Ishna
Deedo IDDP-NSK-C9PYIts promised completion date, Sep 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Adgaon, Nashik 422003 · by Fourth Dimension Properties
Buying a flat here?
See every deed registered on it.
Its promised completion date, Sep 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 18 Feb 2021, completion promised 7 Sep 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51600028294
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600028294 | 18 Feb 2021 | 7 Sep 2024 | 7 Sep 2024 | Fourth Dimension Properties | Project page |
Documents53
1 document held by Deedo, 52 filings listed on MahaRERA's project page
Finance
- PAN CardFDP PAN.pdf · uploaded 9 Feb 2021Source
Legal
- OtherN A Tax Receipt 304-30.pdf · uploaded 9 Feb 2021Source
- OtherLAYOUT LETTER 304-30.pdf · uploaded 9 Feb 2021Source
- Other6-D Entry Chain Document.pdf · uploaded 9 Feb 2021Source
- Other1438.pdf · uploaded 9 Feb 2021Source
- OtherSALE DEED.pdf · uploaded 9 Feb 2021Source
- OtherNA ORDER.pdf · uploaded 9 Feb 2021Source
Show all 53 documentsShow fewer documents
Legal
- Legal Title report1432.pdf · uploaded 9 Feb 2021Source
- Declaration Form BAFFIDAVIT CUM DECLARATION.pdf · uploaded 9 Feb 2021Source
- Other15.pdf · uploaded 11 Apr 2023Source
- Other15.pdf · uploaded 11 Apr 2023Source
- Other15.pdf · uploaded 11 Apr 2023Source
- Other15.pdf · uploaded 11 Apr 2023Source
- Other15.pdf · uploaded 11 Apr 2023Source
- OtherFlat no19.pdf · uploaded 11 Apr 2023Source
- OtherFlat no19.pdf · uploaded 11 Apr 2023Source
- OtherFlat no19.pdf · uploaded 11 Apr 2023Source
- OtherFlat no19.pdf · uploaded 12 Apr 2023Source
- OtherFLAT NO25.pdf · uploaded 12 Apr 2023Source
- OtherFLAT NO25.pdf · uploaded 12 Apr 2023Source
Migrated
- 1 PAN CardFDP PAN.pdf · uploaded 9 Feb 2021Source
- 1 Copy of the legal title report1432.pdf · uploaded 9 Feb 2021Source
- 1 Details of encumbrancesAFFIDAVIT CUM DECLARATION.pdf · uploaded 9 Feb 2021Source
- 1 Copy of Layout Approval (in case of layout)304 Layout Plan.pdf · uploaded 9 Feb 2021Source
- 1 Building Plan Approval / NA Order for plotted development304 Approved Building plan.pdf · uploaded 9 Feb 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT 304.pdf · uploaded 9 Feb 2021Source
- 1 Declaration in FORM BAFFIDAVIT CUM DECLARATION.pdf · uploaded 9 Feb 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE .pdf · uploaded 9 Feb 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE.pdf · uploaded 9 Feb 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICAT .pdf · uploaded 9 Feb 2021Source
- 1 Proforma of Allotment letterAGREEMENT DRAFT.pdf · uploaded 9 Feb 2021Source
- 1 OtherN A Tax Receipt 304-30.pdf · uploaded 9 Feb 2021Source
- 2 OtherLAYOUT LETTER 304-30.pdf · uploaded 9 Feb 2021Source
- 3 Other6-D Entry Chain Document.pdf · uploaded 9 Feb 2021Source
- 4 Other1438.pdf · uploaded 9 Feb 2021Source
- 5 OtherSALE DEED.pdf · uploaded 9 Feb 2021Source
- 6 OtherNA ORDER.pdf · uploaded 9 Feb 2021Source
- 7 Other15.pdf · uploaded 11 Apr 2023Source
- 8 Other15.pdf · uploaded 11 Apr 2023Source
- 9 Other15.pdf · uploaded 11 Apr 2023Source
- 10 Other15.pdf · uploaded 11 Apr 2023Source
- 11 Other15.pdf · uploaded 11 Apr 2023Source
- 12 OtherFlat no19.pdf · uploaded 11 Apr 2023Source
- 13 OtherFlat no19.pdf · uploaded 11 Apr 2023Source
- 14 OtherFlat no19.pdf · uploaded 11 Apr 2023Source
- 15 OtherFlat no19.pdf · uploaded 12 Apr 2023Source
- 16 OtherFLAT NO25.pdf · uploaded 12 Apr 2023Source
- 17 OtherFLAT NO25.pdf · uploaded 12 Apr 2023Source
Technical
Technical (Architect)
- DocumentARCHITECT'S CERTIFICATE .pdf · uploaded 9 Feb 2021Source
Technical (Engineer)
- DocumentENGINEER'S CERTIFICATE.pdf · uploaded 9 Feb 2021Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 30/304/2 at Nashik
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop34 units in all
- Address
- 30/304/2, Jatra Nandur Link Road, AdgaonPIN 422003
- Location
- 20.01322, 73.84652
- Land area for this project
- 733 sq m (7,893 sq ft)
- Permissible built-up area
- 2,421 sq m (26,054 sq ft)
- Sanctioned built-up area
- 2,421 sq m (26,054 sq ft)
- Designated bank account
- 213
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
30/304/2
Boundaries
- North
- Plot No 29 And 31
- South
- 24 Mtr Dp Road
- East
- Remaining Plot Of 304
- West
- 27
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking34 units
0 of 34 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 45.57 sq m · 491 sq ft | 6 | 0 |
| 2BHK | 67.37 sq m · 725 sq ft | 6 | 0 |
| 2BHK | 69.82 sq m · 752 sq ft | 12 | 0 |
| 2BHK | 70.63 sq m · 760 sq ft | 6 | 0 |
| Shop | 13.05 sq m · 140 sq ft | 2 | 0 |
| Shop | 13.72 sq m · 148 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals10
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ravi Amrutkar & Associates | — |
| Chartered accountant | prakash kalwani | — |
| Engineer | Sunil Patel | — |
| Other | Ashok V Landge | — |
| Other | Datta Peche | — |
| Other | Devraj Sharma | — |
| Other | Manik Banaji Chaudhari | — |
| Other | Pankaj Patil | — |
| Other | Satyam Sudhanshu Pandit | — |
| Other | Sikandarlal Yadav | — |
Source: MahaRERA project page. Contact details are not shown.