Deedo IDDP-NGP-ZBEXCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record.
Yerla, Nagpur 441305 · by Pink Stone Developers LLP
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 3 Jul 2026, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPP1190002601015
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PP1190002601015 | 3 Jul 2026 | 31 Dec 2027 | 30 Apr 2028 | Pink Stone Developers LLP | Project page |
Documents29
1 document held by Deedo, 28 filings listed on MahaRERA's project page
Finance
Show all 29 documentsShow fewer documents
Legal
- Declaration Form B213-5-A_compressed.pdf · uploaded 3 Dec 2025Source
- OthersLLP Agreement.pdf · uploaded 16 Dec 2025Source
- Others712.pdf · uploaded 16 Dec 2025Source
- OthersAnnexure vinod sir.pdf · uploaded 16 Dec 2025Source
- Othersannexure (disclsoure of int).pdf · uploaded 16 Dec 2025Source
- OthersSamilikaran Patra.pdf · uploaded 23 Mar 2026Source
- OthersCombined 712 certificate.pdf · uploaded 17 Jun 2026Source
- OthersBhumi Abhilekh.pdf · uploaded 17 Jun 2026Source
- Declaration Form BTitle Report SSD Bliss_edited.pdf · uploaded 17 Jun 2026Source
- Declaration Form BTitle Report SSD Bliss_edited.pdf · uploaded 17 Jun 2026Source
Planning Authority
Technical
- Documenttentative sanction plan (map).pdf · uploaded 27 Nov 2025Source
- DocumentN A ORDER SSD BLISS 42A.pdf · uploaded 27 Nov 2025Source
- DocumentANNEURE A- Declaration-Cum-Undertaking.pdf · uploaded 3 Dec 2025Source
- Othersarchitect's certificate.pdf · uploaded 16 Dec 2025Source
- Others7-12 combined.pdf · uploaded 17 Feb 2026Source
- OthersMail.pdf · uploaded 17 Jun 2026Source
- OthersYERLA 213 FINAL SANCTION PLAN HIGHLIGHTED.pdf · uploaded 17 Jun 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel KH NO 213/4/A/1/1 PH NO 3
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- KH.NO.213/4/A/1/1, 213/4/B, 213/5/A/1, P.H.NO.3 Mouza-YerlaPIN 441305
- Village
- Yerla, Nagpur (Rural) taluka
- Location
- 21.20804, 78.96270
- Land area for this project
- 36,910 sq m (3,97,294 sq ft)
- Permissible built-up area
- 0 sq m (0 sq ft)
- Sanctioned built-up area
- 0 sq m (0 sq ft)
- Recreational open space
- 5,475 sq m (58,932 sq ft)
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
city_survey_gut_no KH NO 213/4/A/1/1 final_plot_no - mauje YERLA road_street - society -
Boundaries
- North
- Nagpur Katol Road
- South
- 18.00 Mtr. Wide D. P. Road
- East
- 18.00 Mtr. Wide D. P. Road
- West
- Land Bearing Kh. No. 213/3/3
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pavan Raviprasad Gupta | — |
| Chartered accountant | Saroj Vidhani | — |
| Engineer | Gourav Pratap Bajaj | — |
Source: MahaRERA project page. Contact details are not shown.