Soham
Deedo IDDP-NSK-K2Y6Its promised completion date, Dec 2017, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Nashik (M Corp.), Nashik 422005 · Promoter: S B Constructions
Its promised completion date, Dec 2017, has passed and MahaRERA does not show it completed
- This projectRegistered 14 Sep 2017, completion promised 31 Dec 2017, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51600013041
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600013041 | 14 Sep 2017 | 31 Dec 2017 | 31 Dec 2017 | S B Constructions | Project page |
Documents21
1 document held by Deedo, 20 filings listed on MahaRERA's project page
Finance
- PAN Cardimg00098.pdf · uploaded 31 Jul 2017Source
Legal
Show all 21 documentsShow fewer documents
Migrated
- 1 Building Plan Approval (IOD)img00110.pdf · uploaded 31 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentcOMMENCEMENT cERTIFICATE.pdf · uploaded 31 Jul 2017Source
- 1 Declaration in FORM BF B.pdf · uploaded 31 Jul 2017Source
- 1 Proforma of Allotment letterAL.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)AC certificate.pdf · uploaded 4 Aug 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)EC Certificate.pdf · uploaded 4 Aug 2017Source
- 1 Certificates of CA (Form 3)FORM 3.pdf · uploaded 4 Aug 2017Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate.pdf · uploaded 1 Aug 2021Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Rera.pdf · uploaded 1 Sep 2021Source
Technical
Technical (Architect)
- DocumentAC certificate.pdf · uploaded 4 Aug 2017Source
Technical (Engineer)
- DocumentEC Certificate.pdf · uploaded 4 Aug 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsPlot no 12 13, Sr no 83/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- Residential20 units in all
- Address
- Plot no 12 13, Sr no 83/2PIN 422005
- Village
- Nashik (M Corp.), Nashik taluka
- Location
- 16.69665, 74.60783
- Designated bank account
- 119
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot no 14
- South
- Sr no 84
- East
- Road
- West
- Plot no 10 11
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking20 units
0 of 20 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Residential | 948.2 sq m · 10,206 sq ft | 20 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Hrishikesh Pawar | — |
Source: MahaRERA project page. Contact details are not shown.