Skip to content
Residential / Group Housing · 1 building · 109 unitsRERA P99000055379

Haridham

Deedo IDDP-PAL-24V0

Completion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 72% of its units are booked.

Virar, Palghar 401303 · by V M Housing

DeliveryExtended 4 moPromised Dec 2027 · now due Apr 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales72% booked78 of 109 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2028

  • This projectRegistered 22 Mar 2024, completion promised 31 Dec 2027, revised to 30 Apr 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000055379
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900005537922 Mar 202431 Dec 202730 Apr 2028V M HousingProject page
Documents104

1 document held by Deedo, 103 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPANCARD (1).pdf · uploaded 13 Oct 2023Source

Legal

  • Declaration Form BFORM-B V M HOUSING.pdf · uploaded 18 Nov 2023Source
  • Legal Title reportHaridham title search new_compressed.pdf · uploaded 30 Nov 2023Source

Migrated

  • 1 PAN CardPANCARD (1).pdf · uploaded 13 Oct 2023Source
  • 1 Copy of Layout Approval (in case of layout)SENCTION PLAN HARIDHAM_compressed.pdf · uploaded 13 Oct 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentSENCTION GROUND FLOOR HARIDHAM_compressed.pdf · uploaded 13 Oct 2023Source
  • 1 a Details of encumbrances concerned to Financeencumbrance legal.pdf · uploaded 19 Oct 2023Source
Show all 104 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to Legalencumbrance legal.pdf · uploaded 19 Oct 2023Source
  • 1 Declaration about Commencement CertificateCC declaration (1).pdf · uploaded 19 Oct 2023Source
  • 1 CERSAI detailscersai declaration (1).pdf · uploaded 19 Oct 2023Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsother real estate.pdf · uploaded 19 Oct 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameseparate bank account (1).pdf · uploaded 19 Oct 2023Source
  • 1 Deviation Report with respect to Allotment letterdeviation allotment (1).pdf · uploaded 19 Oct 2023Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation agreement (1).pdf · uploaded 19 Oct 2023Source
  • 1 Declaration in FORM BFORM-B V M HOUSING.pdf · uploaded 18 Nov 2023Source
  • 1 Copy of the legal title reportHaridham title search new_compressed.pdf · uploaded 30 Nov 2023Source
  • 1 Proforma of Allotment letterHARIDHAM ALLOTMENT .pdf · uploaded 30 Nov 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentHARIDHAM SHEET 5_compressed.pdf · uploaded 19 Dec 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentSENCTION TIPICAL PLAN HARIDHAM_compressed.pdf · uploaded 19 Dec 2023Source
  • 4 Building Plan Approval / NA Order for plotted developmentSENCTION REFUGE PLAN HARIDHAM_compressed (1)_compressed_compressed_compressed.pdf · uploaded 19 Dec 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect letter(2).pdf · uploaded 25 Jan 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer letter(2).pdf · uploaded 25 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA letter.pdf · uploaded 25 Jan 2024Source
  • 1 Other – Technical561-1.pdf · uploaded 25 Jan 2024Source
  • 2 Other – Technical561-2.pdf · uploaded 25 Jan 2024Source
  • 3 Other – Technical561-3.pdf · uploaded 25 Jan 2024Source
  • 4 Other – Technical561-4.pdf · uploaded 25 Jan 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT FOR SALE-HARIDHAM-04-08-23(1).pdf · uploaded 5 Feb 2024Source
  • 1 Commencement Certificates / NA Order for plotted development5 Other – Technical(1).pdf · uploaded 19 Mar 2024Source
  • 5 Other – Technicalcc verification.pdf · uploaded 19 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)vm april to june architech.pdf · uploaded 16 Dec 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 JULY TO SEP.pdf · uploaded 16 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)vm april to june engineer.pdf · uploaded 16 Dec 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 JULY TO SEP.pdf · uploaded 16 Dec 2024Source
  • 2 Disclosure of sold/ booked inventoryVM UNSOLD JULY TO SEP24.pdf · uploaded 16 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)VM ENGINEERS REPORT 23-24_0001.pdf · uploaded 16 Dec 2024Source
  • 1 CERSAI detailsMCHI CERTIFICATE.pdf · uploaded 20 Dec 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameV M HARIDHAM UNDERTAKING 02-12.pdf · uploaded 20 Dec 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)format B.pdf · uploaded 20 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)haridham form 3 apr to june 2024.pdf · uploaded 23 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)haridham form 3july to sep 2024.pdf · uploaded 23 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 HARIDHAM.pdf · uploaded 1 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)V M FORM 2.pdf · uploaded 1 Feb 2025Source
  • 1 Disclosure of sold/ booked inventorySOLDUNSOLD OCT TO DEC24.pdf · uploaded 1 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)V M HOUSING_0001_compressed.pdf · uploaded 4 Feb 2025Source
  • 1 a Details of encumbrances concerned to FinanceSigned Encumbrance_Haridham.pdf · uploaded 11 Feb 2025Source
  • 1 b Details of encumbrances concerned to LegalSigned Encumbrance_Haridham.pdf · uploaded 11 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 JAN TO MRC25.pdf · uploaded 12 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)HARIDHAM FORM 2_0001.pdf · uploaded 12 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)V M HOUSING FORM 3_0001_compressed.pdf · uploaded 13 May 2025Source
  • Withdrawal Update Form 1architect letter(2).pdf · uploaded 26 Sep 2025Source
  • Withdrawal Update Form 2Engineer letter(2).pdf · uploaded 26 Sep 2025Source
  • Withdrawal Update Form 3Haridam.pdf · uploaded 26 Sep 2025Source
  • Withdrawal Update Form 1architect letter(2).pdf · uploaded 2 Dec 2025Source
  • Withdrawal Update Form 2Engineer letter(2).pdf · uploaded 2 Dec 2025Source
  • Withdrawal Update Form 3V M HOUSING_11zon.pdf · uploaded 2 Dec 2025Source
  • Withdrawal Update Form 1architect letter(2).pdf · uploaded 5 Dec 2025Source
  • Withdrawal Update Form 2VM FROM2 JULY TO SEP25.pdf · uploaded 5 Dec 2025Source
  • Withdrawal Update Form 3V M HOUSING_11zon.pdf · uploaded 5 Dec 2025Source
  • Withdrawal Update Form 1FORM 1 OCT TO DEC 2025 VM HOUSING_0001.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 2VM FORM-2.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 3FORM 3 V M HOUSING (HARIDHAM)_11zon.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 1FORM 1 OCT TO DEC 2025 VM HOUSING_0001.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2VM FORM-2.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3FORM 3 V M HOUSING (HARIDHAM)_11zon.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 1Form 1 (1).pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 31V M HOUSING FORM 3.pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 1Form 1 (1).pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 26babd918-79ea-41aa-94d1-75f3f8f58380.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 HARIDHAM_0001.pdf · uploaded 10 Aug 2026Source
  • Form 5 (FY 2023-2024)FORM 5 HARIDHAM 2024.pdf · uploaded 10 Aug 2026Source
  • Form 5 (FY 2024-2025)FORM 5 HARIDHAM 2024-25.pdf · uploaded 10 Aug 2026Source
  • Form 5 (FY 2025-2026)FORM 5 HARIDHAM 2025-26.pdf · uploaded 10 Aug 2026Source
  • Withdrawal Update Form 1Form 1 (1).pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 HARIDHAM_0001.pdf · uploaded 11 Aug 2026Source
  • Form 2A (FY 2023-2024)V M HOUSING FORM 2A 23-24_0001.pdf · uploaded 11 Aug 2026Source
  • Form 2A (FY 2024-2025)V M HOUSING FORM 2A 24-25.pdf · uploaded 11 Aug 2026Source
  • Form 2A (FY 2025-2026)V M HOUSING FORM 2A 25-26.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 1VM-FORM-1-APRIL TO JUNE26.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 3FORM 3 HARIDHAM_0001.pdf · uploaded 14 Aug 2026Source

