Sommet
Deedo IDDP-NGP-ZM7GIts promised completion date, Nov 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.
Besa, Nagpur 440037 · by Inches Realities
Buying a flat here?
See every deed registered on it.
Its promised completion date, Nov 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 15 Jun 2022, completion promised 30 Nov 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP50500045876
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P50500045876 | 15 Jun 2022 | 30 Nov 2024 | 30 Nov 2024 | Inches Realities | Project page |
Documents105
48 documents held by Deedo, 57 filings listed on MahaRERA's project page
Show all 105 documentsShow fewer documents
Commencement certificate
- Commencement certificateDate not statedView
Form 1 (24)
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
- Form 1Date not statedView
Layout plan (7)
Building plan
- Building planDate not statedView
Title report
- Title reportDate not statedView
Form B
- Form BDate not statedView
Legal
Migrated
- 1 PAN Card2 Inches Pan Card.pdf · uploaded 27 May 2022View
- 1 Copy of the legal title report14 Inches Realities_Search Report_compressed.pdf · uploaded 29 May 2022View
- 1 Details of encumbrancesDeclartion.pdf · uploaded 29 May 2022Source
- 1 Copy of Layout Approval (in case of layout)Layout Map.pdf · uploaded 29 May 2022View
- 1 Building Plan Approval / NA Order for plotted developmentSanction Map.pdf · uploaded 29 May 2022View
- 1 Commencement Certificates / NA Order for plotted developmentBuilding Permit.pdf · uploaded 29 May 2022View
- 1 Declaration in FORM BAffidavit_compressed.pdf · uploaded 29 May 2022View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_compressed.pdf · uploaded 29 May 2022View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate_compressed.pdf · uploaded 29 May 2022View
- 1 Declaration about Commencement CertificateCommencement letter.pdf · uploaded 9 Jun 2022Source
- 1 CERSAI detailsDeclaration.pdf · uploaded 9 Jun 2022View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Rera Certificate Inches_compressed (1).pdf · uploaded 9 Jun 2022View
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 9 Jun 2022View
- 2 Proforma of Allotment letterAgreement.pdf · uploaded 9 Jun 2022View
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect Certificate (1)_compressed.pdf · uploaded 17 Aug 2022View
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate (1)_compressed.pdf · uploaded 17 Aug 2022View
- 1 Disclosure of sold/ booked inventoryIMG_0001.pdf · uploaded 17 Aug 2022View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca certificate 12082022.pdf · uploaded 17 Aug 2022View
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architectcertificate30092022.pdf · uploaded 8 Feb 2023View
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)EngineerCertificate30092022.pdf · uploaded 8 Feb 2023View
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Inches Realities Rera30092022.pdf · uploaded 8 Feb 2023View
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate31122022_compressed.pdf · uploaded 14 Feb 2023View
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate31122022_compressed.pdf · uploaded 14 Feb 2023View
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Adobe Scan Feb 21, 2023_compressed.pdf · uploaded 21 Feb 2023View
- 1 Proforma of Agreement for sale2 Proforma of Allotment letter.pdf · uploaded 21 Feb 2023View
- 2 Disclosure of sold/ booked inventoryInventory March 2023.pdf · uploaded 27 Mar 2023View
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate (2).pdf · uploaded 30 Aug 2023View
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate (2).pdf · uploaded 30 Aug 2023View
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sommet Architect Certificate_30062023.pdf · uploaded 17 Nov 2023View
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sommet Architect Certificate_30092023.pdf · uploaded 17 Nov 2023View
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sommet Engineer Certificate_30062023.pdf · uploaded 17 Nov 2023View
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sommet Engineer Certificate_30092023.pdf · uploaded 17 Nov 2023View
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sommet_CA certificate_30062023.pdf · uploaded 24 Nov 2023View
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Sommet_CA certificate_30092023.pdf · uploaded 24 Nov 2023View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)CA Certificate from-504032024.pdf · uploaded 4 Mar 2024View
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE 31122023.pdf · uploaded 5 Feb 2025View
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE 15022024.pdf · uploaded 5 Feb 2025View
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE 31122023.pdf · uploaded 5 Feb 2025View
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE 15022024.pdf · uploaded 5 Feb 2025View
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate.pdf · uploaded 5 Feb 2025View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineer Quaility Assurance 31032023.pdf · uploaded 5 Feb 2025View
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Engineer Quaility Assurance 31032024.pdf · uploaded 5 Feb 2025View
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 SOMMET 31122023.pdf · uploaded 10 Feb 2025View
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 SOMMET_15022024.pdf · uploaded 10 Feb 2025View
- 1 Disclosure of sold/ booked inventorySOMMET INVENTORY.pdf · uploaded 10 Feb 2025View
- 2 Disclosure of sold/ booked inventorySOMMET INVENTORY.pdf · uploaded 10 Feb 2025View
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM-5 SOMMET.pdf · uploaded 10 Feb 2025View
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Plot No 1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK48 units in all
- Address
- Plot No 1, Besa Pipla Road, BesaPIN 440037
- Village
- Nagpur (M Corp.), Nagpur (Urban) taluka
- Location
- 21.08218, 79.10016
- Land area for this project
- 1,770 sq m (19,052 sq ft)
- Permissible built-up area
- 5,575 sq m (60,007 sq ft)
- Sanctioned built-up area
- 4,798 sq m (51,641 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No 1
Boundaries
- North
- Amenity Space
- South
- Open Space
- East
- Road
- West
- Kh No 50 Part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking48 units
48 of 48 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 59.34 sq m · 639 sq ft | 24 | 24 |
| 3BHK | 76.13 sq m · 819 sq ft | 24 | 24 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | C D Giripunje | — |
| Chartered accountant | Pushpak Gadewar | — |
| Engineer | C D Giripunje | — |
Source: MahaRERA project page. Contact details are not shown.