Merkez
Deedo IDDP-PAL-0K7CCompletion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 52% of its units are booked.
Waliv, Palghar 401208 · by Sagar Developer
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2030
- This projectRegistered 10 Oct 2023, completion promised 31 Dec 2029, revised to 30 Apr 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000052992
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000052992 | 10 Oct 2023 | 31 Dec 2029 | 30 Apr 2030 | Sagar Developer | Project page |
Documents70
1 document held by Deedo, 69 filings listed on MahaRERA's project page
Finance
- PAN Cardoffc pan.pdf · uploaded 18 Aug 2023Source
Legal
Migrated
- 1 PAN Cardoffc pan.pdf · uploaded 18 Aug 2023Source
- 1 a Details of encumbrances concerned to FinanceENCUMBRANCE FINANCE.pdf · uploaded 18 Aug 2023Source
- 2 a Details of encumbrances concerned to FinanceENCUMBRANCE LEGAL.pdf · uploaded 18 Aug 2023Source
- 1 b Details of encumbrances concerned to LegalENCUMBRANCE FINANCE.pdf · uploaded 18 Aug 2023Source
Show all 70 documentsShow fewer documents
Migrated
- 2 b Details of encumbrances concerned to LegalENCUMBRANCE LEGAL.pdf · uploaded 18 Aug 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentcc revised.pdf · uploaded 18 Aug 2023Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 18 Aug 2023Source
- 1 Declaration in FORM BAFFIDAVIT form B .pdf · uploaded 18 Aug 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Latest Architect Engineer Certificate_Merkez_Bldng_1 (14-08-2023).pdf · uploaded 18 Aug 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Latest Engineer Certificate_Merkez_Bldng_ (14-08-2023).pdf · uploaded 18 Aug 2023Source
- 1 CERSAI detailscombo cersai report.pdf · uploaded 18 Aug 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAZBAN YUSUF QURESHI SELF DECLARATION.pdf · uploaded 18 Aug 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsMOHAMMED YUSUF SELF DECLARATION.pdf · uploaded 18 Aug 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsRAEES YUSUF QURESHI SELF DECLARATION.pdf · uploaded 18 Aug 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsSAAHIL YUSUF QURESHI SELF DECLARATION.pdf · uploaded 18 Aug 2023Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsSHADAB YUSUF QURESHI SELF DECLARATION.pdf · uploaded 18 Aug 2023Source
- 6 Disclosure of Interest in Other Real Estate OrganizationsZEESHAN YUSUF QURESHI SELF DECLARATION.pdf · uploaded 18 Aug 2023Source
- 1 Proforma of Allotment letterallotement Letter Draft.pdf · uploaded 18 Aug 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK DECLARATION.pdf · uploaded 18 Aug 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation Letter Of Allotment.pdf · uploaded 18 Aug 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Letter Of Agreement.pdf · uploaded 18 Aug 2023Source
- 1 Copy of Layout Approval (in case of layout)layour plan.pdf · uploaded 29 Aug 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentbuilding Plan.pdf · uploaded 29 Aug 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentGround Floor Plan.pdf · uploaded 29 Aug 2023Source
- 3 Building Plan Approval / NA Order for plotted development8th_13th_18 to 22.pdf · uploaded 29 Aug 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)revised CA Certificate on Project Cost Fund withdrawal.pdf · uploaded 6 Sep 2023Source
- 1 Proforma of Agreement for salerevised RERA FLAT 992023.pdf · uploaded 10 Sep 2023Source
- 1 Copy of the legal title reportDOC235COMP.pdf · uploaded 11 Sep 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)VP-4289 FORM-1 29-06-2024_compressed.pdf · uploaded 27 Dec 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)VP-4289 FORM-2 29-06-2024_compressed.pdf · uploaded 27 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)arch encon 3006 merkez.pdf · uploaded 13 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)arch 3009 merkez.pdf · uploaded 13 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)eng 3006 merkez.pdf · uploaded 13 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)eng enco 3009 merkez.pdf · uploaded 13 Feb 2025Source
- 1 Disclosure of sold/ booked inventorysold unsold 3112 merkez_compressed.pdf · uploaded 13 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Merkez Form 1 Dec 2024_0001.pdf · uploaded 13 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Merkez Form 2 Dec 2024_0001_0001.pdf · uploaded 13 Mar 2025Source
- Withdrawal Update Form 1Form 1 Q1.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 1Form 1 Q2.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 1Form 1 Q3.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 1Form 1 Q4.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 2Form 2 Q1.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 2Form 2 Q2.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 2Form 2 Q3.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 2Form 2 Q4.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 3MERKEZ CA CERTIFICATE.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 3MERKEZ CA CERTIFICATE.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 3MERKEZ CA CERTIFICATE.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 3MERKEZ CA CERTIFICATE.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2form 2.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3MERKEZ CA CERTIFICATE.pdf · uploaded 20 Jul 2026Source
Technical
Technical (Architect)
- DocumentVP-4289 FORM-1 29-06-2024_compressed.pdf · uploaded 27 Dec 2024Source
- Documentarch encon 3006 merkez.pdf · uploaded 13 Feb 2025Source
- Documentarch 3009 merkez.pdf · uploaded 13 Feb 2025Source
- DocumentMerkez Form 1 Dec 2024_0001.pdf · uploaded 13 Mar 2025Source
- DocumentForm 1.pdf · uploaded 20 Jul 2026Source
Technical (Engineer)
- DocumentVP-4289 FORM-2 29-06-2024_compressed.pdf · uploaded 27 Dec 2024Source
- Documenteng 3006 merkez.pdf · uploaded 13 Feb 2025Source
- Documenteng enco 3009 merkez.pdf · uploaded 13 Feb 2025Source
- DocumentMerkez Form 2 Dec 2024_0001_0001.pdf · uploaded 13 Mar 2025Source
- Documentform 2.pdf · uploaded 20 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 10, 11 S NO 50 H NO 3 (OLD) S NO H NO 47/5/7A B/48 6/10/11/50/3/ (NEW)
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK324 units in all
- Address
- S No 47 H No 5, 7a, S No 48 H No 6, 10, 11 S No 50 H No 3 (Old) S No H No 47/5/7a B/48 6/10/11/50/3/ (New), Waliv, WalivPIN 401208
- Village
- Vasai-Virar City (M Corp), Vasai taluka
- Location
- 19.41839, 72.86343
- Land area for this project
- 3,433 sq m (36,952 sq ft)
- Permissible built-up area
- 21,916 sq m (2,35,905 sq ft)
- Sanctioned built-up area
- 21,916 sq m (2,35,905 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO 47 H NO 5, 7A, S NO 48 H NO 6, 10,11 S NO 50 H NO 3 (OLD) S NO H NO 47/5/7A B/48 6/10/11/50/3/ (NEW)
Boundaries
- North
- Existing Structure
- South
- D P Road
- East
- D P Road
- West
- Existing Structure
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking324 units
169 of 324 units booked (52%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 38 sq m · 409 sq ft | 22 | 11 |
| 1BHK | 40.69 sq m · 438 sq ft | 22 | 6 |
| 1BHK | 40.78 sq m · 439 sq ft | 18 | 9 |
| 1BHK | 41.62 sq m · 448 sq ft | 70 | 41 |
| 1BHK | 43.11 sq m · 464 sq ft | 22 | 11 |
| 1BHK | 43.56 sq m · 469 sq ft | 4 | 1 |
| 1BHK | 44.39 sq m · 478 sq ft | 4 | 1 |
| 1BHK | 44.41 sq m · 478 sq ft | 4 | 1 |
Show all 23 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 44.87 sq m · 483 sq ft | 4 | 0 |
| 1BHK | 62.23 sq m · 670 sq ft | 2 | 0 |
| 1BHK | 62.34 sq m · 671 sq ft | 1 | 1 |
| 2BHK | 54.16 sq m · 583 sq ft | 18 | 12 |
| 2BHK | 54.19 sq m · 583 sq ft | 4 | 0 |
| 2BHK | 55.46 sq m · 597 sq ft | 18 | 14 |
| 2BHK | 55.56 sq m · 598 sq ft | 18 | 13 |
| 2BHK | 62.14 sq m · 669 sq ft | 4 | 0 |
| 2BHK | 62.23 sq m · 670 sq ft | 2 | 0 |
| 2BHK | 62.34 sq m · 671 sq ft | 17 | 9 |
| 2BHK | 62.89 sq m · 677 sq ft | 18 | 10 |
| 2BHK | 65.82 sq m · 708 sq ft | 4 | 3 |
| 2BHK | 66.41 sq m · 715 sq ft | 4 | 1 |
| 2BHK | 67.54 sq m · 727 sq ft | 22 | 13 |
| 3BHK | 87.42 sq m · 941 sq ft | 22 | 12 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Encon | — |
| Chartered accountant | S B Jain And Associates | — |
| Engineer | Sanjay S Narang | — |
| Other | Khallil Shaikh | — |
| Other | Mohammad Mahabub Maqasud | — |
Source: MahaRERA project page. Contact details are not shown.