Skip to content
Residential / Group Housing · 2 buildings · 10 unitsRERA P52100025578

Prime Avirat

Deedo IDDP-PUN-4Y5F

MahaRERA shows it completed, after its date was pushed back 1 year and 5 months; no MahaRERA orders on record; 100% of its units are booked.

Bhamburda, Pune 411016 · by Prime Priorities

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 1 yr 5 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked10 of 10 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year and 5 months

  • This projectRegistered 1 Jul 2020, completion promised 30 Dec 2021, revised to 31 May 2023.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100025578
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000255781 Jul 202030 Dec 202131 May 2023Prime PrioritiesProject page
Documents57

3 documents held by Deedo, 54 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardPAN CARD.pdf · uploaded 24 Feb 2020Source

Legal

  • Legal Title reportTitla Report_compressed.pdf · uploaded 17 Dec 2019Source
  • Declaration Form BNew Form B_compressed.pdf · uploaded 16 Jun 2020Source
  • Declaration Form BForm -B Prime Avirat.pdf · uploaded 22 Jul 2023Source

Migrated

  • 1 Copy of the legal title reportTitla Report_compressed.pdf · uploaded 17 Dec 2019Source
Show all 57 documentsShow fewer documents

Migrated

  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 25 Dec 2019Source
  • 1 PAN CardPAN CARD.pdf · uploaded 24 Feb 2020Source
  • 1 Copy of Layout Approval (in case of layout)Avirat Approved Plan.pdf · uploaded 24 Feb 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentAvirat Approved Plan.pdf · uploaded 24 Feb 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencment Certificate_compressed.pdf · uploaded 24 Feb 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_compressed.pdf · uploaded 26 Feb 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineering Certificate_compressed.pdf · uploaded 26 Feb 2020Source
  • 1 Details of encumbrancesEncumbrance.pdf · uploaded 29 Feb 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Pages 1-2.pdf · uploaded 12 Mar 2020Source
  • 1 Declaration in FORM BNew Form B_compressed.pdf · uploaded 16 Jun 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2 A- ENGINEER.pdf · uploaded 16 Aug 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 23 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)form 5 (17-18).pdf · uploaded 23 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)form 5 (2018-19).pdf · uploaded 23 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 (19-20).pdf · uploaded 23 Aug 2021Source
  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf · uploaded 22 Sep 2021Source
  • 1 Disclosure of sold/ booked inventorySold unsold 1.pdf · uploaded 23 Sep 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2a Engineer Certificate 20-21.pdf · uploaded 25 Sep 2021Source
  • 2 Disclosure of sold/ booked inventorySold Inventory Final.pdf · uploaded 7 Oct 2021Source
  • 3 Disclosure of sold/ booked inventorySold Inventory Final.pdf · uploaded 11 Oct 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFINAL-Completion original Bhogawata Patra.pdf · uploaded 2 Mar 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 23 Mar 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2(a)_compressed.pdf · uploaded 24 Mar 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 (2020-21).pdf · uploaded 24 Mar 2022Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 26 Mar 2022Source
  • 4 Disclosure of sold/ booked inventoryRecent Sold Unsold Inventory.pdf · uploaded 26 Mar 2022Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentAvirat Bhogawata Patr Final completion.PDF · uploaded 20 Oct 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 (2021-22).pdf · uploaded 9 Dec 2022Source
  • 5 Disclosure of sold/ booked inventoryCIRCULAR 29.pdf · uploaded 24 Apr 2023View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3( JULY 21 TO MAR 22).pdf · uploaded 19 Jul 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FOMR 3 (APR 22 TO OCT 22) (1).pdf · uploaded 19 Jul 2023Source
  • 2 Declaration in FORM BForm -B Prime Avirat.pdf · uploaded 22 Jul 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 22.pdf · uploaded 22 Jul 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 October 22.pdf · uploaded 22 Jul 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)V A Dudhedia- 19-20.pdf · uploaded 22 Jul 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)V A Dudhedia -18-19.pdf · uploaded 22 Jul 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)V A Dudhedia 17-18.pdf · uploaded 22 Jul 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A 22.pdf · uploaded 22 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A 22.pdf · uploaded 22 Jul 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)F 5 17-18.pdf · uploaded 22 Jul 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)F 5 18-19.pdf · uploaded 22 Jul 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)V A Dudhedia- 19-20.pdf · uploaded 22 Jul 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)F5 20-21.pdf · uploaded 22 Jul 2023Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)F5 21-22.pdf · uploaded 22 Jul 2023Source
  • 10 Architect’s Certificate on Completion of Project (Form 4)Final Form 4.pdf · uploaded 26 Aug 2023Source

Technical

  • DocumentAvirat Approved Plan.pdf · uploaded 24 Feb 2020Source
  • DocumentAvirat Approved Plan.pdf · uploaded 24 Feb 2020Source

Technical (Architect)

  • DocumentArchitect Certificate_compressed.pdf · uploaded 26 Feb 2020Source

Technical (Engineer)

  • DocumentForm 2 October 22.pdf · uploaded 22 Jul 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 1120 498 2 Shivajinagar Bhamburda, 1120/498/2 Shivajinagar (Bhamburda)

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
3BHK10 units in all
Address
1120 498 2 Shivajinagar Bhamburda, LAKAKI ROAD, BHAMBURDAPIN 411016
Village
Pune (M Corp.), Pune City taluka
Land area for this project
516 sq m (5,550 sq ft)
Permissible built-up area
880 sq m (9,467 sq ft)
Sanctioned built-up area
476 sq m (5,128 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

1120 498 2 Shivajinagar Bhamburda1120/498/2 Shivajinagar (Bhamburda)

Land as published on MahaRERA's project page

1120 498 2 Shivajinagar Bhamburda

Boundaries

North
Plot No 1
South
Plot No 3
East
Purshottam Apartment
West
40 Ft Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking10 units

10 of 10 units booked (100%), as the promoter reported to MahaRERA

3BHK · 10 units
TypeCarpet areaUnitsBooked
3BHK86.89 sq m · 935 sq ft55
3BHK90.36 sq m · 973 sq ft55

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSiddharth Harishchandrakar—
Chartered accountantKshama S Gundi—
EngineerSiddharth Bhandari—
OtherB N Chaudhary—
OtherMr Amar Chakradev—
OtherMr Mukund Saraf—
OtherMr Parag Chopada—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology