RERA projects in Baramati (M Cl)
191 projects under 193 MahaRERA registrations, registered 2017–2026. 11% have a completion date extended beyond the one promised.
Locality
191RERA projects
193Registrationssome projects hold several
70Completion still due123 past their completion date
20 monthsMedian extension beyond promised date11% of registrations extended
2Regulatory caseson 2 projects
19Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 49 |
| 2018 | 13 |
| 2019 | 14 |
| 2020 | 9 |
| 2021 | 14 |
| 2022 | 11 |
| 2023 | 36 |
| 2024 | 20 |
| 2025 | 19 |
| 2026 | 8 |
Projects in Baramati (M Cl)
191 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Seven Star IconSamarth Icon | P52100079042 | 31 Jan 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| Adarsh ResidencyShivshree Developers | P52100078817 | 13 Jan 2025 | 30 Oct 2026 | — | Not yet due | 0 |
| Sharada BaugMandar Shrikant Sikachi | P52100078344 | 6 Dec 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Raj EliteRiddhi Buildcon | P52100077801 | 7 Nov 2024 | 31 Mar 2029 | — | Not yet due | 0 |
| Durga City MallKhatri Khatmode Buildcon | P52100077555 | 10 Oct 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Chirag Elite Wing BP M Developers | P52100077071 | 23 Jul 2024 | 31 May 2029 | — | Not yet due | 0 |
| Khatri Pawar EnclaveKhatri Pawar Builders & Developers | P52100076703 | 21 Jun 2024 | 31 Dec 2034 | — | Not yet due | 0 |
| Utkarsh ComplexShree Swami Samarth Developers | P52100076620 | 18 Jun 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Om HeightsChandrakant Baban Sawant | P52100066567 | 11 Jun 2024 | 31 Dec 2030 | — | Not yet due | 0 |
| Shree Ram IconTakawale Satav Associates | P52100066522 | 11 Jun 2024 | 31 Dec 2029 | — | Not yet due | 0 |
| Tanai HeightsSurekha Vishnu Kumbhar | P52100056437 | 31 May 2024 | 25 Nov 2026 | — | Not yet due | 0 |
| Ghanwat Jachak IconV Nirmiti Icon | P52100056219 | 22 May 2024 | 31 Dec 2030 | — | Not yet due | 0 |
| G G CapitalGg Builders And Developers | P52100055383 | 22 Mar 2024 | 31 Aug 2026 | — | Promised date passed | 0 |
| Nana Nani Park A WingMalgunde Balgude Associates | P52100055462 | 22 Mar 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| RajmalharSudit Enterprises | P52100055469 | 22 Mar 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Godavari RoyalGodavari Group | P52100055268 | 14 Mar 2024 | 2 Aug 2025 | — | Promised date passed | 0 |
| Indraprastha EnclaveVijay Hanumantrao Dhawan | P52100055130 | 4 Mar 2024 | 31 Oct 2029 | 31 Oct 2032 | Extended 36 mo | 0 |
| Raj Yuthika ApartmentRajmati Heights | P52100055150 | 4 Mar 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Shriya AvenueKanhopatra Hanumant Kate | P52100054663 | 2 Feb 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Jachak Ghanwat PrideV Nirmiti Icon | P52100054505 | 25 Jan 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Shree Swarajya ParkShreegruha Nirman Infra Projects LLP | P52100054365 | 17 Jan 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Babalal Kakade Commercial ComplexJadhav Construction | P52100054166 | 1 Jan 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Avdhoot PlazaVighnaharta Group | P52100054023 | 19 Dec 2023 | 30 Dec 2027 | — | Not yet due | 0 |
| Vedant AvenueVedant Buildcon | P52100054028 | 19 Dec 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Dyaneshwari ParadiseSandip Laxman Shende | P52100053938 | 11 Dec 2023 | 20 Feb 2027 | — | Not yet due | 0 |
Other localities in Baramati
- Jalochi124 projects
- Rui25 projects
- Tandulwadi20 projects
- Baramati Rural12 projects
- Malegaon Bk7 projects
- Vanjarwadi3 projects
- Karanjepul2 projects
- Malegaon Kh.2 projects
- Morgaon2 projects
- Gunwadi1 project
Most active promoters
By projects registered here, as named on MahaRERA.
- Mukti Township Development & Construction Co. Pvt. Ltd.4 projects
- Sanjay Walchand Sanghavi4 projects
- Shri Developers3 projects
- vedant developers3 projects
- Akruti Buildcon2 projects
- Aziz Mehboob Bagwan2 projects
- Dattatray Hanumant Borade2 projects
- Deepak Bhausaheb Kate2 projects
- Jay Nanaso Patil2 projects
- Naman Developers2 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology