Deedo IDDP-PUN-WFJQCompletion was pushed back 1 month to Oct 2024, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.
Bhandgaon, Pune 412214 · by Adisai Housing
Buying a flat here?
See every deed registered on it.
Completion was pushed back 1 month to Oct 2024, and that date has passed too
- This projectRegistered 9 Oct 2019, completion promised 29 Sep 2024, revised to 10 Oct 2024, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100022602
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100022602 | 9 Oct 2019 | 29 Sep 2024 | 10 Oct 2024 | Adisai Housing | Project page |
Documents16
2 documents held by Deedo, 14 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card of Adi Sai Housing.pdf · uploaded 28 Sep 2019Source
Legal
Show all 16 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Layout plan_compressed.pdf · uploaded 28 Sep 2019Source
- 1 Building Plan Approval / NA Order for plotted developmentN A Zone Certificate.pdf · uploaded 28 Sep 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement _compressed.pdf · uploaded 28 Sep 2019Source
- 1 Declaration in FORM BPromoter_compressed.pdf · uploaded 28 Sep 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_compressed.pdf · uploaded 28 Sep 2019Source
- 1 Proforma of Allotment letterRERA Agreement to sale - Darft - 27-09-2019- Mayur.pdf · uploaded 28 Sep 2019Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel G NO 510
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK45 units in all
- Address
- G No 510, G No 510, PunePIN 412214
- Village
- Bhandgaon, Daund taluka
- Land area for this project
- 2,200 sq m (23,681 sq ft)
- Permissible built-up area
- 2,090 sq m (22,500 sq ft)
- Sanctioned built-up area
- 2,090 sq m (22,500 sq ft)
- Recreational open space
- 170 sq m (1,830 sq ft)
- Designated bank account
- 119
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
G NO 510
Boundaries
- North
- G No 510
- South
- 60 M W Pune Solapur Road
- East
- G No 511
- West
- G No 509
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking45 units
0 of 45 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.77 sq m · 374 sq ft | 15 | 0 |
| 1BHK | 35.66 sq m · 384 sq ft | 30 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | prajakta jadhav | — |
| Chartered accountant | aayush nathani | — |
| Engineer | harsh constructions | — |
| Other | Dhanjay Desai | — |
Source: MahaRERA project page. Contact details are not shown.