Technical

  • DocumentSENCTION PLAN HARIDHAM_compressed.pdf · uploaded 13 Oct 2023Source
  • DocumentSENCTION GROUND FLOOR HARIDHAM_compressed.pdf · uploaded 13 Oct 2023Source
  • DocumentHARIDHAM SHEET 5_compressed.pdf · uploaded 19 Dec 2023Source
  • DocumentSENCTION TIPICAL PLAN HARIDHAM_compressed.pdf · uploaded 19 Dec 2023Source
  • DocumentSENCTION REFUGE PLAN HARIDHAM_compressed (1)_compressed_compressed_compressed.pdf · uploaded 19 Dec 2023Source
  • Other – Technical561-1.pdf · uploaded 25 Jan 2024Source
  • Other – Technical561-2.pdf · uploaded 25 Jan 2024Source
  • Other – Technical561-3.pdf · uploaded 25 Jan 2024Source
  • Other – Technical561-4.pdf · uploaded 25 Jan 2024Source
  • Other – Technicalcc verification.pdf · uploaded 19 Mar 2024Source

Technical (Architect)

  • Documentvm april to june architech.pdf · uploaded 16 Dec 2024Source
  • DocumentFORM-1 JULY TO SEP.pdf · uploaded 16 Dec 2024Source
  • DocumentFORM-1 HARIDHAM.pdf · uploaded 1 Feb 2025Source
  • DocumentFORM-1 JAN TO MRC25.pdf · uploaded 12 Apr 2025Source
  • DocumentVM-FORM-1-APRIL TO JUNE26.pdf · uploaded 14 Aug 2026Source

Technical (Engineer)

  • Documentvm april to june engineer.pdf · uploaded 16 Dec 2024Source
  • DocumentFORM-2 JULY TO SEP.pdf · uploaded 16 Dec 2024Source
  • DocumentV M FORM 2.pdf · uploaded 1 Feb 2025Source
  • DocumentHARIDHAM FORM 2_0001.pdf · uploaded 12 Apr 2025Source
  • DocumentForm 2.pdf · uploaded 14 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 313 HISSA NO.2/3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—170 units in all
Address
313 Hissa No.2/3, M B Estate, VirarPIN 401303
Village
Vasai-Virar City (M Corp), Vasai taluka
Land area for this project
2,301 sq m (24,768 sq ft)
Permissible built-up area
9,795 sq m (1,05,432 sq ft)
Sanctioned built-up area
9,776 sq m (1,05,229 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

313 HISSA NO.2/3

Land as published on MahaRERA's project page

313 HISSA NO.2/3

Boundaries

North
Vishal Chs
South
Arihant Chs
East
Shubh Labh Chs
West
New Jay Palace

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking170 units

170 units registered

— · 170 units
TypeCarpet areaUnits
——170

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectUmesh S Kekre—
Chartered accountantRamesh Dhondiram Lukad—
EngineerDevang Dilip Mhatre—
EngineerShailesh Ramnaresh Pandey—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology