RERA projects in Karvir
586 projects under 595 MahaRERA registrations, registered 2017–2026. 42% have a completion date extended beyond the one promised.
Taluka
586RERA projects
595Registrationssome projects hold several
231Completion still due334 past their completion date
4 monthsMedian extension beyond promised date42% of registrations extended
10Regulatory caseson 10 projects
782Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 149 |
| 2018 | 30 |
| 2019 | 31 |
| 2020 | 34 |
| 2021 | 38 |
| 2022 | 73 |
| 2023 | 66 |
| 2024 | 52 |
| 2025 | 43 |
| 2026 | 49 |
Projects in Karvir
586 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Vasant VishwaChougule Hosmani Business Associates | PM1150002602450 | 19 Oct 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| LegacyRandive Builders And Developers | PM1150002602356 | 16 Oct 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Indrayani Co Op Housing Society Ltd.Swapnashilpa Housing LLP | PR1150002602325 | 15 Oct 2026 | 31 Mar 2032 | — | Not yet due | 0 |
| Mangalam ImperiaGaikwad Infrastructure Private Limited | PM1150002602081 | 1 Oct 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Time SquareGrey Bricks Reality | PM1150002602106 | 1 Oct 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Yashshri - Grand Lake VistaDestiny Builders | PM1150002602049 | 1 Oct 2026 | 28 Feb 2029 | 28 Feb 2029 | Not yet due | 0 |
| Shubhashish PrideVp Developers | PR1150002601977 | 21 Sep 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Dwarka Adreno Building BRandive Builders And Developers | PR1151012601927 | 15 Sep 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Aero CityPanjwani Developers | PR1150002601876 | 11 Sep 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Eminent Vision TowerAce Developers | PC1150002601889 | 11 Sep 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Radha RegencyVj And Space Realtors | PM1150002601892 | 11 Sep 2026 | 31 Dec 2031 | 31 Dec 2031 | Not yet due | 0 |
| Geeta BlossomsViva Deva Realty | PM1150002601738 | 1 Sep 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Sharada SquareSquare Angle Infrastructure | PM1150002601548 | 14 Aug 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Krystal TowerM/S SD Associates | PR1150002601510 | 11 Aug 2026 | 31 Dec 2030 | 31 Dec 2030 | Not yet due | 0 |
| Kalyani EnclaveMasute and Patil Builders | PR1150002601251 | 20 Jul 2026 | 1 May 2031 | 1 Sep 2031 | Extended 4 mo | 0 |
| Acharya Shree VidyasagarMasute Builders And Developers | PR1150002601102 | 8 Jul 2026 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Lm EmpireRajendra Lalasaheb Chavan | PM1150002600888 | 22 Jun 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Vrindavan HeightsMahalaxmi Buildcon | PR1150002600878 | 22 Jun 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Sharad Pride 41Pratik Infra | PR1150002600765 | 12 Jun 2026 | 30 Apr 2030 | 30 Aug 2030 | Extended 4 mo | 0 |
| Green CountyMirajkar Nichite Builders And Developers Private Limited | PR1150002600697 | 8 Jun 2026 | 31 Mar 2029 | 31 Mar 2029 | Not yet due | 0 |
| Samarth ResidencyS P Associates | PM1150002600615 | 1 Jun 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| The BalsamM/S Jotiraditya Builders | PR1150002600572 | 29 May 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Loknagari Karande MalaVikesh Abhaykumar Oswal | PR1150002600528 | 25 May 2026 | 31 Mar 2030 | 31 Jul 2030 | Extended 4 mo | 0 |
| Nimbalkar HeritageMorbale Infra Project Private Limited | PM1150002600491 | 21 May 2026 | 29 Dec 2029 | 29 Apr 2030 | Extended 4 mo | 0 |
| Vasant Villas ResidencyShree Datta Developers | PR1150002600487 | 21 May 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
Other talukas in Kolhapur
Most active promoters
By projects registered here, as named on MahaRERA.
- Deshpande Infra7 projects
- Shendre and Associates5 projects
- The Ideal Construction5 projects
- Bedekar Lifespaces LLP4 projects
- Mahabharat Construction Corporation4 projects
- M/S SD Associates4 projects
- Patki-Joshi Engineers and Contractors Pvt. Ltd.4 projects
- Randive Builders and Developers4 projects
- Raysons Constructions4 projects
- Tushar Mohanrao Khatavkar4 projects
Data through19 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology