Nivanta
Deedo IDDP-PAL-HYMTCompletion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 0% of its units are booked.
Dongre, Palghar 401303 · by Mangalmurti Unique Realty Llp
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2030
- This projectRegistered 18 Mar 2025, completion promised 31 Dec 2029, revised to 30 Apr 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Building No 1 Wing A14 floors · 96 units0% booked
- Building No 2 Wing B13 floors · 128 units0% booked
- Building No 3 Wing C11 floors · 87 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000079650
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000079650 | 18 Mar 2025 | 31 Dec 2029 | 30 Apr 2030 | Mangalmurti Unique Realty LLP | Project page |
Documents71
1 document held by Deedo, 70 filings listed on MahaRERA's project page
Finance
- PAN CardMANGALMURTI PAN.pdf · uploaded 29 Jan 2025Source
Legal
- Legal Title reportNivanta_Title_Format A_Legal Title Report.pdf · uploaded 29 Jan 2025Source
- Other – Legal712.pdf · uploaded 10 Feb 2025Source
- Other – LegalCONVEYANCE 186 (1)-1-15_compressed.pdf · uploaded 25 Feb 2025Source
- Other – LegalCONVEYANCE 186 (1)-16-30_compressed.pdf · uploaded 25 Feb 2025Source
- Other – LegalCONVEYANCE 186 (1)-31-45_compressed.pdf · uploaded 25 Feb 2025Source
- Other – LegalCONVEYANCE 186 (1)-46-60_compressed.pdf · uploaded 25 Feb 2025Source
Show all 71 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardMANGALMURTI PAN.pdf · uploaded 29 Jan 2025Source
- 1 Copy of the legal title reportNivanta_Title_Format A_Legal Title Report.pdf · uploaded 29 Jan 2025Source
- 1 Copy of Layout Approval (in case of layout)xxx_compressed.pdf · uploaded 29 Jan 2025Source
- 2 Copy of Layout Approval (in case of layout)page 2 layout_compressed.pdf · uploaded 29 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Nivanta Form 1 Dec 24.pdf · uploaded 29 Jan 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentcc.pdf · uploaded 29 Jan 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentpage 3 wing A_compressed.pdf · uploaded 29 Jan 2025Source
- 2 Building Plan Approval / NA Order for plotted developmentwing b_compressed.pdf · uploaded 29 Jan 2025Source
- 3 Building Plan Approval / NA Order for plotted developmentwing c_compressed.pdf · uploaded 29 Jan 2025Source
- 1 Proforma of Agreement for saleagreement.pdf · uploaded 29 Jan 2025Source
- 1 a Details of encumbrances concerned to FinanceNivanta_Finance Encumbrance.pdf · uploaded 3 Feb 2025Source
- 1 Proforma of Allotment letterDraft Allotment Letter.pdf · uploaded 3 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Nivanta_Form 2.pdf · uploaded 3 Feb 2025Source
- 1 Declaration about Commencement CertificateNivanta_Declaration About CC.pdf · uploaded 3 Feb 2025Source
- 1 CERSAI detailscersai.pdf · uploaded 3 Feb 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Nivanta_Format A.pdf · uploaded 3 Feb 2025Source
- 1 Deviation Report with respect to Allotment letterNivanta Allotment Deviation.pdf · uploaded 3 Feb 2025Source
- 1 b Details of encumbrances concerned to LegalNivanta_Finance Encumbrance.pdf · uploaded 3 Feb 2025Source
- 1 Deviation Report with respect to model copy of AgreementNivanta AFS Deviation.pdf · uploaded 3 Feb 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsNivanta AAM Annexure A.pdf · uploaded 3 Feb 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsNivanta AMM Annexure A.pdf · uploaded 3 Feb 2025Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsNivanta_DKJ_Annexure A.pdf · uploaded 3 Feb 2025Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsNivanta_MJM_Annexure A.pdf · uploaded 3 Feb 2025Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsNivanta_PAM_Annexure A.pdf · uploaded 3 Feb 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Nivanta_Format B.pdf · uploaded 3 Feb 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectNivanta_Secured Unsecured.pdf · uploaded 3 Feb 2025Source
- 2 a Details of encumbrances concerned to FinanceLEGAL ENCUMBRANCES.pdf · uploaded 10 Feb 2025Source
- 1 Other – Legal712.pdf · uploaded 10 Feb 2025Source
- 2 b Details of encumbrances concerned to LegalLEGAL ENCUMBRANCES.pdf · uploaded 10 Feb 2025Source
- 7 Other – LegalCONVEYANCE 186 (1)-76-95_compressed (1).pdf · uploaded 25 Feb 2025Source
- 6 Other – LegalCONVEYANCE 186 (1)-61-75_compressed.pdf · uploaded 25 Feb 2025Source
- 5 Other – LegalCONVEYANCE 186 (1)-46-60_compressed.pdf · uploaded 25 Feb 2025Source
- 3 Other – LegalCONVEYANCE 186 (1)-16-30_compressed.pdf · uploaded 25 Feb 2025Source
- 2 Other – LegalCONVEYANCE 186 (1)-1-15_compressed.pdf · uploaded 25 Feb 2025Source
- 4 Other – LegalCONVEYANCE 186 (1)-31-45_compressed.pdf · uploaded 25 Feb 2025Source
- 1 Other – TechnicalNIVANTA CC VERIFICATION.pdf · uploaded 25 Feb 2025Source
- 1 Declaration in FORM BFORM B (1).pdf · uploaded 8 Mar 2025Source
- 2 Other – TechnicalANNEXURE-A.pdf · uploaded 8 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Nivanta Form 3 (1).pdf · uploaded 12 Mar 2025Source
- Withdrawal Update Form 1Nivanta Form 1 June 2025.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 1Nivanta Form 1 Sep 2025.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 1Nivanta Form 1 Dec 2025.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 2Nivanta Form 2 June 2025.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 2Nivanta Form 2 September 2025.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 2Nivanta Form 2 December 2025.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 3Nivanta Form 3 June 2025.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 3Nivanta Form 3 September 2025.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 3Nivanta Form 3 December 2025.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 1Nivanta Form 1 March 2026.pdf · uploaded 10 Oct 2026Source
- Withdrawal Update Form 2Nivanta Form 2 March 2026.pdf · uploaded 10 Oct 2026Source
- Withdrawal Update Form 3Nivanta Form 3 March 2026.pdf · uploaded 10 Oct 2026Source
Technical
- Documentxxx_compressed.pdf · uploaded 29 Jan 2025Source
- Documentpage 2 layout_compressed.pdf · uploaded 29 Jan 2025Source
- Documentpage 3 wing A_compressed.pdf · uploaded 29 Jan 2025Source
- Documentwing b_compressed.pdf · uploaded 29 Jan 2025Source
- Documentwing c_compressed.pdf · uploaded 29 Jan 2025Source
- Other – TechnicalNIVANTA CC VERIFICATION.pdf · uploaded 25 Feb 2025Source
- Other – TechnicalANNEXURE-A.pdf · uploaded 8 Mar 2025Source
Technical (Architect)
- DocumentNivanta Form 1 March 2026.pdf · uploaded 10 Oct 2026Source
Technical (Engineer)
- DocumentNivanta Form 2 March 2026.pdf · uploaded 10 Oct 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S NO 186 at Vasai
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK311 units in all
- Address
- S No 186, S No 186, Narangi Bypass Road, Village - DongarePIN 401303
- Village
- Dongre, Vasai taluka
- Location
- 19.47192, 72.81069
- Land area for this project
- 8,400 sq m (90,417 sq ft)
- Permissible built-up area
- 27,246 sq m (2,93,276 sq ft)
- Sanctioned built-up area
- 16,455 sq m (1,77,124 sq ft)
- Recreational open space
- 817 sq m (8,789 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO 186
Boundaries
- North
- S No 183
- South
- S No 190
- East
- S No 187
- West
- S No 185
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking311 units
0 of 311 units booked (0%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 1 Wing A | 1BHK | 29.3 sq m · 315 sq ft | 14 | 0 |
| Building No 1 Wing A | 1BHK | 29.74 sq m · 320 sq ft | 26 | 0 |
| Building No 1 Wing A | 1BHK | 29.86 sq m · 321 sq ft | 14 | 0 |
| Building No 1 Wing A | 2BHK | 43.85 sq m · 472 sq ft | 28 | 0 |
| Building No 1 Wing A | 2BHK | 47.55 sq m · 512 sq ft | 14 | 0 |
| Building No 2 Wing B | 1BHK | 29.74 sq m · 320 sq ft | 89 | 0 |
| Building No 2 Wing B | 2BHK | 43.86 sq m · 472 sq ft | 26 | 0 |
| Building No 2 Wing B | 2BHK | 47.73 sq m · 514 sq ft | 13 | 0 |
Show all 13 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 3 Wing C | 1BHK | 29.02 sq m · 312 sq ft | 10 | 0 |
| Building No 3 Wing C | 1BHK | 29.74 sq m · 320 sq ft | 33 | 0 |
| Building No 3 Wing C | 1BHK | 43.86 sq m · 472 sq ft | 22 | 0 |
| Building No 3 Wing C | 2BHK | 47.75 sq m · 514 sq ft | 11 | 0 |
| Building No 3 Wing C | 3BHK | 49.46 sq m · 532 sq ft | 11 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Hardik Patil | — |
| Chartered accountant | Harsh N Shah | — |
| Engineer | Ajay M Shah | — |
Source: MahaRERA project page. Contact details are not shown.