Residential / Group Housing · 1 building · 16 unitsRERA P99000049158

Pride Greens

Completion was pushed back 1 year to Dec 2025, and that date has passed too; no MahaRERA orders on record; 50% of its units are booked.

Umberpada, Palghar 401102 · Promoter: M V Corp

Delivery1 yr 10 mo latePromised Dec 2024 · revised Dec 2025 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales50% booked8 of 16 units · as the promoter reported to MahaRERA
Pride Greens project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 1 year to Dec 2025, and that date has passed too

  • This projectRegistered 1 Feb 2023, completion promised 31 Dec 2024, revised to 31 Dec 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP99000049158
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000491581 Feb 202331 Dec 202431 Dec 2025M V CorpProject page
Documents82

2 documents held by Deedo, 80 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN Card1 PAN Card.pdf · uploaded 23 Nov 2022Source

Legal

  • Legal Title reportLegal title report.pdf · uploaded 23 Nov 2022Source
  • Declaration Form BForm B Prajwal Raut.pdf · uploaded 26 Nov 2022Source

Migrated

  • 1 PAN Card1 PAN Card.pdf · uploaded 23 Nov 2022Source
  • 1 Copy of the legal title reportLegal title report.pdf · uploaded 23 Nov 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 23 Nov 2022Source
Show all 82 documentsShow fewer documents

Migrated

  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate.pdf · uploaded 23 Nov 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentApproval Plan_11zon.pdf · uploaded 26 Nov 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentRevised ZP Order 03 10 2022_11zon.pdf · uploaded 26 Nov 2022Source
  • 1 Declaration in FORM BForm B Prajwal Raut.pdf · uploaded 26 Nov 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Declaration Financial Related.pdf · uploaded 17 Jan 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Declaration Legal.pdf · uploaded 17 Jan 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Declaration Financial Related.pdf · uploaded 17 Jan 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Declaration Legal.pdf · uploaded 17 Jan 2023Source
  • 1 Copy of Layout Approval (in case of layout)Layout declaration.pdf · uploaded 17 Jan 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Inventory.pdf · uploaded 17 Jan 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 17 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest Of Asif.pdf · uploaded 17 Jan 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest Of Bhupendra.pdf · uploaded 17 Jan 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest Of Manish.pdf · uploaded 17 Jan 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsDisclosure Of Interest Of Prajwal.pdf · uploaded 17 Jan 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration Of Bank.pdf · uploaded 17 Jan 2023Source
  • 1 Deviation Report with respect to Allotment letterAllotment Letter.pdf · uploaded 17 Jan 2023Source
  • 1 Declaration about Commencement CertificateDeclaration About Commencement Certificate.pdf · uploaded 21 Jan 2023Source
  • 2 Declaration about Commencement Certificate1 Copy of Layout Approval (in case of layout) (1)-2-3.pdf · uploaded 21 Jan 2023Source
  • 1 CERSAI details1 CERSAI details (1).pdf · uploaded 21 Jan 2023Source
  • 2 CERSAI detailsCersai Declaration.pdf · uploaded 21 Jan 2023Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 21 Jan 2023Source
  • 1 Proforma of Agreement for saleAgreement for Sale.pdf · uploaded 27 Jan 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation AFS (D1 query).pdf · uploaded 27 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 13 Apr 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ilovepdf_merged (22).pdf · uploaded 13 Apr 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 13 Apr 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 final.pdf · uploaded 24 Jun 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 From 1 as on 30-09-2023.pdf · uploaded 25 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Form 1 as on 31-12-2023.pdf · uploaded 25 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 From 1 as on 31-03-2024.pdf · uploaded 25 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Form 1 as on 30-06-2024.pdf · uploaded 25 Feb 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)6 Form 1 as on 30-09-2024.pdf · uploaded 25 Feb 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)7 Form 1 as on 31-12-2024.pdf · uploaded 25 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Form 1 as on 30-06-2023.pdf · uploaded 25 Feb 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 Form 3 30-06-2024.pdf · uploaded 25 Feb 2025Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)7 Form 3 31-12-2024.pdf · uploaded 25 Feb 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)6 From 3 30-09-2024.pdf · uploaded 25 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)4 Form 3 31-03-2024.pdf · uploaded 25 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 Form 3 31-12-2023.pdf · uploaded 25 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 Form 3 30-09-2023.pdf · uploaded 25 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 Form 3 30-06-2023.pdf · uploaded 25 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 FORM 2 - 30-06-23.pdf · uploaded 25 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 FORM 2 - 30-09-23.pdf · uploaded 25 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 FORM 2 - 31-12-23.pdf · uploaded 25 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 FORM 2 - 31-03-24.pdf · uploaded 25 Feb 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 FORM 2 - 30-06-24.pdf · uploaded 25 Feb 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 FORM 2 - 30-09-24.pdf · uploaded 25 Feb 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 FORM 2 - 31-12-24.pdf · uploaded 25 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold Unsold.pdf · uploaded 25 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)M V Corp Form 5 2022-23.pdf · uploaded 7 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)M V Corp Form 5 2023-24.pdf · uploaded 7 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Mar 25.pdf · uploaded 22 May 2025Source
  • 1 Other – TechnicalAppendix F.pdf · uploaded 22 May 2025Source

Technical

  • DocumentApproval Plan_11zon.pdf · uploaded 26 Nov 2022Source
  • DocumentLayout declaration.pdf · uploaded 17 Jan 2023Source
  • Other – TechnicalAppendix F.pdf · uploaded 22 May 2025Source

Technical (Architect)

  • DocumentFORM 1.pdf · uploaded 13 Apr 2023Source
  • Document1 Form 1 as on 30-06-2023.pdf · uploaded 25 Feb 2025Source
  • Document2 From 1 as on 30-09-2023.pdf · uploaded 25 Feb 2025Source
  • Document3 Form 1 as on 31-12-2023.pdf · uploaded 25 Feb 2025Source
  • Document4 From 1 as on 31-03-2024.pdf · uploaded 25 Feb 2025Source
  • Document5 Form 1 as on 30-06-2024.pdf · uploaded 25 Feb 2025Source
  • Document6 Form 1 as on 30-09-2024.pdf · uploaded 25 Feb 2025Source
  • Document7 Form 1 as on 31-12-2024.pdf · uploaded 25 Feb 2025Source
  • DocumentForm 1- Mar 25.pdf · uploaded 22 May 2025Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 13 Apr 2023Source
  • Document1 FORM 2 - 30-06-23.pdf · uploaded 25 Feb 2025Source
  • Document2 FORM 2 - 30-09-23.pdf · uploaded 25 Feb 2025Source
  • Document3 FORM 2 - 31-12-23.pdf · uploaded 25 Feb 2025Source
  • Document4 FORM 2 - 31-03-24.pdf · uploaded 25 Feb 2025Source
  • Document5 FORM 2 - 30-06-24.pdf · uploaded 25 Feb 2025Source
  • Document6 FORM 2 - 30-09-24.pdf · uploaded 25 Feb 2025Source
  • Document7 FORM 2 - 31-12-24.pdf · uploaded 25 Feb 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSurvey no.1/1 Plot no 11

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1BHK Landowners16 units in all
Address
Survey no.1/1 Plot no 11, Umberpada, Nandane, SaphalePIN 401102
Village
Umberpada, Palghar taluka
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

Survey no.1/1 Plot no 11

Boundaries

North
Survey no 1 part
South
Road
East
Survey no 1 part
West
Survey no 1 Plot no 10

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

8 of 16 units booked (50%), as the promoter reported to MahaRERA

1BHK · 13 units1BHK Landowners · 3 units
TypeCarpet areaUnitsBooked
1BHK29.86 sq m · 321 sq ft31
1BHK30.08 sq m · 324 sq ft32
1BHK32.81 sq m · 353 sq ft42
1BHK32.97 sq m · 355 sq ft33
1BHK Landowners29.86 sq m · 321 sq ft10
1BHK Landowners30.08 sq m · 324 sq ft10
1BHK Landowners32.97 sq m · 355 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMahendra Kale—
Chartered accountantCa Bharat Dhonde—
EngineerStructect Consultancy—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology