Residential / Group Housing · 1 building · 27 unitsRERA P52100029490

Arsh Complax

Deedo IDDP-PUN-JJJ8

Completion was pushed back 4 years and 7 months, to Dec 2027; no MahaRERA orders on record; 4% of its units are booked.

Haveli, Maharashtra 411002 · Property rates in Haveli · Promoter: Milan Developers

DeliveryExtended 4 yrs 7 moPromised May 2023 · now due Dec 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales4% booked1 of 27 units · as the promoter reported to MahaRERA
Arsh Complax project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 years and 7 months, to Dec 2027

  • This projectRegistered 4 Jun 2021, completion promised 31 May 2023, revised to 31 Dec 2027.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100029490
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000294904 Jun 202131 May 202331 Dec 2027Milan DevelopersProject page
Documents124

2 documents held by Deedo, 122 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 10 May 2021Source

Legal

  • Legal Title reportSEARCH DEED Titel report.pdf · uploaded 10 May 2021Source
  • Declaration Form BForm B.pdf · uploaded 10 May 2021Source
  • Declaration Form BAffidavit_compressed (1).pdf · uploaded 23 May 2024Source

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate.pdf · uploaded 4 May 2021Source
  • 1 PAN CardPAN CARD.pdf · uploaded 10 May 2021Source
Show all 124 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportSEARCH DEED Titel report.pdf · uploaded 10 May 2021Source
  • 1 Details of encumbrancesEncumbrances Certificate.pdf · uploaded 10 May 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentBUILDING A.pdf · uploaded 10 May 2021Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 10 May 2021Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER-.pdf · uploaded 13 May 2021Source
  • 1 Copy of Layout Approval (in case of layout)leyout plan wide main road01.pdf · uploaded 1 Jun 2021Source
  • 2 Copy of Layout Approval (in case of layout)leyout plan wide main road02.pdf · uploaded 1 Jun 2021Source
  • 3 Copy of Layout Approval (in case of layout)leyout plan1028052021.pdf · uploaded 1 Jun 2021Source
  • 4 Copy of Layout Approval (in case of layout)frist floor plan02.pdf · uploaded 1 Jun 2021Source
  • 5 Copy of Layout Approval (in case of layout)second floor plan01.pdf · uploaded 1 Jun 2021Source
  • 6 Copy of Layout Approval (in case of layout)third floor plan02.pdf · uploaded 1 Jun 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentbulding approvid elevaqiy.pdf · uploaded 1 Jun 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentbulding approvid plan01.pdf · uploaded 1 Jun 2021Source
  • 4 Building Plan Approval / NA Order for plotted developmentbulding approvid plan02.pdf · uploaded 1 Jun 2021Source
  • 5 Building Plan Approval / NA Order for plotted developmentcertificat of area.pdf · uploaded 1 Jun 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 101062021.pdf · uploaded 1 Jun 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 201062021.pdf · uploaded 1 Jun 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MILAN-RESIZE.pdf · uploaded 1 Jun 2021Source
  • 2 Proforma of Allotment letterDraft Agreement of RERA.pdf · uploaded 1 Jun 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Milan Enterprises.pdf · uploaded 19 May 2023Source
  • 2 a Details of encumbrances concerned to FinanceLEGAL ENCUBRANCES.pdf · uploaded 5 Dec 2023Source
  • 1 b Details of encumbrances concerned to LegalLEGAL ENCUBRANCES.pdf · uploaded 5 Dec 2023Source
  • 1 Declaration about Commencement CertificateCommencment Certificate.pdf · uploaded 5 Dec 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 5 Dec 2023Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION TO LOA AND AGREEMENT.pdf · uploaded 5 Dec 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION TO LOA AND AGREEMENT.pdf · uploaded 5 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)QUALITY ASS.pdf · uploaded 12 Dec 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)QUALITY ASS.pdf · uploaded 12 Dec 2023Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD DETAILS.pdf · uploaded 12 Dec 2023Source
  • 1 CERSAI detailsLEGAL ENCUBRANCES.pdf · uploaded 12 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Milan Enterprises Form 5 22-23.pdf · uploaded 12 Dec 2023Source
  • 1 Proforma of Agreement for saleAGREEMENT TO SALE.pdf · uploaded 12 Dec 2023Source
  • 3 Details of encumbrancesENCUMBRANCES.pdf · uploaded 8 May 2024Source
  • 7 Copy of Layout Approval (in case of layout)rera plan1.pdf · uploaded 8 May 2024Source
  • 8 Copy of Layout Approval (in case of layout)rera plan2.pdf · uploaded 8 May 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentrera plan1.pdf · uploaded 8 May 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentrera plan2.pdf · uploaded 8 May 2024Source
  • 2 Declaration about Commencement CertificateCommencment Certificate.pdf · uploaded 8 May 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_compressed.pdf · uploaded 8 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Eng certificate_compressed.pdf · uploaded 8 May 2024Source
  • 2 Disclosure of sold/ booked inventorySold and Unsold_compressed.pdf · uploaded 8 May 2024Source
  • 2 Declaration in FORM BAffidavit_compressed (1).pdf · uploaded 23 May 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1_compressed.pdf · uploaded 3 Jun 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2_compressed.pdf · uploaded 3 Jun 2024Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 MILAN.pdf · uploaded 3 Jun 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07012022.pdf · uploaded 20 Aug 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07012023.pdf · uploaded 20 Aug 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07012024.pdf · uploaded 20 Aug 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07042022.pdf · uploaded 20 Aug 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07042023.pdf · uploaded 20 Aug 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07042024.pdf · uploaded 20 Aug 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07072022.pdf · uploaded 20 Aug 2024Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07072023.pdf · uploaded 20 Aug 2024Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07102022.pdf · uploaded 20 Aug 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate 07102023.pdf · uploaded 20 Aug 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Q1.pdf · uploaded 20 Aug 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Q3.pdf · uploaded 20 Aug 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Q4.pdf · uploaded 20 Aug 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)30062022.pdf · uploaded 30 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)30092022.pdf · uploaded 30 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)31032022.pdf · uploaded 30 Nov 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)31122022.pdf · uploaded 30 Nov 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)30062023.pdf · uploaded 30 Nov 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)30092023.pdf · uploaded 30 Nov 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)31032023.pdf · uploaded 30 Nov 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)31122023.pdf · uploaded 30 Nov 2024Source
  • Form 1Architects Certificate 1 Q4 2526.pdf · uploaded 3 Sep 2026Source
  • Form 2Eng Certificate Q4 2526.pdf · uploaded 3 Sep 2026Source
  • Form 3form 3 q4 25-26.pdf · uploaded 3 Sep 2026Source
  • Disclosure of Sold and Booked InventoryCamScanner.pdf · uploaded 3 Sep 2026Source
  • Disclosure of Sold and Booked InventoryCamScanner 3.pdf · uploaded 3 Sep 2026Source
  • Form 1Architects Certificate 1 Q12627.pdf · uploaded 3 Sep 2026Source
  • Form 2Eng Certificate Updated (1).pdf · uploaded 3 Sep 2026Source
  • Form 3form 3 q1 26-27.pdf · uploaded 3 Sep 2026Source
  • Form 5 (FY 2023-2024)FORM 5 2024 Signed.pdf · uploaded 7 Sep 2026Source
  • Form 5 (FY 2024-2025)FORM 5 2025 Signed.pdf · uploaded 7 Sep 2026Source
  • Withdrawal Update Form 1Architects Certificate Final Q2 25-26.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 1Architects Certificate Final Q1.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 1Architects Certificate 1 Q3 25-26.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 2Eng Certificate Q2 25-26.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 2Eng Certificate Q2 25-26.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 2Eng Certificate Q3 25-26.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 3CA Certificate ForM 3 - Q2 Signed.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 3CA Certificate ForM 3 - Q1 Signed.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 3CA Certificate ForM 3 - Q3.pdf · uploaded 18 Sep 2026Source
  • Form 2A (FY 2024-2025)Quality Assurance Certificate 2024-25.pdf · uploaded 18 Sep 2026Source
  • Form 2A (FY 2025-2026)Quality Assurance Certificate 2025-26.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 1Architects Certificate 1 Q3 25-26.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 1FORM 1 Q4 26.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 1FORM 1 Q1 2627.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 2Eng Certificate Q3 25-26.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 2FORM 2 Q4 26.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 2FORM 2 Q1 2627.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 3FORM 3 Q4 25-26.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 3FORM 3 Q4 25-26.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 3FORM 3 Q1 2627.pdf · uploaded 22 Sep 2026Source
  • Withdrawal Update Form 1FORM 1 Q1 2627.pdf · uploaded 23 Sep 2026Source
  • Withdrawal Update Form 2FORM 2 Q1 2627.pdf · uploaded 23 Sep 2026Source
  • Withdrawal Update Form 3FORM 3 Q1 2627.pdf · uploaded 23 Sep 2026Source

