Skip to content
Residential / Group Housing · 1 building · 14 unitsRERA P51600049476

Govind Vrindavan

Deedo IDDP-NSK-0MEQ

Completion was pushed back 4 months, to May 2027; no MahaRERA orders on record; 7% of its units are booked.

Kamatwade, Nashik 422005 · by Vivaan Infraproject

DeliveryExtended 4 moPromised Jan 2027 · now due May 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales7% booked1 of 14 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to May 2027

  • This projectRegistered 15 Feb 2023, completion promised 31 Jan 2027, revised to 31 May 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51600049476
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160004947615 Feb 202331 Jan 202731 May 2027Vivaan InfraprojectProject page
Documents103

1 document held by Deedo, 102 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardvivaan infra pan-converted.pdf · uploaded 10 Dec 2021Source

Legal

  • Legal Title reportTitle report rera Oct 2021_11zon.pdf · uploaded 11 Dec 2021Source
  • Declaration Form BRera Notary Govind runda_7_11zon.pdf · uploaded 11 Dec 2021Source

Migrated

  • 1 PAN Cardvivaan infra pan-converted.pdf · uploaded 10 Dec 2021Source
  • 1 Copy of the legal title reportTitle report rera Oct 2021_11zon.pdf · uploaded 11 Dec 2021Source
  • 1 Copy of Layout Approval (in case of layout)Layout letter Rera govind_2_11zon.pdf · uploaded 11 Dec 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentNMC APPROVED PLAN SCAN RERA-converted.pdf · uploaded 11 Dec 2021Source
Show all 103 documentsShow fewer documents

Migrated

  • 1 Declaration about Commencement CertificateCommenment declaration.pdf · uploaded 11 Dec 2021Source
  • 1 Declaration in FORM BRera Notary Govind runda_7_11zon.pdf · uploaded 11 Dec 2021Source
  • 1 a Details of encumbrances concerned to FinanceNo emcum finance.pdf · uploaded 13 Dec 2022Source
  • 1 b Details of encumbrances concerned to LegalNO ENCUM LEGAL.pdf · uploaded 13 Dec 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 13 Dec 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate Vivaan infra (1).pdf · uploaded 13 Dec 2022Source
  • 1 Proforma of Allotment letterAllotment Letter Rera.pdf · uploaded 13 Dec 2022Source
  • 1 Proforma of Agreement for saleAgreement for sale - Vivaan Infraproject.pdf · uploaded 13 Dec 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFinal Declaration Sep bank accc.pdf · uploaded 13 Dec 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation for Allotment Letter.pdf · uploaded 13 Dec 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation for AFS Final.pdf · uploaded 13 Dec 2022Source
  • 1 Disclosure of Interest in Other Real Estate Organizations1 PAN Card.pdf · uploaded 3 Jan 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement merged for shortfall compressed.pdf · uploaded 7 Feb 2023Source
  • 1 Other – Technicalbuilding plan.pdf · uploaded 7 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 arch vivaan infra oct 2023.pdf · uploaded 12 Oct 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 12 Oct 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 12 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 12 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 14 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 2021-22.pdf · uploaded 9 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA FROM -1.pdf · uploaded 9 Mar 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)form-2- Govind_Vrindavan_Vivaan_Infra_NSK_-_RERA_07022024.pdf · uploaded 9 Mar 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-3 SCAN_20240208_130301475.pdf · uploaded 9 Mar 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Q-4 FY-23-24 RERA Govind Vrundavan.pdf · uploaded 28 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Q-1 FY-24-25 RERA Govind Vrundavan.pdf · uploaded 28 Jan 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Q-2 FY-24-25 RERA Govind Vrundavan.pdf · uploaded 28 Jan 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Q-1 FY-24-25 RERA Govind Vrundavan.pdf · uploaded 28 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 March-24.pdf · uploaded 28 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 June-24.pdf · uploaded 28 Jan 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Sep-24.pdf · uploaded 28 Jan 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 Dec-2024.pdf · uploaded 28 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2 Q-4 FY-23-24 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK 31032024.pdf · uploaded 28 Jan 2025Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2 Q-1 FY-24-25 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK 30062024.pdf · uploaded 28 Jan 2025Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2 Q-2 FY-24-25 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK 30092024.pdf · uploaded 28 Jan 2025Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2 Q-3 FY-24-25 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK 31122024.pdf · uploaded 28 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5 -Mehta.pdf · uploaded 28 Jan 2025Source
  • Form 1Form-1 Q-4 FY-23-24 RERA Govind Vrundavan.pdf · uploaded 26 May 2025Source
  • Form 2Form-2 Q-4 FY-23-24 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK 31032024.pdf · uploaded 26 May 2025Source
  • Form 3Form-3 March-24.pdf · uploaded 26 May 2025Source
  • Form 1RERA FROM -1.pdf · uploaded 26 May 2025Source
  • Form 2form-2- Govind_Vrindavan_Vivaan_Infra_NSK_-_RERA_07022024.pdf · uploaded 26 May 2025Source
  • Form 3form-3 SCAN_20240208_130301475.pdf · uploaded 26 May 2025Source
  • Form 1Form-1 Q-1 FY-24-25 RERA Govind Vrundavan.pdf · uploaded 26 May 2025Source
  • Form 2Form-2 Q-1 FY-24-25 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK 30062024.pdf · uploaded 26 May 2025Source
  • Form 3Form-3 June-24.pdf · uploaded 26 May 2025Source
  • Form 1Form-1 Q-2 FY-24-25 RERA Govind Vrundavan.pdf · uploaded 26 May 2025Source
  • Form 2Form-2 Q-2 FY-24-25 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK 30092024.pdf · uploaded 26 May 2025Source
  • Form 3Form-3 Sep-24.pdf · uploaded 26 May 2025Source
  • Form 1Form-1 Q-1 FY-24-25 RERA Govind Vrundavan.pdf · uploaded 26 May 2025Source
  • Form 2Form-2 Q-3 FY-24-25 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK 31122024.pdf · uploaded 26 May 2025Source
  • Form 3Form-3 Dec-2024.pdf · uploaded 26 May 2025Source
  • Form 1RERA FROM -1 FY-2024-25 Q-4-.pdf · uploaded 29 May 2025Source
  • Form 2RERA form 2 FY-2024-25 Q-4.pdf · uploaded 29 May 2025Source
  • Form 3Form-3 Q-4 FY-2024-25.pdf · uploaded 29 May 2025Source
  • Form 1form 1 FY-2023-24 Q-2.pdf · uploaded 29 May 2025Source
  • Form 2Form 2 FY-2023-24 Q-2.pdf · uploaded 29 May 2025Source
  • Form 3Form 3 FY-2023-24 Q-2.pdf · uploaded 29 May 2025Source
  • Form 5 (FY 2023-2024)Form-5 FY-2023-24.pdf · uploaded 29 May 2025Source
  • Form 1Form-1 FY-25-26 Q-1.pdf · uploaded 23 Jul 2025Source
  • Form 2Form-2 FY-25-26 Q-1.pdf · uploaded 23 Jul 2025Source
  • Form 3Form-3 FY-25-26 Q-1.pdf · uploaded 23 Jul 2025Source
  • Disclosure of Sold and Booked InventorySold Inventory FY-25-26 Q-1.pdf · uploaded 23 Jul 2025Source
  • Form 5 (FY 2022-2023)FORM 5 2022-23.pdf · uploaded 1 Nov 2025Source
  • Form 5 (FY 2024-2025)RERA Form 5 FY-2024-25.pdf · uploaded 1 Nov 2025Source
  • Form 1Form-1 RERA_Govind Vrindavan_Vivaan Infraproject_.pdf · uploaded 4 Nov 2025Source
  • Form 2Form-2 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK_30092025.pdf · uploaded 4 Nov 2025Source
  • Form 3Form-3 Q-2 FY-2025-26 SCAN_20251101_174538666.pdf · uploaded 4 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold and Unsold Inventory FY-2025-26 Q-2.pdf · uploaded 4 Nov 2025Source
  • Form 3FORM 3 SCAN.pdf · uploaded 14 Nov 2025Source
  • Form 1form 1.pdf · uploaded 14 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 14 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold and Unslod Inventory.pdf · uploaded 14 Nov 2025Source
  • Form 1form 1.pdf · uploaded 14 Nov 2025Source
  • Form 2Form 2.pdf · uploaded 14 Nov 2025Source
  • Form 3FORM 3 SCAN.pdf · uploaded 14 Nov 2025Source
  • Disclosure of Sold and Booked InventorySold and Unslod Inventory.pdf · uploaded 14 Nov 2025Source
  • Form 1MR HARSHAL JADHAV - FROM - 1-.pdf · uploaded 20 Jun 2026Source
  • Form 2Form-2 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK_30092025.pdf · uploaded 20 Jun 2026Source
  • Form 3Form-3 Q-3 FY-2025-26.pdf · uploaded 20 Jun 2026Source
  • OthersCompletion Certificate Govind Vrindavan Vivaan Infrastructure.pdf · uploaded 20 Jun 2026Source
  • Disclosure of Sold and Booked InventorySold and Unsold Inventory FY-2025-26 Q-3.pdf · uploaded 20 Jun 2026Source
  • Form 1MR HARSHAL JADHAV - FROM - 1-.pdf · uploaded 20 Jun 2026Source
  • Form 2Form-2 RERA_Govind Vrindavan_Vivaan Infraproject_ NSK_30092025.pdf · uploaded 20 Jun 2026Source
  • Form 3Form-3 Q-4 FY-2025-26.pdf · uploaded 20 Jun 2026Source
  • Disclosure of Sold and Booked InventorySold and Unsold Inventory FY-2025-26 Q-4.pdf · uploaded 20 Jun 2026Source
  • OthersCompletion Certificate Govind Vrindavan Vivaan Infrastructure.pdf · uploaded 20 Jun 2026Source

Technical

  • DocumentLayout letter Rera govind_2_11zon.pdf · uploaded 11 Dec 2021Source
  • DocumentNMC APPROVED PLAN SCAN RERA-converted.pdf · uploaded 11 Dec 2021Source
  • Other – Technicalbuilding plan.pdf · uploaded 7 Feb 2023Source

Technical (Architect)

  • DocumentRERA FROM -1.pdf · uploaded 9 Mar 2024Source
  • DocumentForm-1 Q-4 FY-23-24 RERA Govind Vrundavan.pdf · uploaded 28 Jan 2025Source
  • DocumentForm-1 Q-1 FY-24-25 RERA Govind Vrundavan.pdf · uploaded 28 Jan 2025Source
  • DocumentForm-1 Q-2 FY-24-25 RERA Govind Vrundavan.pdf · uploaded 28 Jan 2025Source
  • DocumentForm-1 Q-1 FY-24-25 RERA Govind Vrundavan.pdf · uploaded 28 Jan 2025Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 12 Oct 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO 1 SURVEY NO 23/2A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
3BHK14 units in all
Address
Plot No 1 Survey No 23/2a, Vikhe Patil Gschool Road, KamatwadaPIN 422005
Village
Nashik (M Corp.), Nashik taluka
Land area for this project
374 sq m (4,028 sq ft)
Permissible built-up area
1,127 sq m (12,131 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 1 SURVEY NO 23/2A

Land as published on MahaRERA's project page

PLOT NO 1 SURVEY NO 23/2A

Boundaries

North
9 Meter Road
South
NMC Open Space
East
9 Meter Road
West
Plot No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking14 units

1 of 14 units booked (7%), as the promoter reported to MahaRERA

3BHK · 14 units
TypeCarpet areaUnitsBooked
3BHK62.91 sq m · 677 sq ft141

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAshok Jamdar—
Chartered accountantAjay Pravinchandra Mehta—
Chartered accountantCA Paresh Sabara—
Chartered accountantCA Tushar Pagar—
EngineerMilind Rathi—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology