Nilkanth Alpha
Deedo IDDP-NSK-PGMNCompletion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 40% of its units are booked.
Makhmalabad, Nashik 422003 · by Nilkanth Build
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2031
- This projectRegistered 27 Jul 2023, completion promised 31 Dec 2030, revised to 30 Apr 2031.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51600052183
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600052183 | 27 Jul 2023 | 31 Dec 2030 | 30 Apr 2031 | Nilkanth Build | Project page |
Documents82
1 document held by Deedo, 81 filings listed on MahaRERA's project page
Finance
- PAN CardFirm Pan Card.pdf · uploaded 20 Jun 2023Source
Legal
Migrated
- 1 PAN CardFirm Pan Card.pdf · uploaded 20 Jun 2023Source
- 1 Copy of the legal title reportTitle Report.pdf · uploaded 20 Jun 2023Source
- 1 a Details of encumbrances concerned to FinanceEncumbrances.pdf · uploaded 20 Jun 2023Source
- 1 b Details of encumbrances concerned to LegalEncumbrances.pdf · uploaded 20 Jun 2023Source
Show all 82 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)LayoutPlan.pdf · uploaded 20 Jun 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding plan corrected.pdf · uploaded 20 Jun 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT.pdf · uploaded 20 Jun 2023Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 20 Jun 2023Source
- 1 Declaration in FORM BFormB.pdf · uploaded 20 Jun 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 20 Jun 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Jun 2023Source
- 1 CERSAI detailsCersai Asset Based Search.pdf · uploaded 20 Jun 2023Source
- 2 CERSAI detailsCERSAI_Search_Report_200271950582_For_Asset_Based_Search_20_06_2023_12_18_07_537.pdf · uploaded 20 Jun 2023Source
- 3 CERSAI detailsCERSAI_Search_Report_200271950620_For_Asset_Based_Search_20_06_2023_12_18_18_319.pdf · uploaded 20 Jun 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Jun 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A - Disclosure.pdf · uploaded 20 Jun 2023Source
- 1 Proforma of Allotment letterAllotment New.pdf · uploaded 20 Jun 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 20 Jun 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation - AL.pdf · uploaded 20 Jun 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviations- AFS.pdf · uploaded 20 Jun 2023Source
- 1 Other – TechnicalCredai.pdf · uploaded 20 Jun 2023Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance.pdf · uploaded 26 Jun 2023Source
- 2 b Details of encumbrances concerned to LegalEncumbrance.pdf · uploaded 26 Jun 2023Source
- 1 Proforma of Agreement for saleDraft AFS Revised 3.pdf · uploaded 20 Jul 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 8 Feb 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Feb 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 8 Feb 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 8 May 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 May 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 8 May 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3.pdf · uploaded 8 May 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 15 Jul 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 15 Jul 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 15 Jul 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure.pdf · uploaded 6 Aug 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 16 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 16 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 16 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 16 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 02.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 19 Apr 2025Source
- Withdrawal Update Form 1Form 1 NB.pdf · uploaded 30 Jul 2025Source
- Withdrawal Update Form 2Form 2 NB.pdf · uploaded 30 Jul 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 30 Jul 2025Source
- Form 5 (FY 2024-2025)Form 5.pdf · uploaded 11 Oct 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 14 Oct 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 14 Oct 2025Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 14 Oct 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 20 Jan 2026Source
- Form 2A (FY 2024-2025)Form 2A 2025.pdf · uploaded 25 Apr 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 25 Apr 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 18 Jul 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 18 Jul 2026Source
Technical
- DocumentLayoutPlan.pdf · uploaded 20 Jun 2023Source
- DocumentBuilding plan corrected.pdf · uploaded 20 Jun 2023Source
- Other – TechnicalCredai.pdf · uploaded 20 Jun 2023Source
- DocumentAPPROVAL PLAN P NO 62 TO 66 9 BUILDING B WITH SIGN (1).pdf · uploaded 30 Apr 2026Source
- OthersCOMM CERT P NO 62 TO 66 9 BULDING B WITH SIGN (1).pdf · uploaded 30 Apr 2026Source
- DocumentAnn A.pdf · uploaded 2 May 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel P 62 TO 66/9 S NO 410/2
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop, 3BHK63 units in all
- Address
- P 62 To 66/9 S No 410/2, Peth Road, MakhmalabadPIN 422003
- Village
- Nashik (M Corp.), Nashik taluka
- Location
- 20.05206, 73.78764
- Land area for this project
- 1,879 sq m (20,231 sq ft)
- Permissible built-up area
- 5,623 sq m (60,524 sq ft)
- Sanctioned built-up area
- 4,954 sq m (53,324 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
P 62 TO 66/9 S NO 410/2
Boundaries
- North
- 9 Mtr Colony Road
- South
- Open Space
- East
- P 62 To 66 1 To 8
- West
- S No 411
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking63 units
25 of 63 units booked (40%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A Wing | 1BHK | 42.76 sq m · 460 sq ft | 6 | 2 |
| A Wing | 2BHK | 47.92 sq m · 516 sq ft | 6 | 2 |
| A Wing | 2BHK | 50.47 sq m · 543 sq ft | 6 | 0 |
| A Wing | 2BHK | 52.57 sq m · 566 sq ft | 12 | 5 |
| A Wing | Shop | 12.59 sq m · 136 sq ft | 2 | 2 |
| A Wing | Shop | 14.67 sq m · 158 sq ft | 2 | 1 |
| A Wing | Shop | 14.91 sq m · 160 sq ft | 2 | 1 |
| A Wing | Shop | 15.43 sq m · 166 sq ft | 1 | 1 |
Show all 14 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A Wing | Shop | 22.26 sq m · 240 sq ft | 1 | 1 |
| A Wing | Shop | 25.32 sq m · 273 sq ft | 1 | 1 |
| B Wing | 2BHK | 49.76 sq m · 536 sq ft | 6 | 3 |
| B Wing | 2BHK | 53.07 sq m · 571 sq ft | 6 | 2 |
| B Wing | 2BHK | 56.45 sq m · 608 sq ft | 6 | 2 |
| B Wing | 3BHK | 75.51 sq m · 813 sq ft | 6 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Vitthal Kathale | — |
| Chartered accountant | Ca Sonali Gujarathi | — |
| Chartered accountant | Randhir Dwarkadas Gujarathi | — |
| Engineer | Aadhar Engineers | — |
| Engineer | Dharmesh Devjibhai Soliya | — |
Source: MahaRERA project page. Contact details are not shown.