Skip to content
Residential / Group Housing · 1 building · 48 unitsRERA P50500045876

Sommet

Deedo IDDP-NGP-ZM7G

Its promised completion date, Nov 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.

Besa, Nagpur 440037 · by Inches Realities

Delivery2 yrs past duePromised Nov 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked48 of 48 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Nov 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 15 Jun 2022, completion promised 30 Nov 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP50500045876
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5050004587615 Jun 202230 Nov 202430 Nov 2024Inches RealitiesProject page
Documents105

48 documents held by Deedo, 57 filings listed on MahaRERA's project page

Registration certificate

Other (9)

  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
  • OtherDate not statedView
Show all 105 documentsShow fewer documents

Other (9)

  • OtherDate not statedView
  • OtherDate not statedView

Commencement certificate

  • Commencement certificateDate not statedView

Form 1 (24)

  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView
  • Form 1Date not statedView

Layout plan (7)

  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView
  • Layout planDate not statedView

Form 2 (3)

  • Form 2Date not statedView
  • Form 2Date not statedView
  • Form 2Date not statedView

Building plan

  • Building planDate not statedView

Title report

  • Title reportDate not statedView

Form B

  • Form BDate not statedView

Legal

  • Legal Title report14 Inches Realities_Search Report_compressed.pdf · uploaded 29 May 2022View
  • Declaration Form BAffidavit_compressed.pdf · uploaded 29 May 2022View

Migrated

  • 1 PAN Card2 Inches Pan Card.pdf · uploaded 27 May 2022View
  • 1 Copy of the legal title report14 Inches Realities_Search Report_compressed.pdf · uploaded 29 May 2022View
  • 1 Details of encumbrancesDeclartion.pdf · uploaded 29 May 2022Source
  • 1 Copy of Layout Approval (in case of layout)Layout Map.pdf · uploaded 29 May 2022View
  • 1 Building Plan Approval / NA Order for plotted developmentSanction Map.pdf · uploaded 29 May 2022View
  • 1 Commencement Certificates / NA Order for plotted developmentBuilding Permit.pdf · uploaded 29 May 2022View
  • 1 Declaration in FORM BAffidavit_compressed.pdf · uploaded 29 May 2022View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_compressed.pdf · uploaded 29 May 2022View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate_compressed.pdf · uploaded 29 May 2022View
  • 1 Declaration about Commencement CertificateCommencement letter.pdf · uploaded 9 Jun 2022Source
  • 1 CERSAI detailsDeclaration.pdf · uploaded 9 Jun 2022View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Rera Certificate Inches_compressed (1).pdf · uploaded 9 Jun 2022View
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 9 Jun 2022View
  • 2 Proforma of Allotment letterAgreement.pdf · uploaded 9 Jun 2022View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect Certificate (1)_compressed.pdf · uploaded 17 Aug 2022View
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate (1)_compressed.pdf · uploaded 17 Aug 2022View
  • 1 Disclosure of sold/ booked inventoryIMG_0001.pdf · uploaded 17 Aug 2022View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca certificate 12082022.pdf · uploaded 17 Aug 2022View
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architectcertificate30092022.pdf · uploaded 8 Feb 2023View
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)EngineerCertificate30092022.pdf · uploaded 8 Feb 2023View
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Inches Realities Rera30092022.pdf · uploaded 8 Feb 2023View
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate31122022_compressed.pdf · uploaded 14 Feb 2023View
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate31122022_compressed.pdf · uploaded 14 Feb 2023View
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Adobe Scan Feb 21, 2023_compressed.pdf · uploaded 21 Feb 2023View
  • 1 Proforma of Agreement for sale2 Proforma of Allotment letter.pdf · uploaded 21 Feb 2023View
  • 2 Disclosure of sold/ booked inventoryInventory March 2023.pdf · uploaded 27 Mar 2023View
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate (2).pdf · uploaded 30 Aug 2023View
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate (2).pdf · uploaded 30 Aug 2023View
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sommet Architect Certificate_30062023.pdf · uploaded 17 Nov 2023View
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sommet Architect Certificate_30092023.pdf · uploaded 17 Nov 2023View
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sommet Engineer Certificate_30062023.pdf · uploaded 17 Nov 2023View
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sommet Engineer Certificate_30092023.pdf · uploaded 17 Nov 2023View
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sommet_CA certificate_30062023.pdf · uploaded 24 Nov 2023View
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sommet_CA certificate_30092023.pdf · uploaded 24 Nov 2023View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)CA Certificate from-504032024.pdf · uploaded 4 Mar 2024View
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE 31122023.pdf · uploaded 5 Feb 2025View
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE 15022024.pdf · uploaded 5 Feb 2025View
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE 31122023.pdf · uploaded 5 Feb 2025View
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE 15022024.pdf · uploaded 5 Feb 2025View
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate.pdf · uploaded 5 Feb 2025View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineer Quaility Assurance 31032023.pdf · uploaded 5 Feb 2025View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Engineer Quaility Assurance 31032024.pdf · uploaded 5 Feb 2025View
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 SOMMET 31122023.pdf · uploaded 10 Feb 2025View
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 SOMMET_15022024.pdf · uploaded 10 Feb 2025View
  • 1 Disclosure of sold/ booked inventorySOMMET INVENTORY.pdf · uploaded 10 Feb 2025View
  • 2 Disclosure of sold/ booked inventorySOMMET INVENTORY.pdf · uploaded 10 Feb 2025View
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM-5 SOMMET.pdf · uploaded 10 Feb 2025View

Technical

  • DocumentLayout Map.pdf · uploaded 29 May 2022View
  • DocumentSanction Map.pdf · uploaded 29 May 2022View

Technical (Architect)

  • DocumentSommet Architect Certificate_30092023.pdf · uploaded 17 Nov 2023View
  • DocumentARCHITECT CERTIFICATE 31122023.pdf · uploaded 5 Feb 2025View
  • DocumentARCHITECT CERTIFICATE 15022024.pdf · uploaded 5 Feb 2025View

Technical (Engineer)

  • DocumentSommet Engineer Certificate_30092023.pdf · uploaded 17 Nov 2023View
  • DocumentENGINEER'S CERTIFICATE 31122023.pdf · uploaded 5 Feb 2025View
  • DocumentENGINEER'S CERTIFICATE 15022024.pdf · uploaded 5 Feb 2025View

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot No 1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK48 units in all
Address
Plot No 1, Besa Pipla Road, BesaPIN 440037
Village
Nagpur (M Corp.), Nagpur (Urban) taluka
Land area for this project
1,770 sq m (19,052 sq ft)
Permissible built-up area
5,575 sq m (60,007 sq ft)
Sanctioned built-up area
4,798 sq m (51,641 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No 1

Land as published on MahaRERA's project page

Plot No 1

Boundaries

North
Amenity Space
South
Open Space
East
Road
West
Kh No 50 Part

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking48 units

48 of 48 units booked (100%), as the promoter reported to MahaRERA

2BHK · 24 units3BHK · 24 units
TypeCarpet areaUnitsBooked
2BHK59.34 sq m · 639 sq ft2424
3BHK76.13 sq m · 819 sq ft2424

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectC D Giripunje—
Chartered accountantPushpak Gadewar—
EngineerC D Giripunje—

Source: MahaRERA project page. Contact details are not shown.