Residential / Group Housing · 2 buildings · 51 unitsRERA P99000031239

Pearl And Ruby

Deedo IDDP-PAL-D8F3

Completion was pushed back 4 months to Jul 2026, and that date has passed too; no MahaRERA orders on record; 61% of its units are booked.

Waliv, Palghar 401208 · by Skyline Realtors

Delivery8 mo latePromised Mar 2026 · revised Jul 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales61% booked31 of 51 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months to Jul 2026, and that date has passed too

  • This projectRegistered 11 Oct 2021, completion promised 31 Mar 2026, revised to 31 Jul 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000031239
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900003123911 Oct 202131 Mar 202631 Jul 2026Skyline RealtorsProject page
Documents96

2 documents held by Deedo, 94 filings listed on MahaRERA's project page

Registration certificate

Other

  • OtherDate not statedView

Finance

  • PAN Card0 PAN Skyline Realtors.pdf · uploaded 4 Sep 2021Source

Legal

  • Declaration Form BForm B Declaration.pdf · uploaded 10 Sep 2021Source
  • Legal Title report1 Title RERA.pdf · uploaded 1 Oct 2021Source
  • Legal Title report2 Flow of title.pdf · uploaded 1 Oct 2021Source
  • Legal Title report3 Title Clearence Certificate_1.pdf · uploaded 1 Oct 2021Source
  • Legal Title report3 Title Clearence Certificate_2.pdf · uploaded 1 Oct 2021Source
Show all 96 documentsShow fewer documents

Migrated

  • 1 PAN Card0 PAN Skyline Realtors.pdf · uploaded 4 Sep 2021Source
  • 1 Details of encumbrancesGen DECLARATION.pdf · uploaded 4 Sep 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentSkyline Realtors CCOPT.pdf · uploaded 4 Sep 2021Source
  • 1 Declaration about Commencement CertificateForm D_CC DECLARATION.pdf · uploaded 4 Sep 2021Source
  • 1 Declaration in FORM BForm B Declaration.pdf · uploaded 10 Sep 2021Source
  • 1 Proforma of Allotment letterAllotment.pdf · uploaded 10 Sep 2021Source
  • 2 Proforma of Allotment letterModel_Sale_Agreement_As_Per_RERA.pdf · uploaded 10 Sep 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 12 Sep 2021Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT1.pdf · uploaded 19 Sep 2021Source
  • 2 Copy of Layout Approval (in case of layout)LAYOUT2.pdf · uploaded 19 Sep 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentLAYOUT1.pdf · uploaded 19 Sep 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentLAYOUT2.pdf · uploaded 19 Sep 2021Source
  • 1 Copy of the legal title report1 Title RERA.pdf · uploaded 1 Oct 2021Source
  • 2 Copy of the legal title report2 Flow of title.pdf · uploaded 1 Oct 2021Source
  • 3 Copy of the legal title report3 Title Clearence Certificate_1.pdf · uploaded 1 Oct 2021Source
  • 4 Copy of the legal title report3 Title Clearence Certificate_2.pdf · uploaded 1 Oct 2021Source
  • 3 Proforma of Allotment letterPearl Sale Agreement of Skyline Realtors.pdf · uploaded 11 Mar 2022Source
  • 4 Proforma of Allotment letterRuby Sale Agreement of Skyline Realtors.pdf · uploaded 11 Mar 2022Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD_PEARL 310322 OPT.pdf · uploaded 17 May 2022Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD_RUBY 310322 OPT.pdf · uploaded 17 May 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate dated.pdf · uploaded 20 Aug 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate RERA FORM 2 COMPR.pdf · uploaded 20 Aug 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED - Copy_1.pdf · uploaded 20 Aug 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED - Copy_2.pdf · uploaded 20 Aug 2022Source
  • 3 Disclosure of sold/ booked inventorySOLD UNSOLD QE 30 JUNE 22 PEARL.pdf · uploaded 27 Aug 2022Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD QE 30JUNE22 RUBY.pdf · uploaded 27 Aug 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate Form 1CO.pdf · uploaded 20 Oct 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate form 2CO.pdf · uploaded 20 Oct 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED CO.pdf · uploaded 20 Oct 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5_2022_SKYLINE_opt.pdf · uploaded 17 Jan 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_MAR 23.pdf · uploaded 1 May 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA.pdf · uploaded 1 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A RERA.pdf · uploaded 1 May 2023Source
  • 5 Disclosure of sold/ booked inventorySOLD UNSOLD_PEARL_310323.pdf · uploaded 1 May 2023Source
  • 6 Disclosure of sold/ booked inventorySOLD UNSOLD_RUBY_310323.pdf · uploaded 1 May 2023View
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_SKYLINE_Q4 2023 opt.pdf · uploaded 1 May 2023Source
  • 1 Other – TechnicalForm 2A RERA.pdf · uploaded 1 May 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERT.pdf · uploaded 22 Aug 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA Certificate.pdf · uploaded 22 Aug 2023Source
  • 3 Copy of Layout Approval (in case of layout)Pearl Revised OPT.pdf · uploaded 25 Aug 2023Source
  • 4 Copy of Layout Approval (in case of layout)Ruby Revised Plan OPT.pdf · uploaded 25 Aug 2023Source
  • 5 Copy of Layout Approval (in case of layout)Pearl Revised OPT.pdf · uploaded 25 Aug 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentPearl Revised OPT.pdf · uploaded 25 Aug 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentRuby Revised Plan OPT.pdf · uploaded 25 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised CC 2023 OPT.pdf · uploaded 2 Sep 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCH CERT.pdf · uploaded 9 Nov 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENG CERT.pdf · uploaded 9 Nov 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 FINAL OPT.pdf · uploaded 9 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5_2023 SIGNED PEARL RUBY.pdf · uploaded 9 Dec 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate dated FORM 1.pdf · uploaded 18 Jan 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA Certificate FORM 2_compressed.pdf · uploaded 18 Jan 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED - PEARL AND RUBY (Q3)_compressed.pdf · uploaded 20 Jan 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 BLDG 1 2.pdf · uploaded 14 Aug 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 PEARL RUBY Q1 2024 - converted.pdf · uploaded 14 Aug 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA Certificate 10 05 2024 - converted.pdf · uploaded 14 Aug 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PEARL RUBY Q1 2024 - converted.pdf · uploaded 14 Aug 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3_Pearl and Ruby_Q4 signed - converted.pdf · uploaded 14 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 PEARL RUBY Q2 2024.pdf · uploaded 20 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_PEARL RUBY_JUNE 2024 SIGNED - converted.pdf · uploaded 20 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3-PEARL RUBY-Q2 SIGNED.pdf · uploaded 20 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 PEARL RUBY.pdf · uploaded 14 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_Q3 DEC 24_PEARL RUBY_compressed.pdf · uploaded 1 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_Pearl Ruby_Q3 Dec 2024-SIGNED COMPRESSED.pdf · uploaded 1 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PEARL RUBY Q2 2024.pdf · uploaded 1 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_Q3 DEC 24_PEARL RUBY_compressed.pdf · uploaded 1 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_Q4 MAR 25_PEARL RUBY - converted.pdf · uploaded 9 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Pearl Ruby - converted.pdf · uploaded 9 May 2025Source
  • 1 Other – Technical1 OC of Pearl and Ruby combined.pdf · uploaded 18 May 2025Source
  • Form 5 (FY 2024-2025)FORM 5-PEARL AND RUBY_FY 2024-2025_SIGNED.pdf · uploaded 14 Mar 2026Source

Technical

  • DocumentLAYOUT1.pdf · uploaded 19 Sep 2021Source
  • DocumentLAYOUT2.pdf · uploaded 19 Sep 2021Source
  • DocumentLAYOUT1.pdf · uploaded 19 Sep 2021Source
  • DocumentLAYOUT2.pdf · uploaded 19 Sep 2021Source
  • Other – TechnicalForm 2A RERA.pdf · uploaded 1 May 2023Source
  • DocumentPearl Revised OPT.pdf · uploaded 25 Aug 2023Source
  • DocumentRuby Revised Plan OPT.pdf · uploaded 25 Aug 2023Source
  • DocumentPearl Revised OPT.pdf · uploaded 25 Aug 2023Source
  • DocumentPearl Revised OPT.pdf · uploaded 25 Aug 2023Source
  • DocumentRuby Revised Plan OPT.pdf · uploaded 25 Aug 2023Source
  • Other – Technical1 OC of Pearl and Ruby combined.pdf · uploaded 18 May 2025Source

Technical (Architect)

  • DocumentFORM 1 PEARL RUBY Q1 2024 - converted.pdf · uploaded 14 Aug 2024Source
  • DocumentFORM 1 PEARL RUBY Q2 2024.pdf · uploaded 20 Dec 2024Source
  • DocumentFORM 1_Q3 DEC 24_PEARL RUBY_compressed.pdf · uploaded 1 Feb 2025Source
  • DocumentFORM 1_Q4 MAR 25_PEARL RUBY - converted.pdf · uploaded 9 May 2025Source

Technical (Engineer)

  • DocumentFORM 2 PEARL RUBY Q1 2024 - converted.pdf · uploaded 14 Aug 2024Source
  • DocumentFORM 2 PEARL RUBY Q2 2024.pdf · uploaded 1 Feb 2025Source
  • DocumentFORM 2_Q3 DEC 24_PEARL RUBY_compressed.pdf · uploaded 1 Feb 2025Source
  • DocumentForm 2 Pearl Ruby - converted.pdf · uploaded 9 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Address
S No 25, Hno 2/1, Waliv, WalivPIN 401208
Land area for this project
3,220 sq m (34,660 sq ft)
Permissible built-up area
5,322 sq m (57,286 sq ft)
Sanctioned built-up area
5,322 sq m (57,286 sq ft)
Designated bank account
19
Developed in phases
Yes

Land as published on MahaRERA's project page

S NO 25, HNO 2/1

Boundaries

North
Sno25 Hno1
South
Sno 15
East
Sno 25 Hno 2-2
West
Sno25 Hno 1

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectHimesh Gupta & Associates—
Chartered accountantHaresh Mehta & Associates—
Chartered accountantStr And Associates—
EngineerSeemu Consultancy—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology