Bhoomi Builders And Developers
Deedo IDDP-PAL-SVT3Completion was pushed back 6 months to Jun 2025, and that date has passed too; no MahaRERA orders on record; 8% of its units are booked.
Sopara, Palghar 401203 · by Bhoomi Builders And Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 6 months to Jun 2025, and that date has passed too
- This projectRegistered 7 Jan 2020, completion promised 30 Dec 2024, revised to 30 Jun 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000023853
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000023853 | 7 Jan 2020 | 30 Dec 2024 | 30 Jun 2025 | Bhoomi Builders And Developers | Project page |
Documents65
2 documents held by Deedo, 63 filings listed on MahaRERA's project page
Legal
Show all 65 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)LAY OUT PLAN.pdf · uploaded 28 Dec 2019Source
- 1 Building Plan Approval / NA Order for plotted developmentSANCTIONED PLAN.pdf · uploaded 28 Dec 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 28 Dec 2019Source
- 1 Declaration in FORM BFORM B KAMLESH.pdf · uploaded 28 Dec 2019Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 28 Dec 2019Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 28 Dec 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 28 Dec 2019Source
- 1 Proforma of Allotment letterRERA_Agreement_for_Sale_SOPARA_FINAL.pdf · uploaded 28 Dec 2019Source
- 2 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 8 Nov 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentPLAN.pdf · uploaded 8 Nov 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentNEW CC.pdf · uploaded 8 Nov 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 8 Nov 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 8 Nov 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 8 Nov 2023Source
- 1 Other – LegalLETTER UPDATE.pdf · uploaded 21 Nov 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 7 Feb 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 7 Feb 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 7 Feb 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 30 Apr 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 30 Apr 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 30 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5-23 -24.pdf · uploaded 11 May 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT_compressed (2).pdf · uploaded 10 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3_compressed (1).pdf · uploaded 10 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENG_compressed.pdf · uploaded 10 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 30 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 30 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 30 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A.pdf · uploaded 30 Oct 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_compressed (3).pdf · uploaded 13 Dec 2024Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 17 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 17 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 27 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 27 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 27 Mar 2025Source
- Form 1FORM 1.pdf · uploaded 9 Jun 2025Source
- Form 2FORM 2.pdf · uploaded 9 Jun 2025Source
- Form 3FORM 3.pdf · uploaded 9 Jun 2025Source
- Disclosure of Sold and Booked InventorySOLD UNSOLD DISCLOSURE.pdf · uploaded 9 Jun 2025Source
- Self-declaration of Quarterly ProgressSELF DECLARATION.pdf · uploaded 9 Jun 2025Source
- Form 1form 1.pdf · uploaded 10 Aug 2026Source
- Form 2form 2.pdf · uploaded 10 Aug 2026Source
- Form 3form 3.pdf · uploaded 10 Aug 2026Source
- Disclosure of Sold and Booked Inventorysold and unsold.pdf · uploaded 10 Aug 2026Source
- Form 2A (FY 2025-2026)FORM 2A.pdf · uploaded 10 Aug 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S NO 36 H NO 1A AT SOPARA
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop40 units in all
- Address
- S No 36 H No 1a At Sopara, Laxmi Ben Chheda Marg, SoparaPIN 401203
- Village
- Vasai-Virar City (M Corp), Vasai taluka
- Land area for this project
- 5,800 sq m (62,431 sq ft)
- Permissible built-up area
- 867 sq m (9,335 sq ft)
- Sanctioned built-up area
- 643 sq m (6,921 sq ft)
- Designated bank account
- 19
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO 36 H NO 1A AT SOPARA
Boundaries
- North
- Vvcmc Garden Of Natya Mandir
- South
- Konark Darshan Chs Ltd
- East
- Riddhi Siddhi Chs Ltd
- West
- Vvcmc Garden
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking40 units
3 of 40 units booked (8%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 28.25 sq m · 304 sq ft | 4 | 0 |
| 1BHK | 28.7 sq m · 309 sq ft | 14 | 1 |
| 2BHK | 38.01 sq m · 409 sq ft | 7 | 1 |
| 2BHK | 39.77 sq m · 428 sq ft | 3 | 0 |
| Shop | 7.42 sq m · 80 sq ft | 1 | 0 |
| Shop | 8.07 sq m · 87 sq ft | 1 | 0 |
| Shop | 8.37 sq m · 90 sq ft | 1 | 0 |
| Shop | 8.52 sq m · 92 sq ft | 1 | 0 |
Show all 14 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 8.62 sq m · 93 sq ft | 1 | 0 |
| Shop | 9.99 sq m · 108 sq ft | 1 | 0 |
| Shop | 10.96 sq m · 118 sq ft | 1 | 0 |
| Shop | 11.96 sq m · 129 sq ft | 1 | 0 |
| Shop | 13.03 sq m · 140 sq ft | 1 | 0 |
| Shop | 13.33 sq m · 143 sq ft | 3 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | himesh gupta and associates | — |
| Chartered accountant | Kalpak Churi | — |
| Engineer | Jitesh Patel | — |
| Engineer | Sandeep Subhash Parmane | — |
| Other | Harshida Construction | — |
| Other | Sandeep Subhash Paramane | — |
Source: MahaRERA project page. Contact details are not shown.