Skip to content
Residential / Group Housing · 8 buildings · 66 unitsRERA P52100019192 +2

Avior Aatman

Deedo IDDP-PUN-MTQR

MahaRERA shows it completed; no MahaRERA orders on record; 68% of its units are booked.

Ghorapade Peth, Pune 411042 · by Aviorenterprises Llp · 100% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales68% booked45 of 66 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • P52100019192Registered 9 Jan 2019, completion promised 30 Dec 2022.
  • P52100019422Registered 29 Jan 2019, completion promised 30 Dec 2022.
  • P52100029907Registered 15 Jul 2021, completion promised 30 Jun 2023.

No extension certificate on record.

3 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

8 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations3
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000191929 Jan 201930 Dec 202230 Dec 2022Aviorenterprises LLPProject page
P5210001942229 Jan 201930 Dec 202230 Dec 2022Aviorenterprises LLPProject page
P5210002990715 Jul 202130 Jun 202330 Jun 2023Aviorenterprises LLPProject page
Documents169

6 documents held by Deedo, 163 filings listed on MahaRERA's project page

Registration certificate (3)

  • Registration certificateP52100029907 · 15 Jul 2021ViewSource
  • Registration certificateP52100019192 · 9 Sep 2021ViewSource
  • Registration certificateP52100019422 · 9 Sep 2021ViewSource

Other (3)

  • OtherP52100019192 · Date not statedView
  • OtherP52100019422 · Date not statedView
  • OtherP52100029907 · Date not statedView

Finance

  • PAN CardP52100019422 · Avior Enterprises LLP Pan Card.pdf · uploaded 23 Jan 2019Source
  • PAN CardP52100029907 · Avior Enterises LLP PAN.pdf · uploaded 12 Jun 2021Source
Show all 169 documentsShow fewer documents

Finance

  • PAN CardP52100019192 · Avior Enterprises LLP Pan Card.pdf · uploaded 4 Dec 2021Source

Legal

  • Legal Title reportP52100019192 · Search Title Report.pdf · uploaded 4 Jan 2019Source
  • Declaration Form BP52100019192 · Declaration -Promoters.pdf · uploaded 4 Jan 2019Source
  • Declaration Form BP52100019422 · Declaration -Promoters.pdf · uploaded 23 Jan 2019Source
  • Legal Title reportP52100019422 · Search Title Report.pdf · uploaded 23 Jan 2019Source
  • Legal Title reportP52100029907 · Search Title Report.pdf · uploaded 12 Jun 2021Source
  • Declaration Form BP52100029907 · Declaration - Developer.pdf · uploaded 12 Jun 2021Source
  • Legal Title reportP52100029907 · Search Report Format A - for Rera1.pdf · uploaded 6 Jul 2021Source

Migrated

  • 1 Copy of the legal title reportP52100019192 · Search Title Report.pdf · uploaded 4 Jan 2019Source
  • 1 Details of encumbrancesP52100019192 · Non-Encumbrance.pdf · uploaded 4 Jan 2019Source
  • 1 Copy of Layout Approval (in case of layout)P52100019192 · Layout Plan - 31-12-2018.pdf · uploaded 4 Jan 2019Source
  • 1 Building Plan Approval (IOD)P52100019192 · Building Plan 1-1 - 31-12-2018.pdf · uploaded 4 Jan 2019Source
  • 2 Building Plan Approval (IOD)P52100019192 · Building Plan 2-2 - 31-12-2018.pdf · uploaded 4 Jan 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100019192 · CC - Building Plan - 31-12-2018.pdf · uploaded 4 Jan 2019Source
  • 1 Declaration in FORM BP52100019192 · Declaration -Promoters.pdf · uploaded 4 Jan 2019Source
  • 1 Certificates of CA (Form 3)P52100019192 · CA Certificate - 04-01-19.pdf · uploaded 4 Jan 2019Source
  • 1 Proforma of Allotment letterP52100019192 · Flat agr Phase-1.pdf · uploaded 4 Jan 2019Source
  • 1 PAN CardP52100019422 · Avior Enterprises LLP Pan Card.pdf · uploaded 23 Jan 2019Source
  • 1 Copy of the legal title reportP52100019422 · Search Title Report.pdf · uploaded 23 Jan 2019Source
  • 1 Details of encumbrancesP52100019422 · Non-Encumbrance.pdf · uploaded 23 Jan 2019Source
  • 1 Copy of Layout Approval (in case of layout)P52100019422 · Layout Plan - 31-12-2018.pdf · uploaded 23 Jan 2019Source
  • 1 Building Plan Approval (IOD)P52100019422 · Plan.pdf · uploaded 23 Jan 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100019422 · CC - Building Plan - 31-12-2018.pdf · uploaded 23 Jan 2019Source
  • 1 Declaration in FORM BP52100019422 · Declaration -Promoters.pdf · uploaded 23 Jan 2019Source
  • 1 Certificates of CA (Form 3)P52100019422 · CA Certificate Aatman Phase 2 - 24-01-19-ilovepdf-compressed.pdf · uploaded 24 Jan 2019Source
  • 1 Proforma of Allotment letterP52100019422 · Flat agr Phase 2 - 24012019.pdf · uploaded 24 Jan 2019Source
  • 1 Form 2AP52100019422 · Engineer 2A Form - 13-04-19.pdf · uploaded 13 Apr 2019Source
  • 1 Form 2AP52100019192 · Engineer 2A From - 13-04-19.pdf · uploaded 13 Apr 2019Source
  • 2 Form 2AP52100019422 · Engineer 2A Form - Jun19.pdf · uploaded 15 Jul 2019Source
  • 2 Form 2AP52100019192 · Engineer 2A From - Jun19.pdf · uploaded 15 Jul 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)P52100019422 · Form 5 -2018-2019 - Phase-2.pdf · uploaded 15 Oct 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)P52100019192 · From 5 - 2018-2019 - Phase-1.pdf · uploaded 15 Oct 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100019422 · Form 5 -2018-2019 - Phase-2.pdf · uploaded 10 Dec 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100019192 · From 5 - 2018-2019 - Phase-1.pdf · uploaded 10 Dec 2019Source
  • 3 Form 2AP52100019422 · Engineer 2A From - Sept19.pdf · uploaded 13 Feb 2020Source
  • 4 Form 2AP52100019422 · Engineer 2A From - Dec19.pdf · uploaded 13 Feb 2020Source
  • 3 Form 2AP52100019192 · Engineer 2A From - Sept 19.pdf · uploaded 13 Feb 2020Source
  • 4 Form 2AP52100019192 · Engineer 2A From - Dec 19.pdf · uploaded 13 Feb 2020Source
  • 5 Form 2AP52100019422 · Engineer 2A Form - Mar-Jun-20.pdf · uploaded 4 Jul 2020Source
  • 5 Form 2AP52100019192 · Engineers Certificate 2A Form - Mar and Jun 20.pdf · uploaded 4 Jul 2020Source
  • 1 Details of Restarting of Construction work post lockdownP52100019422 · Avior Aatman Phase - 2 - Covid 19.pdf · uploaded 15 Jul 2020Source
  • 1 Details of Restarting of Construction work post lockdownP52100019192 · Avior Aatman - Covid19.pdf · uploaded 15 Jul 2020Source
  • 2 Building Plan Approval (IOD)P52100019422 · Revise Plan - 01-02.pdf · uploaded 30 Oct 2020Source
  • 3 Building Plan Approval (IOD)P52100019422 · Revise Plan - 02-02.pdf · uploaded 30 Oct 2020Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100019422 · CC - 27-10-20.pdf · uploaded 30 Oct 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100019422 · AE LLP - AATMAN PHASE 2 - 2019-2020.pdf · uploaded 13 May 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100019192 · AE LLP - AATMAN PHASE 1 - 2019-2020.pdf · uploaded 13 May 2021Source
  • 1 PAN CardP52100029907 · Avior Enterises LLP PAN.pdf · uploaded 12 Jun 2021Source
  • 1 Copy of the legal title reportP52100029907 · Search Title Report.pdf · uploaded 12 Jun 2021Source
  • 1 Details of encumbrancesP52100029907 · Non-encumbrances letter.pdf · uploaded 12 Jun 2021Source
  • 1 Copy of Layout Approval (in case of layout)P52100029907 · Layout Plan-478-2-2-7-6-21.pdf · uploaded 12 Jun 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100029907 · Plan-478-1-2-7-6-21.pdf · uploaded 12 Jun 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100029907 · Commencement Certificate - 478-7-6-21.pdf · uploaded 12 Jun 2021Source
  • 1 Declaration in FORM BP52100029907 · Declaration - Developer.pdf · uploaded 12 Jun 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100029907 · CA Certificate - 11-06-21.pdf · uploaded 12 Jun 2021Source
  • 1 Proforma of Allotment letterP52100029907 · Agreement - Phase 3.pdf · uploaded 12 Jun 2021Source
  • 1 Disclosure of sold/ booked inventoryP52100019422 · Avior Aatman Phase 2.pdf · uploaded 14 Jun 2021Source
  • 1 Disclosure of sold/ booked inventoryP52100019192 · Avior Aatman.pdf · uploaded 14 Jun 2021Source
  • 2 Copy of the legal title reportP52100029907 · Search Report Format A - for Rera1.pdf · uploaded 6 Jul 2021Source
  • 1 Declaration about Commencement CertificateP52100029907 · Aatman - Declaration - Format D.pdf · uploaded 6 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100029907 · 2A Form Aataman - Sept-21.pdf · uploaded 16 Oct 2021Source
  • 6 Form 2AP52100019422 · 2A Form Aataman - Sept20-Sept21.pdf · uploaded 16 Oct 2021Source
  • 6 Form 2AP52100019192 · 2A Form Aataman - Sept20-Sept-21.pdf · uploaded 16 Oct 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100029907 · 2A Form Aataman - Sept-21.pdf · uploaded 4 Dec 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100019422 · 2A Form Aataman - Sept20-Sept21.pdf · uploaded 4 Dec 2021Source
  • 1 PAN CardP52100019192 · Avior Enterprises LLP Pan Card.pdf · uploaded 4 Dec 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100019192 · 2A Form Aataman - Sept20-Sept-21.pdf · uploaded 4 Dec 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100029907 · 2A Certificate Aataman Phase III - Dec 21.pdf · uploaded 18 Jan 2022Source
  • 7 Form 2AP52100019422 · 2A Certificate Aatman Ph-II-Dec 21.pdf · uploaded 18 Jan 2022Source
  • 7 Form 2AP52100019192 · 2A Certificate Aataman Phase I - Dec 21.pdf · uploaded 18 Jan 2022Source
  • 2 Disclosure of sold/ booked inventoryP52100019422 · Aatman Ph II - Disclosure - Sept 21_II.pdf · uploaded 8 Feb 2022Source
  • 3 Disclosure of sold/ booked inventoryP52100019422 · AELLP - Disclosure - Ph 2 - 31-03-21_II.pdf · uploaded 8 Feb 2022Source
  • 4 Disclosure of sold/ booked inventoryP52100019422 · AELLP - Disclosure - Ph 2 - 30-06-21_II.pdf · uploaded 8 Feb 2022Source
  • 2 Certificates of CA (Form 3)P52100019422 · Form 3 CA Certificate Phase 2_30-09-2021.pdf · uploaded 8 Feb 2022Source
  • 3 Certificates of CA (Form 3)P52100019422 · CA Certificate Phase 2_31-03-2021.pdf · uploaded 8 Feb 2022Source
  • 4 Certificates of CA (Form 3)P52100019422 · CA Certificate Phase 2_30-06-2021.pdf · uploaded 8 Feb 2022Source
  • 2 Disclosure of sold/ booked inventoryP52100019192 · Aatman Ph I - Disclosure - Sept 21_I.pdf · uploaded 8 Feb 2022Source
  • 3 Disclosure of sold/ booked inventoryP52100019192 · AELLP - Disclosure - Ph 1 - 31-03-21_I.pdf · uploaded 8 Feb 2022Source
  • 4 Disclosure of sold/ booked inventoryP52100019192 · AELLP - Disclosure - Ph 1 - 30-06-21.pdf · uploaded 8 Feb 2022Source
  • 2 Certificates of CA (Form 3)P52100019192 · Form 3 CA Certificate Phase 1_30-09-2021.pdf · uploaded 8 Feb 2022Source
  • 3 Certificates of CA (Form 3)P52100019192 · CA Certificate Phase 1_31-03-2021.pdf · uploaded 8 Feb 2022Source
  • 4 Certificates of CA (Form 3)P52100019192 · CA Certificate Phase 1_30-06-2021.pdf · uploaded 8 Feb 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100029907 · Completion Certificate.pdf · uploaded 1 Dec 2022Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)P52100029907 · Architect Certificate - Form 4-3.pdf · uploaded 1 Dec 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100019422 · Completion Certificate.pdf · uploaded 1 Dec 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100019192 · Completion Certificate.pdf · uploaded 1 Dec 2022Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100029907 · Society Registration Certificate.pdf · uploaded 29 Dec 2022Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100019422 · Society Registration Certificate.pdf · uploaded 29 Dec 2022Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100019192 · Society Registration Certificate.pdf · uploaded 29 Dec 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100029907 · 2A Certificate Aataman Phase III - Dec 21.pdf · uploaded 24 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100019422 · 2A Form Aataman Ph-II - Sept20-Sept21.pdf · uploaded 24 Jan 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100019422 · 2A Certificate Aatman Ph-II-Dec 21.pdf · uploaded 24 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100019422 · Form - 5 - Aatman II - 2020 -2021.pdf · uploaded 24 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100019192 · 2A Form Aataman Ph-I- Sept20-Sept-21.pdf · uploaded 24 Jan 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100019192 · 2A Certificate Aataman Phase I - Dec 21.pdf · uploaded 24 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100019192 · Form - 5 - Aatmant - 2020-2021.pdf · uploaded 24 Jan 2023Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)P52100019422 · Form 4 - Architects Certificate Aatman Phase 2.pdf · uploaded 15 Feb 2023Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)P52100019192 · Form 4 - Architects Certificate Aatman Phase 1.pdf · uploaded 15 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100029907 · Form 2 Engineer - Aatman Phase - 3 - MAR 2022.pdf · uploaded 25 Feb 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100029907 · Form 2A Aatman Phase 3 - Mar-2022.pdf · uploaded 25 Feb 2023Source
  • 1 Disclosure of sold/ booked inventoryP52100029907 · Disclosure - Aatman -III - Mar -22.pdf · uploaded 25 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100029907 · Form - 3- Aatman - III - Mar - 22.pdf · uploaded 25 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100029907 · Form - 5- Aatman - III - 2021-2022.pdf · uploaded 25 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100019422 · Form 2 Engineer - Aatman Phase - 2 - MAR 2022.pdf · uploaded 25 Feb 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100019422 · Form 2A Aatman Phase 2 - Mar-2022.pdf · uploaded 25 Feb 2023Source
  • 5 Disclosure of sold/ booked inventoryP52100019422 · Disclosure - Aatman -II - Dec -21.pdf · uploaded 25 Feb 2023Source
  • 6 Disclosure of sold/ booked inventoryP52100019422 · Disclosure - Aatman - II - Mar - 22.pdf · uploaded 25 Feb 2023Source
  • 5 Certificates of CA (Form 3)P52100019422 · Form - 3- Aatman -II - Dec -21.pdf · uploaded 25 Feb 2023Source
  • 6 Certificates of CA (Form 3)P52100019422 · Form - 3 - Aatman - II - Mar - 22.pdf · uploaded 25 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100019422 · From - 5 - Aatman - II - 2021-2022.pdf · uploaded 25 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100019192 · Form 2 Engineer - Aatman Phase - 1 - MAR 2022.pdf · uploaded 25 Feb 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100019192 · Form 2A Aatman Phase 1- Mar-2022.pdf · uploaded 25 Feb 2023Source
  • 5 Disclosure of sold/ booked inventoryP52100019192 · Disclosure - Aatman -I - Dec -21.pdf · uploaded 25 Feb 2023Source
  • 6 Disclosure of sold/ booked inventoryP52100019192 · Disclosure - Aatman -I - Mar - 22.pdf · uploaded 25 Feb 2023Source
  • 5 Certificates of CA (Form 3)P52100019192 · Form - 3- Aatman -I - Dec -21.pdf · uploaded 25 Feb 2023Source
  • 6 Certificates of CA (Form 3)P52100019192 · Form - 3 - Aatman -I- Mar - 22.pdf · uploaded 25 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100019192 · Form -5 - Aatman - I - 2021-2022.pdf · uploaded 25 Feb 2023Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)P52100029907 · Form 4 - Aatman - III.pdf · uploaded 6 Apr 2023Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)P52100019422 · Form 4 - Aatman - II.pdf · uploaded 6 Apr 2023Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)P52100019192 · Form 4 - Aatman - I.pdf · uploaded 6 Apr 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100029907 · Form 2 - Aatman -III - Jun 22.pdf · uploaded 22 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100029907 · Form 2 - Aatman -III - Sept 22.pdf · uploaded 22 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100029907 · Form 2A Aatman Phase 3 - Jun-2022.pdf · uploaded 22 Aug 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100029907 · Form 2A Aatman Phase 3 - Sep-2022.pdf · uploaded 22 Aug 2023Source
  • 2 Disclosure of sold/ booked inventoryP52100029907 · Disclosure - Aatman - III - Jun - 22.pdf · uploaded 22 Aug 2023Source
  • 3 Disclosure of sold/ booked inventoryP52100029907 · Disclosure - Aatman - III - Sept - 22.pdf · uploaded 22 Aug 2023View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100029907 · Form -3 - Aatman - III - Jun - 22.pdf · uploaded 22 Aug 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100029907 · Form -3 - Aatman - III - Sept - 22.pdf · uploaded 22 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100019422 · Form 2 - Aatman-II - Jun 22.pdf · uploaded 22 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100019422 · Form 2 - Aatman-II - Sept 22.pdf · uploaded 22 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100019422 · Form 2A Aatman Phase 2 - Jun-2022.pdf · uploaded 22 Aug 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100019422 · Form 2A Aatman Phase 2 - Sep-2022.pdf · uploaded 22 Aug 2023Source
  • 7 Disclosure of sold/ booked inventoryP52100019422 · Disclosure - Aatman - II - Jun - 22.pdf · uploaded 22 Aug 2023Source
  • 8 Disclosure of sold/ booked inventoryP52100019422 · Disclosure - Aatman - II - Sept - 22.pdf · uploaded 22 Aug 2023View
  • 7 Certificates of CA (Form 3)P52100019422 · Form -3 - Aatman - II - Jun - 22.pdf · uploaded 22 Aug 2023Source
  • 8 Certificates of CA (Form 3)P52100019422 · Form -3 - Aatman - II - Sept - 22.pdf · uploaded 22 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100019192 · Form 2 - Aatman-I - Jun 22.pdf · uploaded 22 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100019192 · Form 2 - Aatman-I - Sept 22_compressed.pdf · uploaded 22 Aug 2023Source
  • 8 Form 2AP52100019192 · Form 2A Aatman Phase 1 - Jun-2022.pdf · uploaded 22 Aug 2023Source
  • 9 Form 2AP52100019192 · Form 2A Aatman Phase 1 - Sep-2022.pdf · uploaded 22 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100019192 · Form 2A Aatman Phase 1 - Jun-2022.pdf · uploaded 22 Aug 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100019192 · Form 2A Aatman Phase 1 - Sep-2022.pdf · uploaded 22 Aug 2023Source
  • 7 Disclosure of sold/ booked inventoryP52100019192 · Disclosure - Aatman - I - Jun - 22.pdf · uploaded 22 Aug 2023Source
  • 8 Disclosure of sold/ booked inventoryP52100019192 · Disclosure - Aatman - I - Sept - 22.pdf · uploaded 22 Aug 2023View
  • 7 Certificates of CA (Form 3)P52100019192 · Form -3 - Aatman - I - Jun - 22.pdf · uploaded 22 Aug 2023Source
  • 8 Certificates of CA (Form 3)P52100019192 · Form -3 - Aatman - I - Sept - 22.pdf · uploaded 22 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100029907 · Form 5 - AELLP PH-3.pdf · uploaded 15 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100019422 · Form 5 - AELLP PH-2.pdf · uploaded 15 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100019192 · Form 5 - AELLP PH-1.pdf · uploaded 15 Mar 2024Source

Technical

  • DocumentP52100019192 · Layout Plan - 31-12-2018.pdf · uploaded 4 Jan 2019Source
  • DocumentP52100019192 · Building Plan 1-1 - 31-12-2018.pdf · uploaded 4 Jan 2019Source
  • DocumentP52100019192 · Building Plan 2-2 - 31-12-2018.pdf · uploaded 4 Jan 2019Source
  • DocumentP52100019422 · Layout Plan - 31-12-2018.pdf · uploaded 23 Jan 2019Source
  • DocumentP52100019422 · Plan.pdf · uploaded 23 Jan 2019Source
  • DocumentP52100019422 · Revise Plan - 01-02.pdf · uploaded 30 Oct 2020Source
  • DocumentP52100019422 · Revise Plan - 02-02.pdf · uploaded 30 Oct 2020Source
  • DocumentP52100029907 · Layout Plan-478-2-2-7-6-21.pdf · uploaded 12 Jun 2021Source
  • DocumentP52100029907 · Plan-478-1-2-7-6-21.pdf · uploaded 12 Jun 2021Source

Technical (Engineer)

  • DocumentP52100029907 · Form 2 - Aatman -III - Sept 22.pdf · uploaded 22 Aug 2023Source
  • DocumentP52100019422 · Form 2 - Aatman-II - Sept 22.pdf · uploaded 22 Aug 2023Source
  • DocumentP52100019192 · Form 2 - Aatman-I - Sept 22_compressed.pdf · uploaded 22 Aug 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 287/2, 287/23

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
3
Unit types
2 BHK, 1BHK, 2BHK66 units in all
Address
287/2 And 3, Ekbote Colony, Ghorpade PethPIN 411042
Village
Pune (M Corp.), Pune City taluka
Land area for this project
1,424 sq m (15,332 sq ft)
Permissible built-up area
3,423 sq m (36,847 sq ft)
Sanctioned built-up area
1,349 sq m (14,519 sq ft)
Designated bank account
171
Developed in phases
No
Also registered as
Avior -Aatman Phase -II, Avior-Aatman Phase - III

Survey, CTS, gat or plot numbers

287/2287/233

Land as published on MahaRERA's project page

287/2 AND 3

Boundaries

North
24 M Dp Road
South
Final Plot No 287-4 And 5
East
9 M Dp Road
West
Final Plot No 287-1

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking66 units

45 of 66 units booked (68%), as the promoter reported to MahaRERA

2 BHK · 48 units1BHK · 1 unit2BHK · 17 units
RERABuildingTypeCarpet areaUnitsBooked
P52100019192Avior Aatman - Phase -12 BHK52.31 sq m · 563 sq ft44
P52100019192Avior Aatman - Phase -12 BHK53.32 sq m · 574 sq ft43
P52100019192Avior Aatman - Phase -12 BHK53.84 sq m · 580 sq ft32
P52100019192Avior Aatman - Phase -12 BHK56.59 sq m · 609 sq ft33
P52100019192Avior Aatman - Phase -12 BHK56.68 sq m · 610 sq ft40
P52100019192Avior Aatman - Phase -12 BHK59 sq m · 635 sq ft33
P52100019422AVIOR AATMAN - PHASE-II- 4th to 9th Floor1BHK42.58 sq m · 458 sq ft10
P52100019422AVIOR AATMAN - PHASE-II- 4th to 9th Floor2 BHK53.32 sq m · 574 sq ft54
Show all 19 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P52100019422AVIOR AATMAN - PHASE-II- 4th to 9th Floor2 BHK53.84 sq m · 580 sq ft62
P52100019422AVIOR AATMAN - PHASE-II- 4th to 9th Floor2 BHK56.59 sq m · 609 sq ft65
P52100019422AVIOR AATMAN - PHASE-II- 4th to 9th Floor2 BHK56.68 sq m · 610 sq ft43
P52100019422AVIOR AATMAN - PHASE-II- 4th to 9th Floor2 BHK59 sq m · 635 sq ft66
P52100019422AVIOR AATMAN - PHASE-II- 4th to 9th Floor2BHK52.31 sq m · 563 sq ft55
P52100029907AVIOR-AATMAN PHASE - III-10th and 11th Floor2BHK52.31 sq m · 563 sq ft20
P52100029907AVIOR-AATMAN PHASE - III-10th and 11th Floor2BHK53.32 sq m · 574 sq ft20
P52100029907AVIOR-AATMAN PHASE - III-10th and 11th Floor2BHK53.84 sq m · 580 sq ft20
P52100029907AVIOR-AATMAN PHASE - III-10th and 11th Floor2BHK56.59 sq m · 609 sq ft22
P52100029907AVIOR-AATMAN PHASE - III-10th and 11th Floor2BHK56.68 sq m · 610 sq ft22
P52100029907AVIOR-AATMAN PHASE - III-10th and 11th Floor2BHK59 sq m · 635 sq ft21

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals22

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectPrakash Chandak—P52100029907
ArchitectPrakash Chandak—P52100019192
ArchitectPrakash Chandak—P52100019422
Chartered accountantCA Rohan Shaha—P52100029907
EngineerAjinkya Gaikwad—P52100029907
OtherG. A. Bhilare Consultant Pvt. Ltd.—P52100019422
OtherG. A. Bhilare Consultant Pvt. Ltd.—P52100019192
Registered real estate agent360 Realtors LLP—P52100019192
Show all 22 professionalsShow fewer professionals
RoleNameRegistration no.RERA
Registered real estate agent360 Realtors LLP—P52100019422
Registered real estate agent360 Realtors LLP—P52100029907
Registered real estate agentANAROCK Property Consultants Pvt. Ltd.—P52100019192
Registered real estate agentANAROCK Property Consultants Pvt. Ltd.—P52100019422
Registered real estate agentHDFC Realty Limited—P52100019422
Registered real estate agentHDFC Realty Limited—P52100019192
Registered real estate agentProptiger Marketing Services Private Limited—P52100019192
Registered real estate agentQuikr Realty Limited—P52100029907
Registered real estate agentR-Constellation Pvt. Ltd.—P52100019192
Registered real estate agentR-Constellation Pvt. Ltd.—P52100019422
Registered real estate agentSquare Yards Consulting Private Limited—P52100019192
Registered real estate agentSquare Yards Consulting Private Limited—P52100019422
Registered real estate agentSquare Yards Consulting Private Limited—P52100029907
Registered real estate agentSuggested Property Private Limited—P52100019192

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology