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF INVENTORY -SEPT 24.pdf · uploaded 6 Aug 2025Source
- Form 1FORM 1-ARCH CERT- DEC 24.pdf · uploaded 6 Aug 2025Source
- Form 2FORM 2-ENGG CERT-DEC 24.pdf · uploaded 6 Aug 2025Source
- Form 3FORM 3-CA CERT-DEC 24.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked InventoryDISCLOSURE OF INVENTORY -DEC 24.pdf · uploaded 6 Aug 2025Source
- Form 5 (FY 2022-2023)FORM 5- FY-2022-2023.pdf · uploaded 6 Aug 2025Source
- Form 5 (FY 2023-2024)FORM 5- ANNUAL REPORT-2023-24.pdf · uploaded 6 Aug 2025Source
- Form 2A (FY 2022-2023)QA 2A certificate F. Y. 22-23.pdf · uploaded 9 Aug 2025Source
- Form 2A (FY 2023-2024)Form 2A Certifcate FY 23-24.pdf · uploaded 9 Aug 2025Source
- Form 2A (FY 2024-2025)Form 2 A certificate FY 24-25.pdf · uploaded 9 Aug 2025Source
- Form 1Architect cert March 25.pdf · uploaded 8 Sep 2025Source
- Form 2Engg Cert March 25.pdf · uploaded 8 Sep 2025Source
- Form 3Form 3 CA March 25.pdf · uploaded 8 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of inventory March 25.pdf · uploaded 8 Sep 2025Source
- Form 5 (FY 2024-2025)Form 5 - FY 2024 25.pdf · uploaded 20 Sep 2025Source
- Withdrawal Update Form 1Form 1 june 25.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 2Form 2 30 june 25.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 3Form no 3 30 06 2025_comp.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 1Form 1 sept 25.pdf · uploaded 29 Nov 2025Source
- Withdrawal Update Form 2Form 2 sept 25.pdf · uploaded 29 Nov 2025Source
- Withdrawal Update Form 3Form 3 sept 25_comp.pdf · uploaded 29 Nov 2025Source
- Withdrawal Update Form 1Architect certificate 31 12 25.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 2Engineer certificate 31 12 25.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 3CA certificate 31 12 25.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 1Architect certificate 31 12 25.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 2Engineer certificate 31 12 25.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 3CA certificate 31 12 25.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 1Architect certificate 31 12 25.pdf · uploaded 10 Feb 2026Source
- Withdrawal Update Form 2Engineer certificate 31 12 25.pdf · uploaded 10 Feb 2026Source
- Withdrawal Update Form 3CA certificate 31 12 25.pdf · uploaded 10 Feb 2026Source
- Withdrawal Update Form 1Architect certificate 31 12 25.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 2Engineer certificate 31 12 25.pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 3Form3- dec 2025 (1).pdf · uploaded 13 Feb 2026Source
- Withdrawal Update Form 1Architect certificate 31 12 25.pdf · uploaded 17 Feb 2026Source
- Withdrawal Update Form 2Engineer certificate 31 12 25.pdf · uploaded 17 Feb 2026Source
- Withdrawal Update Form 3Form 3 - for widrawal correction.pdf · uploaded 17 Feb 2026Source
- Withdrawal Update Form 1Form 1 March 26.pdf · uploaded 15 Jun 2026Source
- Withdrawal Update Form 2Form 2 march 2026.pdf · uploaded 15 Jun 2026Source
- Withdrawal Update Form 3Form 3 31 3 26.pdf · uploaded 15 Jun 2026Source
- Form 2A (FY 2025-2026)Form 2A Year 2025-26.pdf · uploaded 15 Jun 2026Source
- Form 5 (FY 2025-2026)Form 5 Year 2025 26.pdf · uploaded 16 Jun 2026Source
- Withdrawal Update Form 1form 1 Architect cert june 26.pdf · uploaded 20 Sep 2026Source
- Withdrawal Update Form 1form 1 Architect cert june 26.pdf · uploaded 20 Sep 2026Source
- Withdrawal Update Form 2form 2 Engg certificate June 26.pdf · uploaded 20 Sep 2026Source
- Withdrawal Update Form 2form 2 Engg certificate June 26.pdf · uploaded 20 Sep 2026Source
- Withdrawal Update Form 3Form no 3 CA certificate June 26.pdf · uploaded 20 Sep 2026Source
- Withdrawal Update Form 3Form no 3 CA certificate June 26.pdf · uploaded 20 Sep 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals186A
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —130 units in all
- Address
- 186a, Bhaji Mandai Road, Suryanagari, SuryanagariPIN 413102
- Village
- Jalochi, Baramati taluka
- Location
- 18.16951, 74.60736
- Designated bank account
- 82
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Gat No 186
- South
- Yashashree Building
- East
- Gat No 187
- West
- 12 Mtr Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking130 units
130 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Silver Park Building A | — | — | 74 |
| Silver Park Building B | — | — | 56 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mr Abhijeet Anil Kale | — |
| Chartered accountant | Mr Lalaso B Dhaygude | — |
| Chartered accountant | Mr Samrat Ashok Somani | — |
| Engineer | Mr Abhijeet Anil Kale | — |
Source: MahaRERA project page. Contact details are not shown.