Residential / Group Housing · 7 buildings · 40 unitsRERA P52100031657

O2

Deedo IDDP-PUN-GY83

It is due for completion in Dec 2028, with no extension on record; no MahaRERA orders on record; 0% of its units are booked.

Donaje, Pune 411025 · Promoter: Aahan Buildcon

DeliveryDue Dec 2028No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 40 units · as the promoter reported to MahaRERA
O2 project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

It is due for completion in Dec 2028, with no extension on record

  • This projectRegistered 3 Nov 2021, completion promised 31 Dec 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

7 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100031657
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000316573 Nov 202131 Dec 202831 Dec 2028Aahan BuildconProject page
Documents121

1 document held by Deedo, 120 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardaahan buildcon pancard.pdf · uploaded 5 Oct 2021Source

Legal

  • Legal Title reportsearch report_compressed.pdf · uploaded 6 Oct 2021Source
  • Legal Title reporttitle report format A.pdf · uploaded 6 Oct 2021Source
  • Declaration Form BForm B.pdf · uploaded 6 Oct 2021Source

Migrated

  • 1 PAN Cardaahan buildcon pancard.pdf · uploaded 5 Oct 2021Source
  • 1 Details of encumbrancesEncumbarance.pdf · uploaded 5 Oct 2021Source
  • 1 Copy of the legal title reportsearch report_compressed.pdf · uploaded 6 Oct 2021Source
Show all 121 documentsShow fewer documents

Migrated

  • 2 Copy of the legal title reporttitle report format A.pdf · uploaded 6 Oct 2021Source
  • 1 Copy of Layout Approval (in case of layout)layout plan_compressed-1-2.pdf · uploaded 6 Oct 2021Source
  • 2 Copy of Layout Approval (in case of layout)layout plan_compressed-3-5-3(1).pdf · uploaded 6 Oct 2021Source
  • 3 Copy of Layout Approval (in case of layout)layout plan_compressed-6-7.pdf · uploaded 6 Oct 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 6 Oct 2021Source
  • 1 Declaration about Commencement CertificateRevise format D.pdf · uploaded 6 Oct 2021Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 6 Oct 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_compressed.pdf · uploaded 6 Oct 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Final Form 2_compressed.pdf · uploaded 6 Oct 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A.pdf · uploaded 6 Oct 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 6 Oct 2021Source
  • 1 Proforma of Allotment letterFlat Booking Agreement-Donaje-Ahan Buildcon.pdf · uploaded 6 Oct 2021Source
  • 2 Proforma of Allotment letterAllotment letter.pdf · uploaded 6 Oct 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentSITE PLAN.pdf · uploaded 11 Oct 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentSKMBT_C36021102822110 - Copy_compressed.pdf · uploaded 29 Oct 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_compressed.pdf · uploaded 15 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 RERA_merged_compressed.pdf · uploaded 15 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 RERA.pdf · uploaded 15 Feb 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2_compressed.pdf · uploaded 23 Feb 2023Source
  • 1 Disclosure of sold/ booked inventorySold unsold.pdf · uploaded 23 Feb 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 (4)_compressed.pdf · uploaded 12 Apr 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Rera Aahan Buildcon_compressed.pdf · uploaded 5 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Rera Aahan Buildcon.pdf · uploaded 5 Jul 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Rera Aahan Buildcon.pdf · uploaded 5 Jul 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1.pdf · uploaded 29 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 .pdf · uploaded 3 Jun 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Buildcon 3A_organized.pdf · uploaded 3 Jun 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate (10)_11zon.pdf · uploaded 4 Jun 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentT P Office Letter.pdf · uploaded 15 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)DONGE_98 merge (3)_compressed (1).pdf · uploaded 8 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Ahan Buildcon Form 3 (1).pdf · uploaded 8 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)O2 (1) (2).pdf · uploaded 8 Mar 2025Source
  • Form 1Dec 2022 Form 1.pdf · uploaded 21 Aug 2025Source
  • Form 2O2 Dec 22 Form 2.pdf · uploaded 21 Aug 2025Source
  • Form 3O2 Dec 2022 Form 3.pdf · uploaded 21 Aug 2025Source
  • Disclosure of Sold and Booked InventoryDec 2022 Sold Unsold.pdf · uploaded 21 Aug 2025Source
  • Form 1March 2023 Form 1.pdf · uploaded 21 Aug 2025Source
  • Form 2O2 March 23 Form 2.pdf · uploaded 21 Aug 2025Source
  • Form 3O2 March 2023 Form 3.pdf · uploaded 21 Aug 2025Source
  • Disclosure of Sold and Booked InventoryMarch 2023 Sold Unsold.pdf · uploaded 21 Aug 2025Source
  • Form 1Jun 2023 Form 1_compressed.pdf · uploaded 21 Aug 2025Source
  • Form 2o2 Jun 23 Form 2.pdf · uploaded 21 Aug 2025Source
  • Form 3O2 June 2023 Form 3.pdf · uploaded 21 Aug 2025Source
  • Disclosure of Sold and Booked InventoryJun 2023 Sold Unsold.pdf · uploaded 21 Aug 2025Source
  • Form 1Sep 2023 Form 1_compressed.pdf · uploaded 21 Aug 2025Source
  • Form 2O2 Sep 23 Form 2.pdf · uploaded 21 Aug 2025Source
  • Form 3O2 Sept 2023 Form 3.pdf · uploaded 21 Aug 2025Source
  • Disclosure of Sold and Booked InventorySep 2023 Sold Unsold.pdf · uploaded 21 Aug 2025Source
  • Form 1March 2024 Form 1.pdf · uploaded 21 Aug 2025Source
  • Form 2March 2024 Form 2.pdf · uploaded 21 Aug 2025Source
  • Form 3O2 March 2024 Form 3.pdf · uploaded 21 Aug 2025Source
  • Disclosure of Sold and Booked InventoryMarch 2024 Sold Unsold.pdf · uploaded 21 Aug 2025Source
  • Form 1Jun 2024 Form 1_compressed.pdf · uploaded 21 Aug 2025Source
  • Form 2O2 june 24 Form 2.pdf · uploaded 21 Aug 2025Source
  • Form 3O2 June 2024 Form 3.pdf · uploaded 21 Aug 2025Source
  • Disclosure of Sold and Booked InventoryJun 24 Sold Unsold.pdf · uploaded 21 Aug 2025Source
  • Form 1Sep 2024 Form 1 O2_compressed.pdf · uploaded 21 Aug 2025Source
  • Form 2O2 sep 24 Form 2.pdf · uploaded 21 Aug 2025Source
  • Form 3O2 Sept 2024 Form 3.pdf · uploaded 21 Aug 2025Source
  • Disclosure of Sold and Booked InventorySep 2024 Sold Unsold.pdf · uploaded 21 Aug 2025Source
  • Form 1March 2025 Form 1 s_compressed (1).pdf · uploaded 21 Aug 2025Source
  • Form 2O2 March 25 Form 2.pdf · uploaded 21 Aug 2025Source
  • Form 3O2 March 2025 Form 3.pdf · uploaded 21 Aug 2025Source
  • Disclosure of Sold and Booked InventoryMarch 2025 Sold Unsold.pdf · uploaded 21 Aug 2025Source
  • Form 5 (FY 2021-2022)Form 5 2021-22.pdf · uploaded 21 Aug 2025Source
  • Form 1March 2022 Form 1 L_compressed.pdf · uploaded 22 Aug 2025Source
  • Form 2O2 March 22 Form 2 L.pdf · uploaded 22 Aug 2025Source
  • Form 3O2 March 2022 Form 3 L.pdf · uploaded 22 Aug 2025Source
  • Disclosure of Sold and Booked InventoryMarch 2022 Sold Unsold.pdf · uploaded 22 Aug 2025Source
  • Form 1Jun 2022 Form 1s_compressed.pdf · uploaded 22 Aug 2025Source
  • Form 2O2 june 22 Form 2s.pdf · uploaded 22 Aug 2025Source
  • Form 3O2 June 2022 Form 3 s.pdf · uploaded 22 Aug 2025Source
  • Disclosure of Sold and Booked InventoryO2 Jun 2022 Sold Unsold.pdf · uploaded 22 Aug 2025Source
  • Form 1Sep 2022 Form 1 s_compressed (1).pdf · uploaded 22 Aug 2025Source
  • Form 2O2 Sep 22 Form 2 s.pdf · uploaded 22 Aug 2025Source
  • Form 3O2 Sept 2022 Form 3 s.pdf · uploaded 22 Aug 2025Source
  • Disclosure of Sold and Booked InventorySep 2022 Sold Unsold.pdf · uploaded 22 Aug 2025Source
  • Form 2A (FY 2021-2022)Aahan Buildcon21-22.pdf · uploaded 26 Sep 2025Source
  • Form 2A (FY 2022-2023)Aahan Buildcon 22 - 23..pdf · uploaded 26 Sep 2025Source
  • Form 2A (FY 2023-2024)Aahan Buildcon 23 - 24..pdf · uploaded 26 Sep 2025Source
  • Form 2A (FY 2024-2025)Aahan Buildcon 24 - 25..pdf · uploaded 26 Sep 2025Source
  • Form 1Jun 2025 Form 1_compressed.pdf · uploaded 8 Oct 2025Source
  • Form 2O2 june 25 Form 2.pdf · uploaded 8 Oct 2025Source
  • Form 3O2 Buildcon CA Certificate Form 3.pdf · uploaded 8 Oct 2025Source
  • Disclosure of Sold and Booked InventoryAahan Buildcon O2 Sold Undold.pdf · uploaded 8 Oct 2025Source
  • Form 5 (FY 2022-2023)Form 5 2022-23 (3).pdf · uploaded 20 Dec 2025Source
  • Form 5 (FY 2023-2024)Form 5 2023-24.pdf · uploaded 20 Dec 2025Source
  • Form 1Form 1 S_compressed (8).pdf · uploaded 24 Dec 2025Source
  • Form 2Form 2 s.pdf · uploaded 24 Dec 2025Source
  • Form 3Buildcon Form-3 f s.pdf · uploaded 24 Dec 2025Source
  • Disclosure of Sold and Booked InventoryBuildcon Sold Unsold Sept..pdf · uploaded 24 Dec 2025Source
  • Withdrawal Update Form 1Form 1 O2..pdf · uploaded 7 Feb 2026Source
  • Withdrawal Update Form 2Form 2 .pdf · uploaded 7 Feb 2026Source
  • Withdrawal Update Form 3Aahan Buildcon Form-3 RERA (1)_page-0001.pdf · uploaded 7 Feb 2026Source
  • Form 2A (FY 2025-2026)O2 2A 2025-26.pdf · uploaded 20 Feb 2026Source
  • Withdrawal Update Form 1Form 1 O2..pdf · uploaded 4 Mar 2026Source
  • Withdrawal Update Form 2O2 Form 2..pdf · uploaded 4 Mar 2026Source
  • Withdrawal Update Form 3Aahan Buildcon Form-3 RERA (1)_page-0001.pdf · uploaded 4 Mar 2026Source
  • Withdrawal Update Form 1O2 Form 1 Mar26.pdf · uploaded 17 Aug 2026Source
  • Withdrawal Update Form 2O2 Form 2 (1).pdf · uploaded 17 Aug 2026Source
  • Withdrawal Update Form 3O2 Form 3 Mar 26.pdf · uploaded 17 Aug 2026Source
  • Form 5 (FY 2024-2025)O2 Form 5..pdf · uploaded 19 Aug 2026Source
  • Withdrawal Update Form 1O2 Form 1.pdf · uploaded 21 Aug 2026Source
  • Withdrawal Update Form 2O2 Form 2 June 26..pdf · uploaded 21 Aug 2026Source
  • Withdrawal Update Form 3O2 Form 3.pdf · uploaded 21 Aug 2026Source

Technical

  • Documentlayout plan_compressed-1-2.pdf · uploaded 6 Oct 2021Source
  • Documentlayout plan_compressed-3-5-3(1).pdf · uploaded 6 Oct 2021Source
  • Documentlayout plan_compressed-6-7.pdf · uploaded 6 Oct 2021Source
  • DocumentSITE PLAN.pdf · uploaded 11 Oct 2021Source

Technical (Architect)

  • DocumentDONGE_98 merge (3)_compressed (1).pdf · uploaded 8 Mar 2025Source
  • DocumentO2 Form 1.pdf · uploaded 21 Aug 2026Source

Technical (Engineer)

  • DocumentO2 (1) (2).pdf · uploaded 8 Mar 2025Source
  • DocumentO2 Form 2 June 26..pdf · uploaded 21 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPLOT NO 408

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
Bungalow40 units in all
Address
Plot No 408, Chavanwadi Gaothan, DonajePIN 411025
Village
Donaje, Haveli taluka
Designated bank account
43
Developed in phases
Yes

Survey, CTS, gat or plot numbers

PLOT NO 408

Boundaries

North
Plot No 416 And Gaothan Properties
South
Walter D Sauza
East
Zp Road
West
Ghera Shingad Boundary

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking40 units

0 of 40 units booked (0%), as the promoter reported to MahaRERA

Bungalow · 40 units
BuildingTypeCarpet areaUnitsBooked
O2 A WingBungalow78.87 sq m · 849 sq ft20
O2 A WingBungalow80.65 sq m · 868 sq ft20
O2 B WingBungalow75.14 sq m · 809 sq ft40
O2 C WingBungalow67.45 sq m · 726 sq ft20
O2 C WingBungalow68.05 sq m · 732 sq ft20
O2 C WingBungalow73.44 sq m · 791 sq ft40
O2 D WingBungalow75.15 sq m · 809 sq ft80
O2 E WingBungalow71.65 sq m · 771 sq ft20
Show all 11 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
O2 E WingBungalow72.95 sq m · 785 sq ft20
O2 F WingBungalow76.38 sq m · 822 sq ft40
O2 G WingBungalow75.15 sq m · 809 sq ft80

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals9

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectTaw Design Pvt Ltd—
Chartered accountantHarshad Shinde—
Chartered accountantNpsr & Associates—
Chartered accountantPoonam Marathe—
Chartered accountantSachinkumar Kalan—
EngineerPramod Chandrakant Diwakar—
EngineerRohinee Badgujar—
EngineerUdhav Hinge—
OtherShradha Sachin Waman—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology