Deedo IDDP-PUN-C5R1Completion was pushed back 6 months to Mar 2023, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.
Hadapsar, Pune 411028 · Property rates in Hadapsar · Promoter: Dilip Sahebrao Gaikwad
Completion was pushed back 6 months to Mar 2023, and that date has passed too
- This projectRegistered 24 Nov 2020, completion promised 30 Sep 2022, revised to 31 Mar 2023, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100027192
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100027192 | 24 Nov 2020 | 30 Sep 2022 | 31 Mar 2023 | Dilip Sahebrao Gaikwad | Project page |
Documents26
2 documents held by Deedo, 24 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD Dilip Gaikwad.pdf · uploaded 20 Nov 2020Source
Legal
Show all 26 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)LAYOUT SANCTION.pdf · uploaded 20 Nov 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentPLAN APPROVAL.pdf · uploaded 20 Nov 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERT.pdf · uploaded 20 Nov 2020Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 20 Nov 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_1.pdf · uploaded 20 Nov 2020Source
- 1 Proforma of Allotment letterPROFORMA1.pdf · uploaded 20 Nov 2020Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Filled form-3.pdf · uploaded 29 Sep 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form-5.pdf · uploaded 29 Sep 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5.pdf · uploaded 29 Sep 2022Source
- 1 Declaration about Commencement CertificateD Comence Ment Certicate.pdf · uploaded 27 Oct 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)From 2A 20-21.pdf · uploaded 27 Oct 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)From 2A 21-22.pdf · uploaded 27 Oct 2022Source
- 1 Disclosure of sold/ booked inventoryBook Inventory.pdf · uploaded 27 Oct 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)From 5 Fy 21-22.pdf · uploaded 27 Oct 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPMC completion Certificate.pdf · uploaded 20 Jan 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)completion_artechitect.pdf · uploaded 20 Jan 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSr.No.13/3E/1B
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK13 units in all
- Address
- Sr.No.13/3E/1B, Near Saswad Road, HadapsarPIN 411028
- Village
- Hadapsar, Haveli taluka
- Designated bank account
- 17
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 13 Part
- South
- 13 Part
- East
- Road
- West
- 13 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking13 units
0 of 13 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 42 sq m · 452 sq ft | 13 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Shri Sunder S Sable | — |
| Chartered accountant | Ashish Kumar Agrawal | — |
| Engineer | Shantisagar Sukhadeo Sabale | — |
Source: MahaRERA project page. Contact details are not shown.