Ariana
Deedo IDDP-PAL-PGK5Completion was pushed back 4 months, to Jul 2027; no MahaRERA orders on record; 39% of its units are booked.
Sandor, Palghar 401201 · by Mansarovar Estate Builders Llp
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jul 2027
- This projectRegistered 6 Aug 2024, completion promised 31 Mar 2027, revised to 31 Jul 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000077313
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000077313 | 6 Aug 2024 | 31 Mar 2027 | 31 Jul 2027 | Mansarovar Estate Builders LLP | Project page |
Documents98
1 document held by Deedo, 97 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 16 May 2024Source
Legal
- Declaration Form Bestate form B.pdf · uploaded 16 May 2024Source
- Other – Legaldeclaration order 50.pdf · uploaded 29 May 2024Source
- Legal Title reporttitle search report as per scrutiny.pdf · uploaded 4 Jul 2024Source
- Other – Legalallotment_letter final.pdf · uploaded 22 Jul 2024Source
- Other – Legalestate rera query.pdf · uploaded 1 Aug 2024Source
Migrated
- 1 PAN CardPAN.pdf · uploaded 16 May 2024Source
Show all 98 documentsShow fewer documents
Migrated
- 1 Declaration in FORM Bestate form B.pdf · uploaded 16 May 2024Source
- 1 a Details of encumbrances concerned to FinanceDeclaration for non encumbrc.pdf · uploaded 17 May 2024Source
- 2 a Details of encumbrances concerned to FinanceDeclaration for non encumbrc.pdf · uploaded 17 May 2024Source
- 1 b Details of encumbrances concerned to LegalDeclaration for non encumbrc.pdf · uploaded 17 May 2024Source
- 2 b Details of encumbrances concerned to LegalDeclaration for non encumbrc.pdf · uploaded 17 May 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration for bank account.pdf · uploaded 17 May 2024Source
- 1 Deviation Report with respect to Allotment letterdeviation for allotment letter.pdf · uploaded 17 May 2024Source
- 1 Proforma of Allotment letterallotment_letter final.pdf · uploaded 18 May 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentsheet 2.pdf · uploaded 29 May 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentsheet 3.pdf · uploaded 29 May 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentsheet 4.pdf · uploaded 29 May 2024Source
- 1 Declaration about Commencement CertificateCC declaration.pdf · uploaded 29 May 2024Source
- 1 CERSAI detailsCersai Declaration (2).pdf · uploaded 29 May 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAyush Vora.pdf · uploaded 29 May 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDeepak Vora.pdf · uploaded 29 May 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsDhara Shah.pdf · uploaded 29 May 2024Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsDilip Jain.pdf · uploaded 29 May 2024Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsForrum Deepak vora.pdf · uploaded 29 May 2024Source
- 6 Disclosure of Interest in Other Real Estate OrganizationsIla Thar.pdf · uploaded 29 May 2024Source
- 7 Disclosure of Interest in Other Real Estate OrganizationsParth Shah.pdf · uploaded 29 May 2024Source
- 8 Disclosure of Interest in Other Real Estate OrganizationsPritish Jain.pdf · uploaded 29 May 2024Source
- 9 Disclosure of Interest in Other Real Estate OrganizationsRita Vora.pdf · uploaded 29 May 2024Source
- 10 Disclosure of Interest in Other Real Estate OrganizationsRoshan Thar.pdf · uploaded 29 May 2024Source
- 11 Disclosure of Interest in Other Real Estate OrganizationsSanjay Wade.pdf · uploaded 29 May 2024Source
- 1 Other – Legaldeclaration order 50.pdf · uploaded 29 May 2024Source
- 1 Other – Technicaldeclaration order 50.pdf · uploaded 3 Jun 2024Source
- 2 Other – TechnicalClarification as to plot.pdf · uploaded 10 Jun 2024Source
- 3 Other – TechnicalDeclaration for CC.pdf · uploaded 10 Jun 2024Source
- 1 Copy of the legal title reporttitle search report as per scrutiny.pdf · uploaded 4 Jul 2024Source
- 1 Copy of Layout Approval (in case of layout)layout plan_page-0001 (3)_compressed.pdf · uploaded 4 Jul 2024Source
- 2 Copy of Layout Approval (in case of layout)1 Copy of Layout Approval (in case of layout) (2).pdf · uploaded 4 Jul 2024Source
- 1 Commencement Certificates / NA Order for plotted development1 Commencement Certificates _ NA Order for plotted development (3).pdf · uploaded 4 Jul 2024Source
- 1 Deviation Report with respect to model copy of AgreementEstate - Deviation report.pdf · uploaded 4 Jul 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentCC verification mail Mansarover.pdf · uploaded 22 Jul 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 dt 8 6 24.pdf · uploaded 22 Jul 2024Source
- 1 Proforma of Agreement for saleagreement for Sale - Vasai.pdf · uploaded 22 Jul 2024Source
- 2 Other – Legalallotment_letter final.pdf · uploaded 22 Jul 2024Source
- 3 Other – Legalestate rera query.pdf · uploaded 1 Aug 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Mansarovar Estate Builders (FY 23-24).pdf · uploaded 9 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 4 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Mansarovar Estate Builders LLP - Sept 2024.pdf · uploaded 4 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 signed compressed.pdf · uploaded 4 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Mansarovar Estate signed compressed.pdf · uploaded 4 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 4 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Mansarovar Estate Builders - Sept 2024.pdf · uploaded 4 Jan 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Mansarovar Estate Builders as on Dec 2024.pdf · uploaded 17 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mansarovar Estate Builders as on Dec 2024.pdf · uploaded 17 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SIGNED.pdf · uploaded 25 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2023 24 Mansarovar Estate.pdf · uploaded 25 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold booked Inventory June 2024.pdf · uploaded 27 Feb 2025Source
- 2 Disclosure of sold/ booked inventoryDisclosure of Sold, Booked Inventory Sept 2024.pdf · uploaded 27 Feb 2025Source
- 3 Disclosure of sold/ booked inventoryDisclosure of sold booked Inventory Dec 2024.pdf · uploaded 27 Feb 2025Source
- Form 1Form 1.pdf · uploaded 17 Jun 2025Source
- Form 2Form 2.pdf · uploaded 17 Jun 2025Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 17 Jun 2025Source
- Form 3Form 3 Mansarovar Estate.pdf · uploaded 17 Jun 2025Source
- Form 1Form 1.pdf · uploaded 1 Sep 2025Source
- Form 2form 2.pdf · uploaded 1 Sep 2025Source
- Form 3signed Form3.pdf · uploaded 1 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure As on 30-06-2025.pdf · uploaded 1 Sep 2025Source
- Form 1Form 1 - Mansarovar Estate - Builders LLP - Sept 2025.pdf · uploaded 21 Nov 2025Source
- Form 2Form 2 - Mansarovar Estate Builders LLP - Sept 2025.pdf · uploaded 21 Nov 2025Source
- Form 3Form 3 - Mansarovar Estate Builders LLP - Sept 2025..pdf · uploaded 21 Nov 2025Source
- Disclosure of Sold and Booked InventoryDisclosure - Mansarovar Estate Buillders LLP - Sept 2025.pdf · uploaded 21 Nov 2025Source
- Form 5 (FY 2024-2025)Form 5 - Mansarovar Estate Builders LLP - 2024-25.pdf · uploaded 25 Dec 2025Source
- Form 1Form 1.pdf · uploaded 31 Jan 2026Source
- Form 2Form 2.pdf · uploaded 31 Jan 2026Source
- Form 3Form 3.pdf · uploaded 31 Jan 2026Source
- Disclosure of Sold and Booked InventoryDisclosure - Mansarovar Estate Buillders LLP - Dec 2025.pdf · uploaded 31 Jan 2026Source
- Form 2A (FY 2025-2026)Form 2A - Mansarovar Estate Builders LLP - March 2025 ..pdf · uploaded 21 May 2026Source
- Withdrawal Update Form 1Form 1 - Mansarovar Estate - March 2026..pdf · uploaded 2 Jun 2026Source
- Withdrawal Update Form 2Form 2 - Mansarovar Estate - March 2026..pdf · uploaded 2 Jun 2026Source
- Withdrawal Update Form 3Signed Form3 Upload.pdf · uploaded 2 Jun 2026Source
- Withdrawal Update Form 1Form 1 - Mansarovar Estate Builders LLP - June 2026.pdf · uploaded 24 Jul 2026Source
- Withdrawal Update Form 2Form 2 - Mansarovar Estate Builders LLP - June 2026.pdf · uploaded 24 Jul 2026Source
- Withdrawal Update Form 3Form 3 - Mansarovar Estate Builders LLP jun26.pdf · uploaded 24 Jul 2026Source
Technical
- Documentsheet 2.pdf · uploaded 29 May 2024Source
- Documentsheet 3.pdf · uploaded 29 May 2024Source
- Documentsheet 4.pdf · uploaded 29 May 2024Source
- Other – Technicaldeclaration order 50.pdf · uploaded 3 Jun 2024Source
- Other – TechnicalClarification as to plot.pdf · uploaded 10 Jun 2024Source
- Other – TechnicalDeclaration for CC.pdf · uploaded 10 Jun 2024Source
- Documentlayout plan_page-0001 (3)_compressed.pdf · uploaded 4 Jul 2024Source
- Document1 Copy of Layout Approval (in case of layout) (2).pdf · uploaded 4 Jul 2024Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 231/2, 231/3
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- —366 units in all
- Address
- old survey nos. 230/1, new survey no. 230/1/1, old survey no. 231/1, new survey no. 231/1/3, 231/2, 231/3, 231/4, 231/5, 231/6 and 231/7, Bhabola, SandorPIN 401201
- Village
- Vasai-Virar City (M Corp), Vasai taluka
- Land area for this project
- 1,071 sq m (11,526 sq ft)
- Permissible built-up area
- 17,335 sq m (1,86,587 sq ft)
- Sanctioned built-up area
- 17,335 sq m (1,86,587 sq ft)
- Recreational open space
- 323 sq m (3,480 sq ft)
- Designated bank account
- 19
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
old survey nos. 230/1, new survey no. 230/1/1, old survey no. 231/1, new survey no. 231/1/3, 231/2, 231/3, 231/4, 231/5, 231/6 and 231/7
Boundaries
- North
- Future Building
- South
- 20 M Wide Road
- East
- Existing Wing B
- West
- 12 Mt Inbond Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking366 units
366 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 366 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Encon Project Consultant Sanjay S Narang | — |
| Chartered accountant | Ankur Hitendra shah | — |
| Chartered accountant | M/s Nirav Vora & Co. | — |
| Engineer | Amit Das | — |
| Engineer | Mr. Vinay Kania | — |
| Engineer | Sanjay S Narang | — |
Source: MahaRERA project page. Contact details are not shown.