Polaris
Deedo IDDP-NGP-S34YMahaRERA shows it completed, after its date was pushed back 1 year and 10 months; no MahaRERA orders on record; 46% of its units are booked.
Hingna, Nagpur 441110 · by Saraswa Infra, Saraswa Infra
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 1 year and 10 months
- This projectRegistered 20 Apr 2022, completion promised 2 Nov 2022, revised to 30 Sep 2024.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP50500034699
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500034699 | 20 Apr 2022 | 2 Nov 2022 | 30 Sep 2024 | Saraswa Infra | Project page |
Documents88
40 documents held by Deedo, 48 filings listed on MahaRERA's project page
Show all 88 documentsShow fewer documents
Other (11)
Commencement certificate (4)
Form 1 (6)
Allotment letter
- Allotment letterDate not statedView
Encumbrance details (4)
Layout plan (7)
Form B
- Form BDate not statedView
Legal
Migrated
- 1 PAN CardPan Saraswa-converted.pdf · uploaded 4 Nov 2021View
- 1 Details of encumbrancesec certificate.pdf · uploaded 4 Nov 2021View
- 1 Building Plan Approval / NA Order for plotted developmentFinal Map.pdf · uploaded 4 Nov 2021View
- 1 Declaration in FORM BAffidavit cum Declaration.pdf · uploaded 8 Nov 2021View
- 1 Copy of the legal title reportTitle Report.pdf · uploaded 20 Nov 2021View
- 2 Copy of the legal title reportChallan Copy.pdf · uploaded 20 Nov 2021View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Cert Form 3.pdf · uploaded 20 Nov 2021View
- 1 Proforma of Allotment letterAllotment Letter Format.pdf · uploaded 20 Nov 2021View
- 1 CERSAI detailsCERSAI Search Report.pdf · uploaded 30 Nov 2021View
- 1 Declaration about Commencement CertificateDecleration Format D.pdf · uploaded 11 Dec 2021View
- 1 OtherFinal Name Change and Demand Copy.pdf · uploaded 5 Apr 2022View
- 1 Copy of Layout Approval (in case of layout)Final MAP.pdf · uploaded 9 Apr 2022View
- 1 Commencement Certificates / NA Order for plotted developmentCC saraswa.pdf · uploaded 9 Apr 2022View
- 2 Copy of Layout Approval (in case of layout)Saraswa Map.pdf · uploaded 11 May 2022View
- 3 Copy of Layout Approval (in case of layout)Saraswa Map.pdf · uploaded 11 May 2022View
- 2 Commencement Certificates / NA Order for plotted developmentOrder Copy.pdf · uploaded 11 May 2022View
- 2 a Details of encumbrances concerned to FinanceEncumbrances Legal.pdf · uploaded 12 Dec 2022View
- 3 a Details of encumbrances concerned to FinanceEncumbrances Finance.pdf · uploaded 12 Dec 2022View
- 1 b Details of encumbrances concerned to LegalEncumbrances Legal.pdf · uploaded 12 Dec 2022View
- 2 b Details of encumbrances concerned to LegalEncumbrances Finance.pdf · uploaded 12 Dec 2022View
- 4 Copy of Layout Approval (in case of layout)SI FInal Map (1).pdf · uploaded 12 Dec 2022View
- 2 Building Plan Approval / NA Order for plotted developmentWaghdara 46अ Orde Letter.pdf · uploaded 12 Dec 2022View
- 3 Commencement Certificates / NA Order for plotted developmentFinal CC Letter.pdf · uploaded 12 Dec 2022View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality Assurance 2A.pdf · uploaded 12 Dec 2022View
- 1 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 12 Dec 2022View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Annual Report Sarswa Infra.pdf · uploaded 12 Dec 2022View
- 1 Proforma of Agreement for saleSaraswa Infra Allotment Letter.pdf · uploaded 12 Dec 2022View
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Account Saraswa Infra.pdf · uploaded 12 Dec 2022View
- 1 Deviation Report with respect to Allotment letterDeviation Allotment Letter.pdf · uploaded 12 Dec 2022View
- 1 Deviation Report with respect to model copy of AgreementDeviation Saraswa Infra.pdf · uploaded 12 Dec 2022View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)RERA SI Not applicable.pdf · uploaded 23 Sep 2023View
- 1 Disclosure of Interest in Other Real Estate OrganizationsRERA SI Not applicable.pdf · uploaded 23 Sep 2023View
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentNMRDA - Saraswa Infra.pdf · uploaded 23 Sep 2023View
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION DRW SI 1.pdf · uploaded 23 Sep 2023View
- 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION DRW SI 2.pdf · uploaded 23 Sep 2023View
- 1 Other – TechnicalGrampanchayat.pdf · uploaded 23 Sep 2023View
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Completion.pdf · uploaded 27 Jan 2025View
Technical
- DocumentFinal Map.pdf · uploaded 4 Nov 2021View
- DocumentFinal MAP.pdf · uploaded 9 Apr 2022View
- DocumentSaraswa Map.pdf · uploaded 11 May 2022View
- DocumentSaraswa Map.pdf · uploaded 11 May 2022View
- DocumentSI FInal Map (1).pdf · uploaded 12 Dec 2022View
- DocumentWaghdara 46अ Orde Letter.pdf · uploaded 12 Dec 2022View
- Other – TechnicalGrampanchayat.pdf · uploaded 23 Sep 2023View
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 76B
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- 76B, Hingna Road, HingnaPIN 441110
- Village
- Wagdara (536054), Hingna taluka
- Location
- 21.07402, 78.97743
- Land area for this project
- 9,052 sq m (97,433 sq ft)
- Permissible built-up area
- 0 sq m (0 sq ft)
- Sanctioned built-up area
- 0 sq m (0 sq ft)
- Recreational open space
- 1,547 sq m (16,648 sq ft)
- Designated bank account
- 82
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
76B
Boundaries
- North
- Kh No 75
- South
- Kh No 65-2 and 65-3
- East
- Kh No 77
- West
- Kh No 75-1 and Kh No 75-B-2
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | G R Mundle and Associates | — |
| Chartered accountant | Prafulla Khiwasara | — |
| Engineer | G R Mundle and Associates | — |
| Engineer | V V Talwekar | — |
Source: MahaRERA project page. Contact details are not shown.