Technical

  • DocumentBUILDING A.pdf · uploaded 10 May 2021Source
  • Documentleyout plan wide main road01.pdf · uploaded 1 Jun 2021Source
  • Documentleyout plan wide main road02.pdf · uploaded 1 Jun 2021Source
  • Documentleyout plan1028052021.pdf · uploaded 1 Jun 2021Source
  • Documentfrist floor plan02.pdf · uploaded 1 Jun 2021Source
  • Documentsecond floor plan01.pdf · uploaded 1 Jun 2021Source
  • Documentthird floor plan02.pdf · uploaded 1 Jun 2021Source
  • Documentbulding approvid elevaqiy.pdf · uploaded 1 Jun 2021Source
  • Documentbulding approvid plan01.pdf · uploaded 1 Jun 2021Source
  • Documentbulding approvid plan02.pdf · uploaded 1 Jun 2021Source
  • Documentcertificat of area.pdf · uploaded 1 Jun 2021Source
  • Documentrera plan1.pdf · uploaded 8 May 2024Source
  • Documentrera plan2.pdf · uploaded 8 May 2024Source
  • Documentrera plan1.pdf · uploaded 8 May 2024Source
  • Documentrera plan2.pdf · uploaded 8 May 2024Source

Technical (Architect)

  • DocumentFORM 1 Q1 2627.pdf · uploaded 22 Sep 2026Source

Technical (Engineer)

  • DocumentFORM 2 Q1 2627.pdf · uploaded 22 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK, 3BHK, Shop27 units in all
Address
810, BHAWANI PETH PUNE, Pune, PunePIN 411002
Village
Peth, Haveli taluka
Designated bank account
109
Developed in phases
No

Boundaries

North
Cts No 814
South
Plot No 02
East
Cts No 809
West
Cts No 800 And 801

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking27 units

1 of 27 units booked (4%), as the promoter reported to MahaRERA

1BHK · 15 units1RK · 1 unit2BHK · 7 units3BHK · 1 unitShop · 3 units
TypeCarpet areaUnitsBooked
1BHK32.76 sq m · 353 sq ft10
1BHK32.93 sq m · 354 sq ft10
1BHK39.86 sq m · 429 sq ft10
1BHK41.46 sq m · 446 sq ft70
1BHK41.96 sq m · 452 sq ft10
1BHK42.85 sq m · 461 sq ft11
1BHK45.55 sq m · 490 sq ft10
1BHK47.79 sq m · 514 sq ft10
Show all 17 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK52.6 sq m · 566 sq ft10
1RK23.84 sq m · 257 sq ft10
2BHK58.36 sq m · 628 sq ft30
2BHK59.33 sq m · 639 sq ft30
2BHK75.71 sq m · 815 sq ft10
3BHK89.88 sq m · 967 sq ft10
Shop37.47 sq m · 403 sq ft10
Shop50.2 sq m · 540 sq ft10
Shop66.9 sq m · 720 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRahil Shaikh—
Chartered accountantDheeraj Dharmawat—
Chartered accountantSagar Sharad Dharmavat—
EngineerFarook Mulla—
EngineerShivaji Mane—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology