RERA projects in Kapsi Bk

2 projects under 2 MahaRERA registrations, registered 2022–2023. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
0Completion still due2 past their completion date
4 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20221
20231

Projects in Kapsi Bk

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mangalam-Phase IIMangalamP505000491561 Feb 202331 Mar 202431 Mar 2024Promised date passed0
MangalamMangalamP5050003491628 Apr 202231 Mar 202631 Jul 2026Extended 4 mo0

Other localities in Kamptee

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Mangalam2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology