10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects1
Registrations1
Completion still due01 past their date
Median extensionNot on record0% of registrations extended
Regulatory cases0none on MahaRERA's lists

10 in 10 registrations run late here

1 MahaRERA registration in Ekundi (J)

1 past even the latest date

Projects in Ekundi (J)

1 project registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Shantadevi HomesSanjay Bhaskarrao ChalukyaCompleted——
Ekundi (J) market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Sanjay Bhaskarrao Chalukya1 project

Ekundi (J), in questions

How many projects in Ekundi (J) run late?

10 in 10 MahaRERA registrations (1 of 1): their completion date was extended or has passed, data through 7 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ekundi (J) by Deedo. Medians on fewer than 3 deeds are not shown.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology