Skip to content
Residential / Group Housing · 6 buildings · 529 unitsRERA P52100032086

Vivacity

Deedo IDDP-PUN-3Z19

It is due for completion in Dec 2026, with no extension on record; no MahaRERA orders on record; 88% of its units are booked.

Haveli, Maharashtra 411015 · Property rates in Haveli · Promoter: Realcon Landmarks LLP

DeliveryDue Dec 2026No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales88% booked463 of 529 units · as the promoter reported to MahaRERA
Vivacity project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

It is due for completion in Dec 2026, with no extension on record

  • This projectRegistered 6 Dec 2021, completion promised 31 Dec 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100032086
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000320866 Dec 202131 Dec 202631 Dec 2026Realcon Landmarks LLPProject page
Documents104

1 document held by Deedo, 103 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN-Realcon landmark LLP.pdf · uploaded 17 Nov 2021Source

Legal

  • Legal Title reportRERA -TSR-24-11-2021.pdf · uploaded 26 Nov 2021Source
  • Declaration Form BFormB.pdf · uploaded 26 Nov 2021Source

Migrated

  • 1 Details of encumbrancesNo emcumbrance_Dhanori.pdf · uploaded 12 Nov 2021Source
  • 1 Copy of Layout Approval (in case of layout)Vivacity- LAYOUT.pdf · uploaded 12 Nov 2021Source
  • 1 Building Plan Approval / NA Order for plotted development4-18 - A - FLOOR PLANS_compressed.pdf · uploaded 12 Nov 2021Source
  • 2 Building Plan Approval / NA Order for plotted development9-18 - B - FLOOR PLANS_compressed.pdf · uploaded 12 Nov 2021Source
Show all 104 documentsShow fewer documents

Migrated

  • 3 Building Plan Approval / NA Order for plotted development15-18 - F - FLOOR PLANS_compressed.pdf · uploaded 12 Nov 2021Source
  • 1 Commencement Certificates / NA Order for plotted development211022 - CC_compressed (1).pdf · uploaded 12 Nov 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dhanori Form1_compressed.pdf · uploaded 12 Nov 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2_Viva City.pdf · uploaded 12 Nov 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA Form 03 Viva City311021.PDF · uploaded 12 Nov 2021Source
  • 1 PAN CardPAN-Realcon landmark LLP.pdf · uploaded 17 Nov 2021Source
  • 1 Copy of the legal title reportRERA -TSR-24-11-2021.pdf · uploaded 26 Nov 2021Source
  • 1 Declaration about Commencement CertificateFormatD_declaration.pdf · uploaded 26 Nov 2021Source
  • 1 Declaration in FORM BFormB.pdf · uploaded 26 Nov 2021Source
  • 1 Proforma of Allotment letterDRAFT AGREEMENT TOSELL ALLOTMENT LETTER.pdf · uploaded 26 Nov 2021Source
  • 1 CERSAI detailsCERSAI_Realcon.pdf · uploaded 27 Nov 2021Source
  • 2 Proforma of Allotment letterDhanori 9 Draft new-01-02-2022 (2).pdf · uploaded 9 Feb 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Vivacity.pdf · uploaded 1 Oct 2022Source
  • 2 Copy of Layout Approval (in case of layout)1881_1_compressed.pdf · uploaded 14 Oct 2022Source
  • 2 Commencement Certificates / NA Order for plotted development220810 - CC_compressed.pdf · uploaded 14 Oct 2022Source
  • 2 Declaration about Commencement CertificateCC Declaration (1).pdf · uploaded 14 Oct 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)kohinoor viva city date-14-01-23_compressed.pdf · uploaded 12 Feb 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Viva City.pdf · uploaded 12 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)viva city.pdf · uploaded 12 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)viva city_compressed.pdf · uploaded 12 Feb 2023Source
  • 3 Copy of Layout Approval (in case of layout)1-34_compressed.pdf · uploaded 23 Feb 2023Source
  • 3 Commencement Certificates / NA Order for plotted development230117 - CC - Revised.pdf · uploaded 23 Feb 2023Source
  • 3 Declaration about Commencement CertificateViva City CC declaration.pdf · uploaded 23 Feb 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)230630 -Viva City- Form 1.pdf · uploaded 24 Jul 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)20230710_Form 2_Viva city.pdf · uploaded 24 Jul 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Viva City.PDF · uploaded 5 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Vivacity.pdf · uploaded 29 Sep 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q4 21 22.pdf · uploaded 13 Mar 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q1 22 23.pdf · uploaded 13 Mar 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q2 22 23.pdf · uploaded 13 Mar 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4 21 22.pdf · uploaded 13 Mar 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1 22 23.pdf · uploaded 13 Mar 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2 22 23.pdf · uploaded 13 Mar 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q4 22-23.pdf · uploaded 14 Mar 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q2 23-24.pdf · uploaded 14 Mar 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q3 23-24.pdf · uploaded 14 Mar 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4 22-23.pdf · uploaded 14 Mar 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2 23-24.pdf · uploaded 14 Mar 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3 23-24.pdf · uploaded 14 Mar 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q2 22-23.pdf · uploaded 14 Mar 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q4 22-23.pdf · uploaded 14 Mar 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q2 23-24_1.pdf · uploaded 14 Mar 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q3 23-24.pdf · uploaded 14 Mar 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Viva City Q1 22 23.pdf · uploaded 19 Mar 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIVA CITY Q4 21 22.pdf · uploaded 20 Mar 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)VIVA CITY Q1 22 23.pdf · uploaded 20 Mar 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VIVA CITY.pdf · uploaded 19 Apr 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VIVA CITY.pdf · uploaded 19 Apr 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VIVA CITY.pdf · uploaded 20 Apr 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-01 Q1 FY 24-25 VIVA CITY.pdf · uploaded 20 Jul 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-02 Q1 FY 24-25 VIVA CITY.pdf · uploaded 20 Jul 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-03 Q1 FY 24-25 VIVA CITY.pdf · uploaded 20 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Viva City.pdf · uploaded 8 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Viva city.pdf · uploaded 11 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Viva city.pdf · uploaded 19 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Viva city.pdf · uploaded 19 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A_VIVA CITY.pdf · uploaded 3 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Viva city.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_VIVA CITY.pdf · uploaded 27 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_VIVA CITY.pdf · uploaded 27 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_K VIVA CITY.pdf · uploaded 19 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 03_Viva City.pdf · uploaded 9 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 02_Viva City.pdf · uploaded 9 May 2025Source
  • Withdrawal Update Form 1Viva city.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 2Form 02_Viva City.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 3Form 03_Viva City.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 1FORM 1- VIVA CITY.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 2Form 02_Viva City.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 3Form 03_Viva City.pdf · uploaded 25 Oct 2025Source
  • Form 5 (FY 2024-2025)Form 05_Viva City.pdf · uploaded 7 Nov 2025Source
  • Form 2A (FY 2024-2025)Form 2A_Viva City.pdf · uploaded 15 Nov 2025Source
  • Withdrawal Update Form 1FORM 1_VIVA CITY.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2Form 02_Viva City.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3Form 03_Viva City.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1Form 1 - Viva city.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 2Form 02_Viva City.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 3Form 03_Viva City.pdf · uploaded 21 Apr 2026Source
  • Withdrawal Update Form 1Viva city.pdf · uploaded 19 Jul 2026Source
  • Withdrawal Update Form 2Form 02_Viva City.pdf · uploaded 19 Jul 2026Source
  • Withdrawal Update Form 3Form 03_Viva City.pdf · uploaded 19 Jul 2026Source
  • Form 5 (FY 2025-2026)Viva Pixel Phase I Form 05 _31-03-2026.pdf · uploaded 31 Jul 2026Source
  • Form 2A (FY 2025-2026)Form 2A-Viva City.pdf · uploaded 23 Sep 2026Source

Technical

  • DocumentVivacity- LAYOUT.pdf · uploaded 12 Nov 2021Source
  • Document4-18 - A - FLOOR PLANS_compressed.pdf · uploaded 12 Nov 2021Source
  • Document9-18 - B - FLOOR PLANS_compressed.pdf · uploaded 12 Nov 2021Source
  • Document15-18 - F - FLOOR PLANS_compressed.pdf · uploaded 12 Nov 2021Source
  • Document1881_1_compressed.pdf · uploaded 14 Oct 2022Source
  • Document1-34_compressed.pdf · uploaded 23 Feb 2023Source

Technical (Architect)

  • DocumentForm 1- Viva city.pdf · uploaded 11 Oct 2024Source
  • DocumentForm 1- Viva city.pdf · uploaded 20 Jan 2025Source
  • DocumentFORM 1_K VIVA CITY.pdf · uploaded 19 Apr 2025Source
  • DocumentViva city.pdf · uploaded 19 Jul 2026Source

Technical (Engineer)

  • DocumentForm 2- Viva city.pdf · uploaded 19 Oct 2024Source
  • DocumentFORM 2_VIVA CITY.pdf · uploaded 27 Jan 2025Source
  • DocumentForm 02_Viva City.pdf · uploaded 9 May 2025Source
  • DocumentForm 02_Viva City.pdf · uploaded 19 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsS NO 9

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, TWO AND HALF BHK, 1BHK, Shop, 3BHK529 units in all
Address
S No 9 Village Dhanori Tal Haveli Dist Pune, S No 9, , Village Dhanori, Tal Pune City, PunePIN 411015
Designated bank account
82
Developed in phases
Yes

Survey, CTS, gat or plot numbers

S NO 9

Boundaries

North
18 Mtr Wide Dp Road
South
Adj S No 9 Part
East
By 30 Mt Wide Dp Road
West
Adj S Sno 9 Part

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking529 units

463 of 529 units booked (88%), as the promoter reported to MahaRERA

2BHK · 246 unitsTWO AND HALF BHK · 61 units1BHK · 53 unitsShop · 54 units3BHK · 115 units
BuildingTypeCarpet areaUnitsBooked
A2BHK60.4 sq m · 650 sq ft98
A2BHK63.24 sq m · 681 sq ft2828
A2BHK64.58 sq m · 695 sq ft11
ATWO AND HALF BHK71.1 sq m · 765 sq ft88
ATWO AND HALF BHK72.43 sq m · 780 sq ft3535
B1BHK39.39 sq m · 424 sq ft366
B1BHK39.4 sq m · 424 sq ft95
B1BHK45.68 sq m · 492 sq ft80
Show all 41 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
B2BHK62.79 sq m · 676 sq ft99
B2BHK63.24 sq m · 681 sq ft1816
BShop21.2 sq m · 228 sq ft42
BShop23.28 sq m · 251 sq ft21
C2BHK62.79 sq m · 676 sq ft1818
C2BHK63.24 sq m · 681 sq ft2726
C2BHK67.6 sq m · 728 sq ft11
C3BHK83.93 sq m · 903 sq ft1717
CShop21.2 sq m · 228 sq ft88
CShop23.28 sq m · 251 sq ft55
D2BHK62.79 sq m · 676 sq ft1817
D2BHK63.24 sq m · 681 sq ft1818
D3BHK83.93 sq m · 903 sq ft1818
D3BHK87.04 sq m · 937 sq ft1817
DShop17.03 sq m · 183 sq ft11
DShop21.18 sq m · 228 sq ft126
DShop23.31 sq m · 251 sq ft96
DShop36.23 sq m · 390 sq ft11
DTWO AND HALF BHK71.1 sq m · 765 sq ft1818
E2BHK60.4 sq m · 650 sq ft2726
E2BHK63.24 sq m · 681 sq ft1817
E2BHK66.61 sq m · 717 sq ft11
E2BHK69.36 sq m · 747 sq ft11
E3BHK81.99 sq m · 883 sq ft2623
E3BHK87.04 sq m · 937 sq ft1716
EShop21.18 sq m · 228 sq ft66
EShop23.28 sq m · 251 sq ft66
F2BHK60.4 sq m · 650 sq ft2626
F2BHK62.79 sq m · 676 sq ft1818
F2BHK63.24 sq m · 681 sq ft88
F3BHK81.99 sq m · 883 sq ft99
F3BHK87.04 sq m · 937 sq ft99
F3BHK91.71 sq m · 987 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals61

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVk A Architecture—
Chartered accountantVinod N Nikam & Co—
EngineerPlanedge Consultants Pvt Ltd—
Registered real estate agentAarti Rohit Shaha—
Registered real estate agentAbhijit Prafulla Deori—
Registered real estate agentAbhilasha Shrivastava—
Registered real estate agentAmit Devraj Swain—
Registered real estate agentAmit Pareek Trivedi—
Show all 61 professionalsShow fewer professionals
RoleNameRegistration no.
Registered real estate agentAnish Neema—
Registered real estate agentAnkit Kumar Chaudhary—
Registered real estate agentBaljit Kaur—
Registered real estate agentBhoomi Singh—
Registered real estate agentBhushan Tarachand Sorte—
Registered real estate agentDevendra Jagannath Jagtap—
Registered real estate agentDhiraj Kumar Dahiya—
Registered real estate agentGourav Gupta—
Registered real estate agentIshwar Baban Misal—
Registered real estate agentJalindar Sahebrao Vhojage—
Registered real estate agentKamalesh Rajendra Patil—
Registered real estate agentKishor Bharat Mittal—
Registered real estate agentKrishna Kumar Panday—
Registered real estate agentKunal Sham Gholap—
Registered real estate agentKundan Balaji Kamble—
Registered real estate agentManish Gaur—
Registered real estate agentManju Dip—
Registered real estate agentNishant Madhukar Bhoinallu—
Registered real estate agentPankaj Singh—
Registered real estate agentParvati Mahendra Pratap Goswami—
Registered real estate agentPrachi Dilip More—
Registered real estate agentPrashant Shahurao Lande—
Registered real estate agentpravin shantappa dhodmani—
Registered real estate agentRahul Ramkrishna Pal—
Registered real estate agentRajeshree Yogesh Shah—
Registered real estate agentRaj Sadashiv Bansode—
Registered real estate agentRaju Namdev Jagtap—
Registered real estate agentReetu Singh—
Registered real estate agentRishabh Jain—
Registered real estate agentRohit Singh—
Registered real estate agentRohit Sunil Wadyalkar—
Registered real estate agentRoshan Pradeep Salunkhe—
Registered real estate agentRuby Singh—
Registered real estate agentRushikesh Rameshrao Patil—
Registered real estate agentSachin Manikrao Khedekar—
Registered real estate agentSagar Mohan Nanaware—
Registered real estate agentSahil Raju Kapoor—
Registered real estate agentSamod Munnalal Jadon—
Registered real estate agentSandip Shivaji Rathod—
Registered real estate agentSanjay Bhanudas Waghmare—
Registered real estate agentSanjay Chandradhar Mishra—
Registered real estate agentSanjeev Kumar—
Registered real estate agentSaroj Vinod Jain—
Registered real estate agentSharad Baban Khalse—
Registered real estate agentShreyash Bisen—
Registered real estate agentShubham Nilkantharao Pusadkar—
Registered real estate agentShubham Rajendra Nashine—
Registered real estate agentSonika Dilip Pol—
Registered real estate agentSumit Sanjay Jagtap—
Registered real estate agentSunayana Wason—
Registered real estate agentSunil Chandrakant Suratwala—
Registered real estate agentVaishali Shailesh Aher—
Registered real estate agentVikas Satish Gupta—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology