Skip to content
Residential / Group Housing · 4 buildings · 160 unitsRERA P50500023240 +2

Leverage Greenwoods Harmony

Its promised completion date, Mar 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 98% of its units are booked.

Pipla, Nagpur 440034 · Promoter: Leverage Spaces LLP

Delivery1 yr 7 mo past duePromised Mar 2025 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales98% booked157 of 160 units · as the promoter reported to MahaRERA
Leverage Greenwoods Harmony project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Mar 2025, has passed and MahaRERA does not show it completed

  • P50500023240Registered 6 Dec 2019, completion promised 30 Mar 2024, and still not shown completed today.
  • P50500025134Registered 18 Mar 2020, completion promised 30 Mar 2025, and still not shown completed today.
  • P50500026781Registered 25 Oct 2020, completion promised 30 Mar 2025, and still not shown completed today.

No extension certificate on record.

3 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations3
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P505000232406 Dec 201930 Mar 202430 Mar 2024Leverage Spaces LLPProject page
P5050002513418 Mar 202030 Mar 202530 Mar 2025Leverage Spaces LLPProject page
P5050002678125 Oct 202030 Mar 202530 Mar 2025Leverage Spaces LLPProject page
Documents192

70 documents held by Deedo, 122 filings listed on MahaRERA's project page

Registration certificate (3)

  • Registration certificateP50500023240 · 8 Sep 2021ViewSource
  • Registration certificateP50500025134 · 8 Sep 2021ViewSource
  • Registration certificateP50500026781 · 8 Sep 2021ViewSource

Other (6)

  • OtherP50500025134 · Date not statedView
  • OtherP50500026781 · Date not statedView
  • OtherP50500023240 · Date not statedView
  • OtherP50500025134 · Date not statedView
  • OtherP50500025134 · Date not statedView
Show all 192 documentsShow fewer documents

Other (6)

  • OtherP50500025134 · Date not statedView

Building plan (26)

  • Building planP50500023240 · Date not statedView
  • Building planP50500025134 · Date not statedView
  • Building planP50500025134 · Date not statedView
  • Building planP50500023240 · Date not statedView
  • Building planP50500023240 · Date not statedView
  • Building planP50500025134 · Date not statedView
  • Building planP50500023240 · Date not statedView
  • Building planP50500025134 · Date not statedView
  • Building planP50500025134 · Date not statedView
  • Building planP50500023240 · Date not statedView
  • Building planP50500023240 · Date not statedView
  • Building planP50500025134 · Date not statedView
  • Building planP50500023240 · Date not statedView
  • Building planP50500025134 · Date not statedView
  • Building planP50500025134 · Date not statedView
  • Building planP50500023240 · Date not statedView
  • Building planP50500026781 · Date not statedView
  • Building planP50500026781 · Date not statedView
  • Building planP50500026781 · Date not statedView
  • Building planP50500026781 · Date not statedView
  • Building planP50500026781 · Date not statedView
  • Building planP50500026781 · Date not statedView
  • Building planP50500026781 · Date not statedView
  • Building planP50500026781 · Date not statedView
  • Building planP50500026781 · Date not statedView
  • Building planP50500026781 · Date not statedView

Commencement certificate (3)

  • Commencement certificateP50500025134 · Date not statedView
  • Commencement certificateP50500023240 · Date not statedView
  • Commencement certificateP50500026781 · Date not statedView

Form B (3)

  • Form BP50500023240 · Date not statedView
  • Form BP50500025134 · Date not statedView
  • Form BP50500026781 · Date not statedView

Layout plan (9)

  • Layout planP50500023240 · Date not statedView
  • Layout planP50500025134 · Date not statedView
  • Layout planP50500026781 · Date not statedView
  • Layout planP50500025134 · Date not statedView
  • Layout planP50500025134 · Date not statedView
  • Layout planP50500025134 · Date not statedView
  • Layout planP50500026781 · Date not statedView
  • Layout planP50500026781 · Date not statedView
  • Layout planP50500026781 · Date not statedView

Form 1 (11)

  • Form 1P50500023240 · Date not statedView
  • Form 1P50500025134 · Date not statedView
  • Form 1P50500025134 · Date not statedView
  • Form 1P50500025134 · Date not statedView
  • Form 1P50500025134 · Date not statedView
  • Form 1P50500025134 · Date not statedView
  • Form 1P50500026781 · Date not statedView
  • Form 1P50500026781 · Date not statedView
  • Form 1P50500026781 · Date not statedView
  • Form 1P50500026781 · Date not statedView
  • Form 1P50500026781 · Date not statedView

Form 2 (3)

  • Form 2P50500023240 · Date not statedView
  • Form 2P50500026781 · Date not statedView
  • Form 2P50500025134 · Date not statedView

Title report (4)

  • Title reportP50500023240 · Date not statedView
  • Title reportP50500025134 · Date not statedView
  • Title reportP50500023240 · Date not statedView
  • Title reportP50500026781 · Date not statedView

Encumbrance details (2)

  • Encumbrance detailsP50500025134 · Date not statedView
  • Encumbrance detailsP50500025134 · Date not statedView

Legal

  • Declaration Form BP50500023240 · Form B.pdf · uploaded 4 Nov 2019View
  • Legal Title reportP50500023240 · Title Search Report.pdf · uploaded 4 Nov 2019View
  • Legal Title reportP50500023240 · New Title Search Report.pdf · uploaded 13 Nov 2019View
  • Legal Title reportP50500025134 · New Title Search Report.pdf · uploaded 3 Mar 2020View
  • Declaration Form BP50500025134 · Form B.pdf · uploaded 3 Mar 2020View
  • Legal Title reportP50500026781 · Title Verification Report.pdf · uploaded 21 Oct 2020View
  • Declaration Form BP50500026781 · Form B - Affidavit cum Declaration.pdf · uploaded 21 Oct 2020View
  • OtherP50500023240 · MOU.pdf · uploaded 24 Mar 2022View
  • OtherP50500025134 · MOU.pdf · uploaded 24 Mar 2022View
  • OtherP50500026781 · MOU.pdf · uploaded 24 Mar 2022View

Migrated

  • 1 PAN CardP50500023240 · Pan Card.pdf · uploaded 4 Nov 2019Source
  • 1 Copy of the legal title reportP50500023240 · Title Search Report.pdf · uploaded 4 Nov 2019View
  • 1 Details of encumbrancesP50500023240 · Non - Encumbrance Certificate.pdf · uploaded 4 Nov 2019Source
  • 1 Copy of Layout Approval (in case of layout)P50500023240 · Layout Map.pdf · uploaded 4 Nov 2019Source
  • 1 Building Plan Approval / NA Order for plotted developmentP50500023240 · Map 1.pdf · uploaded 4 Nov 2019View
  • 2 Building Plan Approval / NA Order for plotted developmentP50500023240 · Map 2.pdf · uploaded 4 Nov 2019View
  • 3 Building Plan Approval / NA Order for plotted developmentP50500023240 · Map 3.pdf · uploaded 4 Nov 2019View
  • 4 Building Plan Approval / NA Order for plotted developmentP50500023240 · Map 4.pdf · uploaded 4 Nov 2019View
  • 5 Building Plan Approval / NA Order for plotted developmentP50500023240 · Map 5.pdf · uploaded 4 Nov 2019View
  • 6 Building Plan Approval / NA Order for plotted developmentP50500023240 · Map 6.pdf · uploaded 4 Nov 2019View
  • 7 Building Plan Approval / NA Order for plotted developmentP50500023240 · Map 7.pdf · uploaded 4 Nov 2019View
  • 8 Building Plan Approval / NA Order for plotted developmentP50500023240 · Map 8.pdf · uploaded 4 Nov 2019View
  • 1 Commencement Certificates / NA Order for plotted developmentP50500023240 · Permit-compressed.pdf · uploaded 4 Nov 2019View
  • 1 Declaration in FORM BP50500023240 · Form B.pdf · uploaded 4 Nov 2019View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500023240 · Architect Certificate RERA.pdf · uploaded 4 Nov 2019View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500023240 · Engineer Certificate.pdf · uploaded 4 Nov 2019View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500023240 · CA Certificate.pdf · uploaded 4 Nov 2019Source
  • 1 Proforma of Allotment letterP50500023240 · Agreement to Sale.pdf · uploaded 4 Nov 2019Source
  • 2 Proforma of Allotment letterP50500023240 · Allotment Letter.pdf · uploaded 4 Nov 2019Source
  • 2 Copy of the legal title reportP50500023240 · New Title Search Report.pdf · uploaded 13 Nov 2019View
  • 2 Details of encumbrancesP50500023240 · New Non Encumbrance Certificate.pdf · uploaded 13 Nov 2019Source
  • 1 PAN CardP50500025134 · Pan Card.pdf · uploaded 3 Mar 2020View
  • 1 Copy of the legal title reportP50500025134 · New Title Search Report.pdf · uploaded 3 Mar 2020View
  • 1 Details of encumbrancesP50500025134 · Non Encumbrance Certificate.pdf · uploaded 3 Mar 2020View
  • 1 Copy of Layout Approval (in case of layout)P50500025134 · Layout Map.pdf · uploaded 3 Mar 2020View
  • 1 Building Plan Approval / NA Order for plotted developmentP50500025134 · Sanction Map 1.pdf · uploaded 3 Mar 2020View
  • 2 Building Plan Approval / NA Order for plotted developmentP50500025134 · Sanction Map 2.pdf · uploaded 3 Mar 2020View
  • 3 Building Plan Approval / NA Order for plotted developmentP50500025134 · Sanction Map 3.pdf · uploaded 3 Mar 2020View
  • 4 Building Plan Approval / NA Order for plotted developmentP50500025134 · Sanction Map 4.pdf · uploaded 3 Mar 2020View
  • 5 Building Plan Approval / NA Order for plotted developmentP50500025134 · Sanction Map 5.pdf · uploaded 3 Mar 2020View
  • 6 Building Plan Approval / NA Order for plotted developmentP50500025134 · Sanction Map 6.pdf · uploaded 3 Mar 2020View
  • 7 Building Plan Approval / NA Order for plotted developmentP50500025134 · Sanction Map 7.pdf · uploaded 3 Mar 2020View
  • 8 Building Plan Approval / NA Order for plotted developmentP50500025134 · Sanction Map 8.pdf · uploaded 3 Mar 2020View
  • 1 Commencement Certificates / NA Order for plotted developmentP50500025134 · Building Permit.pdf · uploaded 3 Mar 2020View
  • 1 Declaration in FORM BP50500025134 · Form B.pdf · uploaded 3 Mar 2020View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500025134 · Architect Certificate.pdf · uploaded 3 Mar 2020View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500025134 · Engineer Certificate.pdf · uploaded 3 Mar 2020View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500025134 · CA Certificate.pdf · uploaded 3 Mar 2020View
  • 1 Proforma of Allotment letterP50500025134 · Sample Agreement.pdf · uploaded 3 Mar 2020View
  • 2 Proforma of Allotment letterP50500025134 · Allotment Letter.pdf · uploaded 3 Mar 2020View
  • 3 Details of encumbrancesP50500023240 · Encumbrance certificate.pdf · uploaded 20 Jul 2020Source
  • 1 PAN CardP50500026781 · Pan Card.pdf · uploaded 21 Oct 2020Source
  • 1 Copy of the legal title reportP50500026781 · Title Verification Report.pdf · uploaded 21 Oct 2020View
  • 1 Details of encumbrancesP50500026781 · Encumbrance Certificate.pdf · uploaded 21 Oct 2020Source
  • 1 Copy of Layout Approval (in case of layout)P50500026781 · Layout Map.pdf · uploaded 21 Oct 2020View
  • 1 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 1.pdf · uploaded 21 Oct 2020View
  • 2 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 2.pdf · uploaded 21 Oct 2020View
  • 3 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 3.pdf · uploaded 21 Oct 2020View
  • 4 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 4.pdf · uploaded 21 Oct 2020View
  • 5 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 5.pdf · uploaded 21 Oct 2020View
  • 6 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 6.pdf · uploaded 21 Oct 2020View
  • 7 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 7.pdf · uploaded 21 Oct 2020View
  • 8 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 8.pdf · uploaded 21 Oct 2020View
  • 9 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 9.pdf · uploaded 21 Oct 2020View
  • 10 Building Plan Approval / NA Order for plotted developmentP50500026781 · Page no 10.pdf · uploaded 21 Oct 2020View
  • 1 Commencement Certificates / NA Order for plotted developmentP50500026781 · Sanction Permit.pdf · uploaded 21 Oct 2020View
  • 1 Declaration in FORM BP50500026781 · Form B - Affidavit cum Declaration.pdf · uploaded 21 Oct 2020View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500026781 · Architect Certificate.pdf · uploaded 21 Oct 2020View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500026781 · Engineer's Certificate.pdf · uploaded 21 Oct 2020View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P50500026781 · Form 3 Leverage Spaces LLP (1).pdf · uploaded 21 Oct 2020View
  • 1 Proforma of Allotment letterP50500026781 · Allotment Letter.pdf · uploaded 21 Oct 2020View
  • 2 Proforma of Allotment letterP50500026781 · Agreement.pdf · uploaded 21 Oct 2020View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500023240 · Wing-B and C_compressed.pdf · uploaded 25 Aug 2021View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500025134 · Wing-A_compressed (1).pdf · uploaded 25 Aug 2021View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P50500026781 · Wing-D_compressed.pdf · uploaded 25 Aug 2021View
  • 1 OtherP50500023240 · MOU.pdf · uploaded 24 Mar 2022View
  • 1 OtherP50500025134 · MOU.pdf · uploaded 24 Mar 2022View
  • 1 OtherP50500026781 · MOU.pdf · uploaded 24 Mar 2022View
  • 1 b Details of encumbrances concerned to LegalP50500025134 · PHOTO-2022-07-01-14-41-44.pdf · uploaded 1 Jul 2022View
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP50500023240 · Ocupency Certificate.pdf · uploaded 12 Dec 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500025134 · Engineer's Certificate-Spaces.pdf · uploaded 9 Aug 2023View
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P50500026781 · Engineer's Certificate-Spaces.pdf · uploaded 9 Aug 2023View
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP50500025134 · OC WING A.pdf · uploaded 15 Dec 2023View
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP50500026781 · OC WING D.pdf · uploaded 15 Dec 2023View
  • 1 Architect’s Certificate on Completion of Project (Form 4)P50500026781 · FORM 4 Wing D.pdf · uploaded 21 Dec 2023View
  • 3 Architect’s Certificate on Completion of Project (Form 4)P50500023240 · FORM 4 B AND C.pdf · uploaded 20 Jul 2024Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)P50500025134 · FORM 4 Wing A.pdf · uploaded 20 Jul 2024View

Technical

  • DocumentP50500023240 · Layout Map.pdf · uploaded 4 Nov 2019Source
  • DocumentP50500023240 · Map 1.pdf · uploaded 4 Nov 2019View
  • DocumentP50500023240 · Map 2.pdf · uploaded 4 Nov 2019View
  • DocumentP50500023240 · Map 3.pdf · uploaded 4 Nov 2019View
  • DocumentP50500023240 · Map 4.pdf · uploaded 4 Nov 2019View
  • DocumentP50500023240 · Map 5.pdf · uploaded 4 Nov 2019View
  • DocumentP50500023240 · Map 6.pdf · uploaded 4 Nov 2019View
  • DocumentP50500023240 · Map 7.pdf · uploaded 4 Nov 2019View
  • DocumentP50500023240 · Map 8.pdf · uploaded 4 Nov 2019View
  • DocumentP50500025134 · Layout Map.pdf · uploaded 3 Mar 2020View
  • DocumentP50500025134 · Sanction Map 1.pdf · uploaded 3 Mar 2020View
  • DocumentP50500025134 · Sanction Map 2.pdf · uploaded 3 Mar 2020View
  • DocumentP50500025134 · Sanction Map 3.pdf · uploaded 3 Mar 2020View
  • DocumentP50500025134 · Sanction Map 4.pdf · uploaded 3 Mar 2020View
  • DocumentP50500025134 · Sanction Map 5.pdf · uploaded 3 Mar 2020View
  • DocumentP50500025134 · Sanction Map 6.pdf · uploaded 3 Mar 2020View
  • DocumentP50500025134 · Sanction Map 7.pdf · uploaded 3 Mar 2020View
  • DocumentP50500025134 · Sanction Map 8.pdf · uploaded 3 Mar 2020View
  • DocumentP50500026781 · Page no 1.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Page no 2.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Page no 3.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Page no 4.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Page no 5.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Page no 6.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Page no 7.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Page no 8.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Page no 9.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Page no 10.pdf · uploaded 21 Oct 2020View
  • DocumentP50500026781 · Layout Map.pdf · uploaded 21 Oct 2020View

Technical (Architect)

  • DocumentP50500023240 · Wing-B and C_compressed.pdf · uploaded 25 Aug 2021View
  • DocumentP50500025134 · Wing-A_compressed (1).pdf · uploaded 25 Aug 2021View
  • DocumentP50500026781 · Wing-D_compressed.pdf · uploaded 25 Aug 2021View

Technical (Engineer)

  • DocumentP50500023240 · Engineer Certificate.pdf · uploaded 4 Nov 2019View
  • DocumentP50500025134 · Engineer's Certificate-Spaces.pdf · uploaded 9 Aug 2023View
  • DocumentP50500026781 · Engineer's Certificate-Spaces.pdf · uploaded 9 Aug 2023View

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsKH NO 152/3, PLOT NO 1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
3
Unit types
2BHK, 3BHK160 units in all
Address
Kh No 152/3, Plot No 1, Besa Pipla Road, PiplaPIN 440034
Village
Pipla, Nagpur (Rural) taluka
Designated bank account
76
Developed in phases
Yes
Also registered as
Leverage Greenwoods - Harmony, Wing - A, Leverage Greenwoods Harmony Wing D

Survey, CTS, gat or plot numbers

KH NO 152/3PLOT NO 1

Boundaries

North
Kh No 152
South
12 Mtr Wide Road
East
Kh No 152
West
Kh No 153

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking160 units

157 of 160 units booked (98%), as the promoter reported to MahaRERA

2BHK · 81 units3BHK · 79 units
RERABuildingTypeCarpet areaUnitsBooked
P50500025134Wing A2BHK63.42 sq m · 683 sq ft1616
P50500025134Wing A2BHK63.46 sq m · 683 sq ft2020
P50500025134Wing A2BHK63.98 sq m · 689 sq ft44
P50500023240Wing B2BHK63.42 sq m · 683 sq ft1616
P50500023240Wing B2BHK63.46 sq m · 683 sq ft2020
P50500023240Wing B2BHK63.98 sq m · 689 sq ft44
P50500023240Wing C3BHK75.66 sq m · 814 sq ft1818
P50500023240Wing C3BHK76.21 sq m · 820 sq ft22
Show all 19 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P50500023240Wing C3BHK77.24 sq m · 831 sq ft99
P50500023240Wing C3BHK77.72 sq m · 837 sq ft99
P50500023240Wing C3BHK77.75 sq m · 837 sq ft11
P50500023240Wing C3BHK78.66 sq m · 847 sq ft11
P50500026781Wing D2BHK58.19 sq m · 626 sq ft11
P50500026781Wing D3BHK75.65 sq m · 814 sq ft109
P50500026781Wing D3BHK75.66 sq m · 814 sq ft97
P50500026781Wing D3BHK76.21 sq m · 820 sq ft22
P50500026781Wing D3BHK77.24 sq m · 831 sq ft88
P50500026781Wing D3BHK77.25 sq m · 832 sq ft99
P50500026781Wing D3BHK77.79 sq m · 837 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals12

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectPrashant Baliram Satpute—P50500025134
ArchitectPrashant Baliram Satpute—P50500023240
ArchitectPrashant Baliram Satpute—P50500026781
Chartered accountantVinod Hassani—P50500023240
Chartered accountantVinod Hassani—P50500025134
Chartered accountantVinod Hassani—P50500026781
EngineerP S Patankar—P50500025134
EngineerP S Patankar—P50500026781
Show all 12 professionalsShow fewer professionals
RoleNameRegistration no.RERA
EngineerSanjay Bhutani—P50500023240
OtherBabubhai Laxmanbhai Pansheriya—P50500023240
Registered real estate agentJyoti Ranjan Pani—P50500023240
Registered real estate agentJyoti Ranjan Pani—P50500025134

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology