Its promised completion date, Mar 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Hadapsar, Pune 411028 · Property rates in Hadapsar · Promoter: nilesh mohandas navalakha
Its promised completion date, Mar 2026, has passed and MahaRERA does not show it completed
- This projectRegistered 9 Feb 2022, completion promised 31 Mar 2026, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100033110
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100033110 | 9 Feb 2022 | 31 Mar 2026 | 31 Mar 2026 | nilesh mohandas navalakha | Project page |
Documents99
1 document held by Deedo, 98 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card Nilesh sir.pdf · uploaded 29 Nov 2021Source
Legal
Migrated
- 1 PAN Cardpan card Nilesh sir.pdf · uploaded 29 Nov 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement certificate.pdf · uploaded 29 Nov 2021Source
- 1 Proforma of Allotment letterProforma_of_the_allotment_letter_and_agreement_for_sale final.pdf · uploaded 14 Dec 2021Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 29 Dec 2021Source
Show all 99 documentsShow fewer documents
Migrated
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect form 1.pdf · uploaded 30 Dec 2021Source
- 1 Copy of Layout Approval (in case of layout)1 PLAN.pdf · uploaded 4 Jan 2022Source
- 1 Building Plan Approval / NA Order for plotted development2 PLAN.pdf · uploaded 4 Jan 2022Source
- 1 Details of encumbrancesdeclaration for encumbrance.pdf · uploaded 5 Jan 2022Source
- 2 Proforma of Allotment letterRERA AGREEMENT.pdf · uploaded 5 Jan 2022Source
- 1 Declaration about Commencement CertificateDECLARATION AABOUT COMMENECEMENT.pdf · uploaded 6 Jan 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Certificates of CA (Form 3).pdf · uploaded 12 Jan 2022Source
- 1 Copy of the legal title reportMahaRERA Title_compressed.pdf · uploaded 7 Feb 2022Source
- 1 CERSAI detailsWaterfront.pdf · uploaded 7 Feb 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Waterfront as on March 2022.pdf · uploaded 18 Apr 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Waterfront as on June 2022.pdf · uploaded 18 Apr 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Waterfront as on September 2022.pdf · uploaded 18 Apr 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Waterfront as on December 2022.pdf · uploaded 18 Apr 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Waterfront as on March 2022.pdf · uploaded 18 Apr 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Waterfront as on June 2022.pdf · uploaded 18 Apr 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Waterfront as on September 2022.pdf · uploaded 18 Apr 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Waterfront as on December 2022.pdf · uploaded 18 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Certificate 609 (1)_compressed.pdf · uploaded 18 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)New Format Form 5 Waterfront FY22-23.pdf · uploaded 5 Dec 2023Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)New Format Form 5 Waterfront FY22-23.pdf · uploaded 5 Dec 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Waterfront as on March 2023.pdf · uploaded 27 Dec 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Waterfront as on June 2023.pdf · uploaded 27 Dec 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Waterfront as on September 2023.pdf · uploaded 27 Dec 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Waterfront as on 31-03-2023.pdf · uploaded 27 Dec 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Waterfront as on 30-06-2023.pdf · uploaded 27 Dec 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Waterfront as on 30-09-2023.pdf · uploaded 27 Dec 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Waterfront as on Dec 2023.pdf · uploaded 3 Feb 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Waterfront as on Dec 2023.pdf · uploaded 3 Feb 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Waterfront as on Dec 2023.pdf · uploaded 3 Feb 2024Source
- 2 Building Plan Approval / NA Order for plotted development1.pdf · uploaded 16 Feb 2024Source
- 3 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 16 Feb 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentWaterfront - Commencement Certificate.pdf · uploaded 16 Feb 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Waterfront as on March 2024.pdf · uploaded 4 May 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Waterfront as on March 2024.pdf · uploaded 4 May 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf · uploaded 20 Jul 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)9 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf · uploaded 20 Jul 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)jjjjjjjjjjjjjj.pdf · uploaded 20 Jul 2024Source
- 2 Copy of Layout Approval (in case of layout)11 plan_compressed.pdf · uploaded 7 Aug 2024Source
- 3 Copy of Layout Approval (in case of layout)11 plan (1)_compressed.pdf · uploaded 7 Aug 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Waterfront as on June 2024.pdf · uploaded 16 Aug 2024Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Waterfront as on June 2024.pdf · uploaded 16 Aug 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Waterfront as on 30-09-2024.pdf · uploaded 16 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Waterfront as on 30th September 2024.pdf · uploaded 16 Oct 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Waterfront as on 30-09-2024.pdf · uploaded 12 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 of Water Front - FY 2023-24.pdf · uploaded 12 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Sept 2024.pdf · uploaded 21 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Sept 2024.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 2021-22.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 2022-23.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2023-24.pdf · uploaded 21 Nov 2024Source
- 1 Disclosure of sold/ booked inventoryCircular 29 Sept 2024.pdf · uploaded 21 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Final.pdf · uploaded 21 Nov 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Sept 2024.pdf · uploaded 21 Nov 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Final.pdf · uploaded 21 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Sept 2024.pdf · uploaded 21 Nov 2024Source
- 1 Disclosure of sold/ booked inventoryCircular 29 Sept 2024.pdf · uploaded 21 Nov 2024Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 2021-22.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 2022-23.pdf · uploaded 21 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2023-24.pdf · uploaded 21 Nov 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 2023-24.pdf · uploaded 2 Dec 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Waterfront as on 31-12-2024.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Waterfront as on 31-12-2024.pdf · uploaded 20 Jan 2025Source
- Withdrawal Update Form 12 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 12 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 12 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 2Form 2 - Waterfront as on June 2024.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 2Form 2 - Waterfront as on June 2024.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 2Form 2 - Waterfront as on June 2024.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 3Form 3 - Waterfront as on June 2024.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 3Form 3 - Waterfront as on June 2024.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 3Form 3 - Waterfront as on June 2024.pdf · uploaded 6 Feb 2026Source
- Withdrawal Update Form 12 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2).pdf · uploaded 1 May 2026Source
- Withdrawal Update Form 2Form 2 - Waterfront as on June 2024.pdf · uploaded 1 May 2026Source
- Withdrawal Update Form 3Form 3 - Water Front as on March 2026.pdf · uploaded 1 May 2026Source
- Form 2A (FY 2025-2026)form 2a.pdf · uploaded 3 Aug 2026Source
Technical
- Document1 PLAN.pdf · uploaded 4 Jan 2022Source
- Document2 PLAN.pdf · uploaded 4 Jan 2022Source
- Document1.pdf · uploaded 16 Feb 2024Source
- Document2.pdf · uploaded 16 Feb 2024Source
- Document11 plan_compressed.pdf · uploaded 7 Aug 2024Source
- Document11 plan (1)_compressed.pdf · uploaded 7 Aug 2024Source
Technical (Architect)
Technical (Engineer)
- DocumentForm 2 - Waterfront as on June 2024.pdf · uploaded 16 Aug 2024Source
- DocumentForm 2 - Waterfront as on 30th September 2024.pdf · uploaded 16 Oct 2024Source
- DocumentForm 2 - Sept 2024.pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 - Sept 2024.pdf · uploaded 21 Nov 2024Source
- DocumentForm 2 - Waterfront as on 31-12-2024.pdf · uploaded 20 Jan 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals256/13B/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1RK55 units in all
- Address
- 256/13b/2, 256/13b Hadapsar, Canal Road, Near Tupe Shooting RangePIN 411028
- Village
- Hadapsar, Haveli taluka
- Location
- 18.52322, 73.93214
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 256
- South
- 152
- East
- 256
- West
- Road And Canal
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking55 units
0 of 55 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1RK | 17.25 sq m · 186 sq ft | 12 | 0 |
| 1RK | 18.4 sq m · 198 sq ft | 6 | 0 |
| 1RK | 18.75 sq m · 202 sq ft | 6 | 0 |
| 1RK | 19.55 sq m · 210 sq ft | 13 | 0 |
| 1RK | 21.05 sq m · 227 sq ft | 6 | 0 |
| 1RK | 21.76 sq m · 234 sq ft | 6 | 0 |
| 1RK | 24.4 sq m · 263 sq ft | 6 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.