Sovrano Tower-B
Deedo IDDP-MSB-R9K5Completion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 23% of its units are booked.
Oshiwara, Mumbai Suburban 400102 · by Lodha Developers Limited · 93% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2031
- This projectRegistered 11 Dec 2025, completion promised 31 Dec 2030, revised to 30 Apr 2031.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1180002501743
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1180002501743 | 11 Dec 2025 | 31 Dec 2030 | 30 Apr 2031 | Lodha Developers Limited | Project page |
Documents36
1 document held by Deedo, 35 filings listed on MahaRERA's project page
Finance
Legal
- OthersInterest Disclosure Lodha_removed.pdf · uploaded 5 Dec 2025Source
- Declaration Form BLegal Title Report.pdf · uploaded 5 Dec 2025Source
- Declaration Form BForm B -Sovrano Tower B.pdf · uploaded 5 Dec 2025Source
- Declaration Form B1_Conveyance Deed of Unichem Laboratories Limited and Lodha Developers Limited of Reg No19004-2025.pdf · uploaded 5 Dec 2025Source
- Declaration Form B2_Conveyance Deed of Unichem Laboratories Limited and Lodha Developers Limited of RegNo19004-2025.pdf · uploaded 5 Dec 2025Source
Show all 36 documentsShow fewer documents
Migrated
- Withdrawal Update Form 1Form-1 Sovarno B Dec-25.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 2Sovrano Tower B Form 2.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 3SOVRANO TOWER-B.pdf · uploaded 24 Jan 2026Source
- Withdrawal Update Form 1Form1 -Sovrano Tower-B - PR1180002501743-ok.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Sovrano B Form 2.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form- 3 regg- Sovarno B _F.pdf · uploaded 20 Apr 2026Source
- Form 2A (FY 2025-2026)Form 2A - Sovrano Tower-B - PR1180002501743.pdf · uploaded 29 Jun 2026Source
- Withdrawal Update Form 1Form1 - June 26.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 2Form 2 - June 26.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 3Form-3 - June 26.pdf · uploaded 17 Jul 2026Source
- Form 5 (FY 2025-2026)Sovrano Tower-B.pdf · uploaded 29 Sep 2026Source
Planning Authority
- DocumentMCGM_2504229_IOD_signed.pdf · uploaded 5 Dec 2025Source
- DocumentMCGM_2505757_FirstCC_signed.pdf · uploaded 5 Dec 2025Source
- DocumentMCGM_Provisional_Fire_NOC_Certificate.pdf · uploaded 5 Dec 2025Source
- DocumentMCGM_051701070215249599116.pdf · uploaded 5 Dec 2025Source
- DocumentMCGM_052103070215250547616.pdf · uploaded 5 Dec 2025Source
- DocumentMCGM_051803070215250547716.pdf · uploaded 5 Dec 2025Source
Technical
- Document20251203 For RERA Submission Wing No 4 - converted.pdf · uploaded 5 Dec 2025Source
- DocumentApproved IOD Wing -4 - converted.pdf · uploaded 5 Dec 2025Source
- DocumentOrder 50.pdf · uploaded 5 Dec 2025Source
- DocumentSheet 2 For FSI.pdf · uploaded 5 Dec 2025Source
- Othersland area declartion-Final tower B Final-ok.pdf · uploaded 10 Dec 2025Source
- Othersland area declartion-Final tower B -Final F.pdf · uploaded 10 Dec 2025Source
- Othersland area declartion-Final tower B Declaartion Final.pdf · uploaded 10 Dec 2025Source
- OthersLayout Highli - converted.pdf · uploaded 10 Dec 2025Source
- OthersAck Wing 4.pdf · uploaded 10 Dec 2025Source
Technical (Architect)
- DocumentForm1 - June 26.pdf · uploaded 17 Jul 2026Source
Technical (Engineer)
- DocumentForm 2 - June 26.pdf · uploaded 17 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 510
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —120 units in all
- Address
- Off -S.V Road, Jogeshwari WestPIN 400102
- Village
- Oshiwara, Andheri taluka
- Location
- 19.08352, 72.88345
- Land area for this project
- 1,112 sq m (11,970 sq ft)
- Approved layout area
- 13,392 sq m (1,44,150 sq ft)
- Permissible built-up area
- 13,495 sq m (1,45,256 sq ft)
- Sanctioned built-up area
- 13,495 sq m (1,45,256 sq ft)
- Recreational open space
- 1,348 sq m (14,510 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
510
Boundaries
- North
- CTS No 510(pt)
- South
- CTS No 510(pt)
- East
- 9.00 Mt Driveway
- West
- 9.00 Mt Driveway
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking120 units
120 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 120 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pradeep M Kamble | — |
| Architect | Vini Vilas Desai | — |
| Chartered accountant | Chirag Bharat Sarvaiya | — |
| Engineer | Mehul Kaivant Shah | — |
| Engineer | Tushar Hodbe | — |
Source: MahaRERA project page. Contact details are not shown.