Deedo IDDP-PUN-N52ACompletion was pushed back 3 years, to Dec 2026; no MahaRERA orders on record; 0% of its units are booked.
Chikhali, Pune 411062 · Property rates in Chikhali · Promoter: Sachin Bapurao Khupse
Completion was pushed back 3 years, to Dec 2026
- This projectRegistered 20 Jun 2022, completion promised 31 Dec 2023, revised to 31 Dec 2026.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Sep 2026 | Shri Corner · 103 | Primary sale | 410 sq ft | View Primary sale, Sep 2026 | |
| Aug 2026 | Shri Corner · 102 | Primary sale | 410 sq ft | View Primary sale, Aug 2026 | |
| Aug 2026 | Unit C-105 | Rental | — | View Rental, Aug 2026 | |
| Aug 2026 | Not on record | Other | 885 sq ft | View Other, Aug 2026 | |
| Jun 2026 | Shri Corner · 501 | Primary sale | 410 sq ft | View Primary sale, Jun 2026 | |
| Apr 2026 | Shri Corner · 403 | Primary sale | 410 sq ft | View Primary sale, Apr 2026 | |
| Mar 2026 | Not on record | Primary sale | 3,170 sq ft | View Primary sale, Mar 2026 | |
| Mar 2026 | Not on record | Primary sale | 344 sq ft | View Primary sale, Mar 2026 | |
| Mar 2026 | Not on record | Primary sale | 169 sq ft | View Primary sale, Mar 2026 | |
| Mar 2026 | Shri Corner | Rental | — | View Rental, Mar 2026 |
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100046194
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100046194 | 20 Jun 2022 | 31 Dec 2023 | 31 Dec 2026 | Sachin Bapurao Khupse | Project page |
Documents294
2 documents held by Deedo, 292 filings listed on MahaRERA's project page
Finance
- PAN Card3) Pancard.pdf · uploaded 9 Jun 2022Source
Legal
Migrated
- 1 PAN Card3) Pancard.pdf · uploaded 9 Jun 2022Source
Show all 294 documentsShow fewer documents
Migrated
- 1 Details of encumbrances9) Encombrancment Decleration.pdf · uploaded 9 Jun 2022Source
- 1 Copy of Layout Approval (in case of layout)4) Layout Plan - 1_compressed.pdf · uploaded 9 Jun 2022Source
- 2 Copy of Layout Approval (in case of layout)5) Layout Plan - 2.PDF · uploaded 9 Jun 2022Source
- 1 Building Plan Approval / NA Order for plotted development13) NA Order.pdf · uploaded 9 Jun 2022Source
- 1 Commencement Certificates / NA Order for plotted development6) Commincment Certificate_compressed.pdf · uploaded 9 Jun 2022Source
- 1 Declaration about Commencement Certificate15) Declaration Of Commincement Certificate.pdf · uploaded 9 Jun 2022Source
- 1 Declaration in FORM B10) Form B.pdf · uploaded 9 Jun 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)12) C A Certificate Form 3.pdf · uploaded 9 Jun 2022Source
- 1 Proforma of Allotment letter11) Agreement Draft.pdf · uploaded 9 Jun 2022Source
- 1 Copy of the legal title report14) Search Report - 2022.pdf · uploaded 10 Jun 2022Source
- 1 CERSAI details16) Title Report - Cersai Report.pdf · uploaded 10 Jun 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Form - 1 - Shri Corner.pdf · uploaded 14 Feb 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Shri Corner (1)F 2.pdf · uploaded 14 Feb 2023Source
- 1 Disclosure of sold/ booked inventoryShri Corner sold.pdf · uploaded 14 Feb 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 24 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)rera update latter Shree Corner.pdf · uploaded 23 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Shri Corner - Form - 5.pdf · uploaded 14 Nov 2024Source
- 2 Disclosure of sold/ booked inventory7) Sold Unsold Inventry.pdf · uploaded 18 Nov 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)8) Form 2 A.pdf · uploaded 18 Nov 2024Source
- 3 Disclosure of sold/ booked inventory7) Sold Unsold Inventry.pdf · uploaded 19 Nov 2024Source
- 18 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sep 2024form 1.pdf · uploaded 30 Nov 2024Source
- 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)June 2024 form 1.pdf · uploaded 30 Nov 2024Source
- 8 Disclosure of sold/ booked inventoryDec 2024 sold.pdf · uploaded 30 Nov 2024Source
- 11 Disclosure of sold/ booked inventorySep 2024 sold unsold.pdf · uploaded 30 Nov 2024Source
- 10 Disclosure of sold/ booked inventoryJune 2024 Sold.pdf · uploaded 30 Nov 2024Source
- 9 Disclosure of sold/ booked inventoryMarch2024 sold.pdf · uploaded 30 Nov 2024Source
- 7 Disclosure of sold/ booked inventorySep 2023 Sold.pdf · uploaded 30 Nov 2024Source
- 6 Disclosure of sold/ booked inventoryJune 2023 sold.pdf · uploaded 30 Nov 2024Source
- 5 Disclosure of sold/ booked inventorySep 2022 sold.pdf · uploaded 30 Nov 2024Source
- 4 Disclosure of sold/ booked inventoryJune 2022 Sold.pdf · uploaded 30 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A Date 06_07_2022.pdf · uploaded 30 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)from 5 2022-2023.pdf · uploaded 30 Nov 2024Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Date 10_04_2023.pdf · uploaded 30 Nov 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)2023-2024 CA.pdf · uploaded 30 Nov 2024Source
- 20 Architect’s Certificate of Percentage of Completion of Work (Form 1)3) Shri Corner - Architect Form - 1 (2).pdf · uploaded 3 Dec 2024Source
- 19 Architect’s Certificate of Percentage of Completion of Work (Form 1)1) Architects Certificate.pdf · uploaded 3 Dec 2024Source
- 12 Disclosure of sold/ booked inventoryDEC 2022 SOLD.pdf · uploaded 3 Dec 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 2023.pdf · uploaded 3 Dec 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 2024.pdf · uploaded 3 Dec 2024Source
- 23 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Date 09_11_2023.pdf · uploaded 5 Dec 2024Source
- 22 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Date 05_08_2023.pdf · uploaded 5 Dec 2024Source
- 21 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Date 05_08_2022.pdf · uploaded 5 Dec 2024Source
- 20 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 june 2022.pdf · uploaded 5 Dec 2024Source
- 19 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 (2).pdf · uploaded 5 Dec 2024Source
- 18 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 - 30-06-2023 (1).pdf · uploaded 5 Dec 2024Source
- 17 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Dec 2024.pdf · uploaded 5 Dec 2024Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June 2024.pdf · uploaded 10 Dec 2024Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sep 2023.pdf · uploaded 10 Dec 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)From 2 Dec 2023.pdf · uploaded 10 Dec 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 2024.pdf · uploaded 10 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Date 09_11_2023.pdf · uploaded 23 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryMarch2024 sold.pdf · uploaded 23 Jan 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 - 30-09-2022_compressed.pdf · uploaded 24 Jan 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 - 30-06-2023.pdf · uploaded 24 Jan 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 - 30-09-2022_compressed.pdf · uploaded 24 Jan 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 -30-09-23.pdf · uploaded 24 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 - 30-09-2022_compressed.pdf · uploaded 24 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 - 30-09-2022_compressed.pdf · uploaded 24 Jan 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 Form 2.pdf · uploaded 24 Jan 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 Form 2.pdf · uploaded 24 Jan 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)10 Form 2.pdf · uploaded 24 Jan 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)8 Form 2.pdf · uploaded 24 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 Form 2.pdf · uploaded 24 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)9 Form 2.pdf · uploaded 24 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Date 31-12-24.pdf · uploaded 24 Jan 2025Source
- 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)10 Architect’s Certificate of Percentage of Completion of Work (Form 1) (6) (1).pdf · uploaded 25 Jan 2025Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (23) (1).pdf · uploaded 25 Jan 2025Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)11 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2) (1).pdf · uploaded 25 Jan 2025Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)9 Architect’s Certificate of Percentage of Completion of Work (Form 1) (7) (1).pdf · uploaded 25 Jan 2025Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)7 Architect’s Certificate of Percentage of Completion of Work (Form 1) (10) (1).pdf · uploaded 25 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)8) Form 1 29-9-2022.pdf · uploaded 25 Jan 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)9) Form 1 29-12-2023.pdf · uploaded 25 Jan 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_ JUNE 2024.pdf · uploaded 25 Jan 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (23) (1).pdf · uploaded 25 Jan 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 Architect’s Certificate of Percentage of Completion of Work (Form 1) (17) (1).pdf · uploaded 25 Jan 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Architect’s Certificate of Percentage of Completion of Work (Form 1) (18) (1).pdf · uploaded 25 Jan 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (16) (1).pdf · uploaded 25 Jan 2025Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (13) (1).pdf · uploaded 25 Jan 2025Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)6 Architect’s Certificate of Percentage of Completion of Work (Form 1) (14) (1).pdf · uploaded 25 Jan 2025Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)8 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (1).pdf · uploaded 25 Jan 2025Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate June 22 (1).pdf · uploaded 25 Jan 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate 30 Sep 2023.pdf · uploaded 25 Jan 2025Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2) (19) (1).pdf · uploaded 25 Jan 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Engineer’s Certificate on Cost Incurred on Project (Form 2) (17) (1).pdf · uploaded 25 Jan 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 Engineer’s Certificate on Cost Incurred on Project (Form 2) (16) (1).pdf · uploaded 25 Jan 2025Source
- 1 Declaration in FORM BP52100046194_FileName_2.pdf · uploaded 9 Feb 2025Source
- 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 2024 (2).pdf · uploaded 18 Feb 2025Source
- 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 2024.pdf · uploaded 18 Feb 2025Source
- 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 - 30-06-2024_compressed.pdf · uploaded 18 Feb 2025Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 - 31-03-2024_compressed.pdf · uploaded 18 Feb 2025Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 Dec 2023.pdf · uploaded 18 Feb 2025Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM _3- 31-03-2023_compressed.pdf · uploaded 18 Feb 2025Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 2024 (2).pdf · uploaded 18 Feb 2025Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 - 31-12-2022.pdf · uploaded 18 Feb 2025Source
- 1 CERSAI detailsCERSAI_Search_Report_200342736287_For_Asset_Based_Search_01_03_2025_14_58_47_569 (1).pdf · uploaded 1 Mar 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A (1).pdf · uploaded 1 Mar 2025Source
- 1 Declaration in FORM BDECLARATION (3).pdf · uploaded 18 Mar 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)7 Architect’s Certificate of Percentage of Completion of Work (Form 1) (4) (1).pdf · uploaded 25 Mar 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (4) (1).pdf · uploaded 25 Mar 2025Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Dec 2024 form 1 (1).pdf · uploaded 25 Mar 2025Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sep Form 1 2024 (1).pdf · uploaded 25 Mar 2025Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 June 2024 (1).pdf · uploaded 25 Mar 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)March 2024 form 1.pdf · uploaded 25 Mar 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (5).pdf · uploaded 25 Mar 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (4).pdf · uploaded 25 Mar 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (3).pdf · uploaded 25 Mar 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (2).pdf · uploaded 25 Mar 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (1).pdf · uploaded 25 Mar 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)March 2023 form 3.pdf · uploaded 25 Mar 2025Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Dec form 3.pdf · uploaded 25 Mar 2025Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sep 2024 form 3 (1).pdf · uploaded 25 Mar 2025Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)June 2024 form 3 (1).pdf · uploaded 25 Mar 2025Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)March 2024 form 3 (1).pdf · uploaded 25 Mar 2025Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM _3 - 31-12-2023_11zon.pdf · uploaded 25 Mar 2025Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sep 2023 form 3 (1).pdf · uploaded 25 Mar 2025Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)June 2023 form 3 (1).pdf · uploaded 25 Mar 2025Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)March 2023 form 3 (1).pdf · uploaded 25 Mar 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Dec 2022 form 3.pdf · uploaded 25 Mar 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM _3 - 31-12-2023_11zon.pdf · uploaded 25 Mar 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sep 2022 form 3 (1).pdf · uploaded 25 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)June 2022 form 3.pdf · uploaded 25 Mar 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)12 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf · uploaded 25 Mar 2025Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)dec2024 form 2.pdf · uploaded 25 Mar 2025Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sep 2024 form 2.pdf · uploaded 25 Mar 2025Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)June 2024 form 2 (1).pdf · uploaded 25 Mar 2025Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)March 2024 eng.pdf · uploaded 25 Mar 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Dec 2023 form 2 (1).pdf · uploaded 25 Mar 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)June 2023 form 2.pdf · uploaded 25 Mar 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)March 2023 form 2.pdf · uploaded 25 Mar 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)15 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf · uploaded 25 Mar 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sep 2022 form 2.pdf · uploaded 25 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)March 22 form 2 (1).pdf · uploaded 25 Mar 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sep 2023 form 2.pdf · uploaded 25 Mar 2025Source
- 16 Disclosure of sold/ booked inventorySOLD UNSOLD CIRCULAR 29 (1)11 (5).pdf · uploaded 25 Mar 2025Source
- 15 Disclosure of sold/ booked inventorySOLD UNSOLD CIRCULAR 29 (1)11 (3).pdf · uploaded 25 Mar 2025Source
- 14 Disclosure of sold/ booked inventorySOLD UNSOLD CIRCULAR 29 (1)11 (2).pdf · uploaded 25 Mar 2025Source
- 13 Disclosure of sold/ booked inventorySOLD UNSOLD CIRCULAR 29 (1)11 (1).pdf · uploaded 25 Mar 2025Source
- 12 Disclosure of sold/ booked inventoryDec 2024 sold.pdf · uploaded 25 Mar 2025Source
- 11 Disclosure of sold/ booked inventorySep sold 2024.pdf · uploaded 25 Mar 2025Source
- 10 Disclosure of sold/ booked inventoryJune 2024 sold.pdf · uploaded 25 Mar 2025Source
- 9 Disclosure of sold/ booked inventoryJune 2024 sold.pdf · uploaded 25 Mar 2025Source
- 8 Disclosure of sold/ booked inventorySep 2022 sold (3).pdf · uploaded 25 Mar 2025Source
- 7 Disclosure of sold/ booked inventorySep 2022 sold (2).pdf · uploaded 25 Mar 2025Source
- 6 Disclosure of sold/ booked inventorySep sold 2023.pdf · uploaded 25 Mar 2025Source
- 5 Disclosure of sold/ booked inventoryJune sold 2023.pdf · uploaded 25 Mar 2025Source
- 4 Disclosure of sold/ booked inventoryMarch 2023 sold.pdf · uploaded 25 Mar 2025Source
- 3 Disclosure of sold/ booked inventorySold Dec 2022.pdf · uploaded 25 Mar 2025Source
- 2 Disclosure of sold/ booked inventorySep 2022 sold.pdf · uploaded 25 Mar 2025Source
- 1 Disclosure of sold/ booked inventorySep 2022 sold (1).pdf · uploaded 25 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 - 31-12-2022.pdf · uploaded 18 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM _3- 31-03-2023.pdf · uploaded 18 Apr 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM_3 - 31-03-2024.pdf · uploaded 18 Apr 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)6 Form - 3 31-12-2024_compressed.pdf · uploaded 18 Apr 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)8 Form -2-31_12_2023.pdf · uploaded 18 Apr 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)10 Form -2-30_06_2024.pdf · uploaded 18 Apr 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 Form -2-31_03_2024.pdf · uploaded 18 Apr 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)9 Form -2-15_09_2023.pdf · uploaded 18 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 Form -2-31_12_2022.pdf · uploaded 18 Apr 2025Source
- 1 Disclosure of sold/ booked inventory1 - Sold Inventroy - 09-07-22.pdf · uploaded 18 Apr 2025Source
- 2 Disclosure of sold/ booked inventory2 - Sold Inventroy - 02-10-22.pdf · uploaded 18 Apr 2025Source
- 3 Disclosure of sold/ booked inventory3 - Sold Inventroy - 05-04-23.pdf · uploaded 18 Apr 2025Source
- 4 Disclosure of sold/ booked inventory4 - Sold Inventroy - 11-07-23.pdf · uploaded 18 Apr 2025Source
- 5 Disclosure of sold/ booked inventory5 - Sold Inventroy - 05-10-23.pdf · uploaded 18 Apr 2025Source
- 6 Disclosure of sold/ booked inventory6- Sold Inventroy - 10-01-24.pdf · uploaded 18 Apr 2025Source
- 7 Disclosure of sold/ booked inventory7 - Sold Inventroy - 12-04-24.pdf · uploaded 18 Apr 2025Source
- 8 Disclosure of sold/ booked inventory8 - Sold Inventroy - 05-07-24.pdf · uploaded 18 Apr 2025Source
- 9 Disclosure of sold/ booked inventory9 - Sold Inventroy - 25-10-24.pdf · uploaded 18 Apr 2025Source
- 10 Disclosure of sold/ booked inventory10 - Sold Inventroy - 31-12-24.pdf · uploaded 18 Apr 2025Source
- 11 Disclosure of sold/ booked inventory11 - Sold Inventroy - 31-03-25.pdf · uploaded 18 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)10 - Form 2A - 2022-2023.pdf · uploaded 18 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2022-2023.pdf · uploaded 18 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)11 - Form 2A - 2023-2024.pdf · uploaded 18 Apr 2025Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Form 1 - 20-01-2025.pdf · uploaded 19 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 05_05_2022.pdf · uploaded 19 Apr 2025Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 07_04_2025.pdf · uploaded 19 Apr 2025Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 Form -1-28_12_2024.pdf · uploaded 19 Apr 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 08_09_2024.pdf · uploaded 19 Apr 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 10_06_2024.pdf · uploaded 19 Apr 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 09_11_2023done.pdf · uploaded 19 Apr 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 05_08_2023done.pdf · uploaded 19 Apr 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Form-1-05_05_2023done .pdf · uploaded 19 Apr 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 06_02_2023done.pdf · uploaded 19 Apr 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 05_08_2022.pdf · uploaded 19 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31 DEC 2024.pdf · uploaded 23 Apr 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31 MARCH 2025.pdf · uploaded 23 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3 31-03-2025 (2).pdf · uploaded 20 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form -2-31_03_2025.pdf · uploaded 20 May 2025Source
- Form 1FORM 1 (1).pdf · uploaded 18 Sep 2026Source
- Form 1FORM 1 (1).pdf · uploaded 18 Sep 2026Source
- Form 1FORM 1 (1).pdf · uploaded 18 Sep 2026Source
- Form 2FORM 2 (1).pdf · uploaded 18 Sep 2026Source
- Form 2FORM 2 (1).pdf · uploaded 18 Sep 2026Source
- Form 2FORM 2 (1).pdf · uploaded 18 Sep 2026Source
- Form 3Rohan Associates Shri Corner CA Form-3 June-2025.pdf · uploaded 18 Sep 2026Source
- Form 3Rohan Associates Shri Corner CA Form-3 Sep-2025.pdf · uploaded 18 Sep 2026Source
- Form 3Rohan Associates Shri Corner CA Form-3 Dec-2025.pdf · uploaded 18 Sep 2026Source
- Disclosure of Sold and Booked InventorySold Inventroy.pdf · uploaded 18 Sep 2026Source
- Disclosure of Sold and Booked InventorySold Inventroy.pdf · uploaded 18 Sep 2026Source
- Disclosure of Sold and Booked InventorySold Inventroy.pdf · uploaded 18 Sep 2026Source
- Form 1FORM 1.pdf · uploaded 21 Sep 2026Source
- Form 2FORM 2.pdf · uploaded 21 Sep 2026Source
- Form 3FORM 3.pdf · uploaded 21 Sep 2026Source
- Disclosure of Sold and Booked InventorySold Inventroy.pdf · uploaded 21 Sep 2026Source
Technical
Technical (Architect)
- Documentrera update latter Shree Corner.pdf · uploaded 23 May 2023Source
- DocumentJune 2024 form 1.pdf · uploaded 30 Nov 2024Source
- DocumentSep 2024form 1.pdf · uploaded 30 Nov 2024Source
- Document1) Architects Certificate.pdf · uploaded 3 Dec 2024Source
- Document3) Shri Corner - Architect Form - 1 (2).pdf · uploaded 3 Dec 2024Source
- DocumentForm 1 Date 05_08_2022.pdf · uploaded 5 Dec 2024Source
- DocumentForm 1 Date 05_08_2023.pdf · uploaded 5 Dec 2024Source
- DocumentForm 1 Date 09_11_2023.pdf · uploaded 5 Dec 2024Source
- DocumentForm 1 Date 09_11_2023.pdf · uploaded 23 Jan 2025Source
- Document8) Form 1 29-9-2022.pdf · uploaded 25 Jan 2025Source
- Document9) Form 1 29-12-2023.pdf · uploaded 25 Jan 2025Source
- DocumentFORM 1_ JUNE 2024.pdf · uploaded 25 Jan 2025Source
- Document1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (23) (1).pdf · uploaded 25 Jan 2025Source
- Document2 Architect’s Certificate of Percentage of Completion of Work (Form 1) (17) (1).pdf · uploaded 25 Jan 2025Source
- Document3 Architect’s Certificate of Percentage of Completion of Work (Form 1) (18) (1).pdf · uploaded 25 Jan 2025Source
- Document4 Architect’s Certificate of Percentage of Completion of Work (Form 1) (16) (1).pdf · uploaded 25 Jan 2025Source
- Document5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (13) (1).pdf · uploaded 25 Jan 2025Source
- Document6 Architect’s Certificate of Percentage of Completion of Work (Form 1) (14) (1).pdf · uploaded 25 Jan 2025Source
- Document7 Architect’s Certificate of Percentage of Completion of Work (Form 1) (10) (1).pdf · uploaded 25 Jan 2025Source
- Document8 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (1).pdf · uploaded 25 Jan 2025Source
- Document9 Architect’s Certificate of Percentage of Completion of Work (Form 1) (7) (1).pdf · uploaded 25 Jan 2025Source
- Document11 Architect’s Certificate of Percentage of Completion of Work (Form 1) (2) (1).pdf · uploaded 25 Jan 2025Source
- Document1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (23) (1).pdf · uploaded 25 Jan 2025Source
- Document10 Architect’s Certificate of Percentage of Completion of Work (Form 1) (6) (1).pdf · uploaded 25 Jan 2025Source
- Document5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (4) (1).pdf · uploaded 25 Mar 2025Source
- Document7 Architect’s Certificate of Percentage of Completion of Work (Form 1) (4) (1).pdf · uploaded 25 Mar 2025Source
- Document1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (1).pdf · uploaded 25 Mar 2025Source
- Document1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (2).pdf · uploaded 25 Mar 2025Source
- Document1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (3).pdf · uploaded 25 Mar 2025Source
- Document1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (4).pdf · uploaded 25 Mar 2025Source
- Document1 Architect’s Certificate of Percentage of Completion of Work (Form 1) (9) (5).pdf · uploaded 25 Mar 2025Source
- DocumentMarch 2024 form 1.pdf · uploaded 25 Mar 2025Source
- Documentform 1 June 2024 (1).pdf · uploaded 25 Mar 2025Source
- DocumentSep Form 1 2024 (1).pdf · uploaded 25 Mar 2025Source
- DocumentDec 2024 form 1 (1).pdf · uploaded 25 Mar 2025Source
- DocumentForm 1 - 05_05_2022.pdf · uploaded 19 Apr 2025Source
- DocumentForm 1 - 05_08_2022.pdf · uploaded 19 Apr 2025Source
- DocumentForm 1 - 06_02_2023done.pdf · uploaded 19 Apr 2025Source
- Document3 Form-1-05_05_2023done .pdf · uploaded 19 Apr 2025Source
- DocumentForm 1 - 05_08_2023done.pdf · uploaded 19 Apr 2025Source
- DocumentForm 1 - 09_11_2023done.pdf · uploaded 19 Apr 2025Source
- DocumentForm 1 - 10_06_2024.pdf · uploaded 19 Apr 2025Source
- DocumentForm 1 - 08_09_2024.pdf · uploaded 19 Apr 2025Source
- Document4 Form -1-28_12_2024.pdf · uploaded 19 Apr 2025Source
- Document1 Form 1 - 20-01-2025.pdf · uploaded 19 Apr 2025Source
- DocumentForm 1 - 07_04_2025.pdf · uploaded 19 Apr 2025Source
- DocumentForm 1 31 DEC 2024.pdf · uploaded 23 Apr 2025Source
- DocumentForm 1 31 MARCH 2025.pdf · uploaded 23 Apr 2025Source
Technical (Engineer)
- DocumentShri Corner (1)F 2.pdf · uploaded 14 Feb 2023Source
- DocumentForm 2 March 2024.pdf · uploaded 10 Dec 2024Source
- DocumentFrom 2 Dec 2023.pdf · uploaded 10 Dec 2024Source
- DocumentForm 2 Sep 2023.pdf · uploaded 10 Dec 2024Source
- DocumentForm 2 June 2024.pdf · uploaded 10 Dec 2024Source
- Document9 Form 2.pdf · uploaded 24 Jan 2025Source
- Document11 Form 2.pdf · uploaded 24 Jan 2025Source
- Document8 Form 2.pdf · uploaded 24 Jan 2025Source
- Document10 Form 2.pdf · uploaded 24 Jan 2025Source
- Document6 Form 2.pdf · uploaded 24 Jan 2025Source
- Document7 Form 2.pdf · uploaded 24 Jan 2025Source
- Document3 Engineer’s Certificate on Cost Incurred on Project (Form 2) (16) (1).pdf · uploaded 25 Jan 2025Source
- Document2 Engineer’s Certificate on Cost Incurred on Project (Form 2) (17) (1).pdf · uploaded 25 Jan 2025Source
- Document1 Engineer’s Certificate on Cost Incurred on Project (Form 2) (19) (1).pdf · uploaded 25 Jan 2025Source
- DocumentMarch 22 form 2 (1).pdf · uploaded 25 Mar 2025Source
- DocumentSep 2022 form 2.pdf · uploaded 25 Mar 2025Source
- Document12 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf · uploaded 25 Mar 2025Source
- Document15 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf · uploaded 25 Mar 2025Source
- DocumentMarch 2023 form 2.pdf · uploaded 25 Mar 2025Source
- DocumentJune 2023 form 2.pdf · uploaded 25 Mar 2025Source
- DocumentSep 2023 form 2.pdf · uploaded 25 Mar 2025Source
- DocumentDec 2023 form 2 (1).pdf · uploaded 25 Mar 2025Source
- DocumentMarch 2024 eng.pdf · uploaded 25 Mar 2025Source
- DocumentJune 2024 form 2 (1).pdf · uploaded 25 Mar 2025Source
- DocumentSep 2024 form 2.pdf · uploaded 25 Mar 2025Source
- Documentdec2024 form 2.pdf · uploaded 25 Mar 2025Source
- Document7 Form -2-31_12_2022.pdf · uploaded 18 Apr 2025Source
- Document9 Form -2-15_09_2023.pdf · uploaded 18 Apr 2025Source
- Document8 Form -2-31_12_2023.pdf · uploaded 18 Apr 2025Source
- Document5 Form -2-31_03_2024.pdf · uploaded 18 Apr 2025Source
- Document10 Form -2-30_06_2024.pdf · uploaded 18 Apr 2025Source
- DocumentForm -2-31_03_2025.pdf · uploaded 20 May 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsGat No.1648
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop or Office11 units in all
- Address
- Gat No.1648, Gat No.1648, Patilnagar Raod, ChikhaliPIN 411062
- Village
- Chikhali, Haveli taluka
- Location
- 18.68657, 73.81207
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Road
- South
- DR Waghamare Property
- East
- malekar and londhe property
- West
- PCMC Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking11 units
0 of 11 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29.95 sq m · 322 sq ft | 3 | 0 |
| 2BHK | 29.98 sq m · 323 sq ft | 3 | 0 |
| Shop or Office | 11.12 sq m · 120 sq ft | 1 | 0 |
| Shop or Office | 12.15 sq m · 131 sq ft | 1 | 0 |
| Shop or Office | 14.14 sq m · 152 sq ft | 1 | 0 |
| Shop or Office | 15.2 sq m · 164 sq ft | 1 | 0 |
| Shop or Office | 16.65 sq m · 179 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Hrushikesh Deore | — |
| Chartered accountant | Sachin Chordiya | — |
| Chartered accountant | Varad S Kalkarni | — |
| Engineer | Abhijit Babasaheb Shinde | — |
Source: MahaRERA project page. Contact details are not shown.
Shri Corner in numbers
Registered deals, summarised
Deedo has 13 registered documents at Shri Corner, from Jan 2026 to Sep 2026: 8 sales, 3 leave and licence agreements, 1 mortgage. The median registered sale works out to about ₹6,500 per sq ft, at a median of ₹26 L a deal; 0% of sales were resales.
- What is the price per sq ft at Shri Corner?
- The median registered sale works out to about ₹6,500 per sq ft, at a median of ₹26 L a deal; 0% of sales were resales.
- How many properties have been sold at Shri Corner?
- 8 sales are registered at Shri Corner.
- Are properties at Shri Corner rented out?
- Yes: 3 leave and licence agreements are registered at Shri Corner, at a median rent of about ₹10,000 a month with a deposit of about ₹25,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Shri Corner by Deedo, last updated with deals registered in Sep 2026.
Latest deal · Primary sale · Sep 2026
₹25–50 L