RERA projects in Nagpur (Urban)
1,096 projects under 1,110 MahaRERA registrations, registered 2017–2026. 38% have a completion date extended beyond the one promised.
Taluka
1,096RERA projects
1,110Registrationssome projects hold several
404Completion still due627 past their completion date, 95 marked completed
4 monthsMedian extension beyond promised date38% of registrations extended
85Regulatory caseson 56 projects
1,474Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 212 |
| 2018 | 77 |
| 2019 | 71 |
| 2020 | 60 |
| 2021 | 80 |
| 2022 | 151 |
| 2023 | 121 |
| 2024 | 104 |
| 2025 | 100 |
| 2026 | 55 |
Projects in Nagpur (Urban)
1,096 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vrindavan ApartmentsDelta Developers | PR1190002602478 | 19 Oct 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Vivek ApartmentR L Infraventure | PR1190002602318 | 15 Oct 2026 | 30 Sep 2030 | — | Not yet due | 0 |
| Shri Ameya ApartmentsK.k. Associates | PR1190002602310 | 14 Oct 2026 | 31 Aug 2031 | — | Not yet due | 0 |
| Mahendra SkywalkMahendra Redevelopers | PR1190002602274 | 13 Oct 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| Orbital WorldGudadhe Housing Developers and Promoters | PR1190002602239 | 9 Oct 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| SDPL Om ShubhlaxmiSandeep Dwellers Pvt. Ltd. | PR1190002602174 | 7 Oct 2026 | 31 Dec 2032 | 31 Dec 2032 | Not yet due | 0 |
| Royal ParkRai Udyog Globe Associates | PM1190002602124 | 5 Oct 2026 | 31 Mar 2031 | 31 Mar 2031 | Not yet due | 0 |
| SwastikKapil Nandkishore Nathani | PR1190002602147 | 5 Oct 2026 | 31 Mar 2030 | 31 Mar 2030 | Not yet due | 0 |
| DevotieAdhirath Ventures | PR1190002602043 | 24 Sep 2026 | 31 Jul 2031 | 31 Jul 2031 | Not yet due | 0 |
| Swapnapurtee - A Project by NMCSandeep Dwellers Pvt. Ltd. | PM1190002602047 | 24 Sep 2026 | 31 Jul 2030 | 31 Jul 2030 | Not yet due | 0 |
| Rai CrestRai Udyog Unity Mediscience Private Limited | PM1190002602027 | 23 Sep 2026 | 31 Mar 2030 | 31 Mar 2030 | Not yet due | 0 |
| Mahalaxmi Nagar 51 AnayaMahalaxmi Infraventures LLP | PP1190002602003 | 22 Sep 2026 | 4 Sep 2031 | 4 Sep 2031 | Not yet due | 0 |
| Ashoka Nagari-2Ashoka Realty Aop | PR1190002601834 | 8 Sep 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| The NestBlue Sparrow Properties Private Limited | PR1190002601829 | 8 Sep 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Pebbles 21Space Associates | PR1190002601688 | 27 Aug 2026 | 31 Mar 2029 | 31 Mar 2029 | Not yet due | 0 |
| Trident ParkShantanu Vinod Raut | PR1190002601652 | 25 Aug 2026 | 31 Jul 2029 | 31 Jul 2029 | Not yet due | 0 |
| Kamal NagariKamal Reality | PP1190002601538 | 13 Aug 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Devasheesh (18 Bless) ApartmentRaghukul Constructions Private Limited | PR1190002601502 | 11 Aug 2026 | 30 Apr 2032 | 30 Apr 2032 | Not yet due | 0 |
| Sarvadya CitySarvadya City | PP1190002601506 | 11 Aug 2026 | 31 Mar 2029 | 31 Mar 2029 | Not yet due | 0 |
| ProsperaEvergreen Estate | PP1190002601408 | 3 Aug 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Himalaya SignatureHimalaya Infraprojects (India) Private Limited | PR1190002601388 | 31 Jul 2026 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| One RiseMahalaxmi Infraprojects Private Limited | PR1190002601318 | 27 Jul 2026 | 14 Jul 2031 | 14 Nov 2031 | Extended 4 mo | 0 |
| Ayodhyaa CitySiddhivinayak Infraventures | PR1190002601224 | 20 Jul 2026 | 31 Dec 2036 | 30 Apr 2037 | Extended 4 mo | 0 |
| Sayalee ApartmentVaijnath Associates | PR1190002601108 | 9 Jul 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| The SarnathArg Infra Group | PR1190002601124 | 9 Jul 2026 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
Other talukas in Nagpur
Most active promoters
By projects registered here, as named on MahaRERA.
- Sandeep Dwellers Pvt. Ltd.16 projects
- Raghukul Constructions Private Limited10 projects
- Rai Udyog Limited10 projects
- MHADA (Nagpur Board)8 projects
- Nanis Buildcon Private Limited8 projects
- Delta Developers7 projects
- Kapil Nandkishor Nathani7 projects
- Kukreja Infrastructures7 projects
- Rachana construction Co. (Nagpur) Pvt. Ltd.7 projects
- Goldbricks Infrastructure Pvt Ltd6 projects
Data through20 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology